  1. Slide 1: End-to-End Connection Process and Timeline Part II

    End-to-End Connection Process and Timeline Part II June 22, 2010 1

  2. Slide 2: Welcome

    Welcome We appreciate you taking the time today to join us as we deliver the next in a series of webinars to help you with various aspects of the connection process. Our aim is to provide regular, timely and meaningful information to help bring your projects to fruition. 2

  3. Slide 3: May 18th Webinar Reviewed

    May 18th Webinar Reviewed: 1. End to end connection process (Part I) which included: – High Level Process Steps to Connect – Connection Impact Assessment (CIA); including Distance Limitation impacts – Initial Cost Estimate – Connection Cost Estimate (CCE) – Connection Cost Agreement (CCA) 2. HST Imp

  4. Slide 4: Agenda

    Agenda 1. Review end to end connection process (Part II) – Engineering, Procurement and Construction – Cost Detail Report Example – Confirmation of Verification Evidence Report (C.O.V.E.R.) – Distribution Connection Agreement – Connection Requirements – Post Connection Activities – Total Approximate

  5. Slide 5: Date Definitions

    Date Definitions • Energization Date: – Date project becomes a load customer – Also known as Load Date • In-service Date: – Date project is approved to generate electricity onto the grid – Also known as Ready for Service Date • Commercial Operation Date (COD): – Recognized by the OPA as the contract

  6. Slide 6: Engineering, Procurement and Construction

    Engineering, Procurement and Construction • Project In-Service Date is negotiated at the project kick- off meeting – Kick-off meeting will take place no later than 45 days after the Connection Cost Agreement (CCA) has been executed 6

  7. Slide 7: Engineering, Procurement and Construction Kickoff Meeting

    Engineering, Procurement and Construction Kickoff Meeting • The assigned Project Manager (PM) and the proponent will: – Determine/Finalize In-Service date – Discuss scope of work – Discuss timelines for generator deliverables 7

  8. Slide 8: Engineering, Procurement and Construction Kickoff Meeting

    Engineering, Procurement and Construction Kickoff Meeting • The assigned Project Manager (PM) and the proponent will: – Review high-level project schedule (created by PM) – Answer any outstanding questions the proponent may have with regards to processes, deliverables and/or timelines – Discuss/prov

  9. Slide 9: Engineering, Procurement and Construction

    Engineering, Procurement and Construction • Proponent must submit information to the distributor for detailed design review and approval – Single Line Diagram (SLD) – Commissioning Schedule – Revenue metering configuration • Generation output must be measured net of station service as per FIT Standa

  10. Slide 10: Connection Requirements

    Connection Requirements • Generator provides the revenue metering single line diagram six months before generator is connected • Generator builds metering installation to Hydro One retail meter standards – If the metering installation is not located at the Point of Common Coupling (PCC), then the ge

  11. Slide 11: Connection Requirements

    Connection Requirements • Hydro One installs meter and tests the meter at generator’s cost • Generator must have all necessary Electrical Safety Authority (ESA) approvals in order to be connected • Generator returns executed Distribution Connection Agreement (DCA) with electronic funds transfer (EFT

  12. Slide 12: Connection Requirements

    Connection Requirements • Generator establishes COD via a declaration to both Hydro One and the OPA, per the FIT program rules • Force Majeure: – Generator must prove to the OPA that the distributor could not connect the project by the COD due to issues beyond the generator’s control in order to avo

  13. Slide 13: Cost Detail Report

    Cost Detail Report • Cost detail report is provided to the proponent by the Project Manager (PM) on a regular basis in order to determine and track the actual connection costs as of a specific date Report Includes: • Graph of planned/estimated cost against up-to-date actual costs incurred on the pro

  14. Slide 14: Cost Detail Report

    Cost Detail Report Report Includes (cont’d): • Details on status of the project: • Timing • Scope changes • Scheduling • Outstanding project issues • Report will be provided by the PM to the proponent on a monthly basis • The report that outlines costs for a certain month will be sent out by the end

  15. Slide 15: Cost Detail Report Example

    Cost Detail Report Example 15

  16. Slide 16: C.O.V.E.R. Confirmation of Verification Evidence Report

    C.O.V.E.R. Confirmation of Verification Evidence Report A process where generators test their own equipment • COVER must be completed 1 month prior to the in-service date • Generator submits to the distributor a protection philosophy for approval • COVER document ensures the protection proposed is a

  17. Slide 17: C.O.V.E.R.

    C.O.V.E.R. Confirmation of Verification Evidence Report • Generator completes the COVER template, which specifies: 9 What the generator will test? 9 The generator’s equipment • Hydro One approves the proposal • Testing is then performed by the generator 17

  18. Slide 18: C.O.V.E.R.

    C.O.V.E.R. Confirmation of Verification Evidence Report • COVER is completed by the generator and submitted to Hydro One • Hydro One approves the COVER 9 Approved by the assigned COVER Coordinator to the project 18

  19. Slide 19: Distribution Connection Agreement (DCA)

    Distribution Connection Agreement (DCA) • As per the Distribution System Code (DSC) a “Connection Agreement” is an agreement entered into between a distributor and a customer connected to its distribution system 19

  20. Slide 20: Distribution Connection Agreement (DCA)

    Distribution Connection Agreement (DCA) • DCA defines the conditions of the connection and obligations of the generator and Hydro One with respect to delivery of electricity to or from that connection – One-time event which must be completed before Hydro One connects the proposed facility – Must be

  21. Slide 21: Distribution Connection Agreement (DCA)

    Distribution Connection Agreement (DCA) • Outlines the technical and operating requirements • Documents asset ownership • Provides an outline of the roles and responsibilities of each party • Lists all the pertinent contact information for the generator and Hydro One (schedule F) 21

  22. Slide 22: Reconciliation of Project Connection Costs

    Reconciliation of Project Connection Costs • Occurs after the project has gone in-service and all relevant project costs have been posted to the project • Project Manager determines if there is a difference between the payments made by the generator and the actual connection cost 22

  23. Slide 23: Reconciliation of Project Connection Costs

    Reconciliation of Project Connection Costs • If there is a difference between the payments made by the generator and the actual connection costs then: – a refund is issued to the generator or – an invoice is sent to collect the remainder of the funds required to close the project • Completed within

  24. Slide 24: Post Connection Activities

    Post Connection Activities • OPA provides a letter of direction for Hydro One to: – Pay the generator at a specified contract price – Effective on a commercial operation date – For a specified contract term • The generator name on the OPA letter of direction must be exactly the same name as that on

  25. Slide 25: Post Connection Activities

    Post Connection Activities • Hydro One bills the generator for electricity withdrawn from the distribution system at OEB approved rates • Billing is issued on a billing cycle basis • Each billing cycle is approximately 30 days long but does not align with the calendar month 25

  26. Slide 26: Post Connection Activities

    Post Connection Activities • Hydro One will: – deposit the payment into the generator’s bank account – send a generation statement electronically to the generator • Hydro One: – pays the generator based on calendar month – issues payment 21 business days after the end of the calendar month 26

  27. Slide 27: Total Approximate Connection Time

    Total Approximate Connection Time 9 60 days: Proponent applies for CIA (120 days if multiple LDC’s involved) 9 6 months: Application for CCE, Submit Notice to Proceed to OPA, Application for CCA 9 8 – 12 months: Construction of Project 9 3 – 6 months: Reconciliation of project connection costs betwe

  28. Slide 28: Next Steps

    Next Steps • Economic Connection Test (ECT) – Starting August 3, 2010 – To be completed by the Ontario Power Authority – Is a process for prioritizing transmission expansion – The OPA will identify economically justifiable transmission expansion projects which are required to accommodate FIT program

  29. Slide 29: Update from last Webinar

    Update from last Webinar • Technical Working Group (TWG) on Feeder Distance Issues • Five industry associations were asked to send delegates: • CanWEA, CanSIA, APAO (Agri-Energy Producers Association of Ontario), OWA and OSEA • The Working Group has met five times since the beginning of April • Fina

  30. Slide 30: TWG on Feeder Distance Issues

    TWG on Feeder Distance Issues Structure of Final Report • 3 to 4 page Executive Summary • Table of Contents will include: – Introduction – Voltage Performance Criteria • Fundamental Nature of the Problem • Impact of distance and DG size – Power Distance Limitations – Potential Solutions – Conclusion

  31. Slide 31: TWG on Feeder Distance Issues

    TWG on Feeder Distance Issues Structure of Final Report (Cont’d) • Appendices: – will contain the relevant detailed submissions from the Working Group Members Timeline • Draft circulated to Members by June 24th • Feedback from members and edits due by July 5th • Final report ready for external distr

  32. Slide 32: Connection Impact Assessment (CIA) Turnaround Time

    Connection Impact Assessment (CIA) Turnaround Time • DSC requires a distributor provide an assessment of the impact of the proposed generation on the system within 60 days • 60 days starts once Hydro One deems the CIA application to be complete – not the same as the OPA scheduled CIA application win

  33. Slide 33: CIA Turnaround Time

    CIA Turnaround Time • An application is deemed complete once Hydro One verifies the CIA application package 1. has all required information included and 2. technically complete and accurate 33

  34. Slide 34: CIA Turnaround Time

    CIA Turnaround Time • A complete application package consists of the following: 3 Signed Form B • Stamped by a licensed Professional Engineer 3 Distribution Operating Map (DOM) 3 Single Line Diagram (SLD) • Stamped by a licensed Professional Engineer 3 Signed CIA Study Agreement 3 Correct CIA paymen

  35. Slide 35: CIA Turnaround Time

    CIA Turnaround Time Exceptions for Non-CAE project only: • A completed CIA application will be put on-hold if there is a “pending complete” application(s) from another generator(s) who: 1. Applied to the same distribution station and 2. Were allotted an earlier application window by the OPA 35

  36. Slide 36: CIA Turnaround Time – Same Station Applications

    CIA Turnaround Time – Same Station Applications SAMPLE TIMELINE* Project One Project Two Application window scheduled by the May 31 June 1 OPA – receive electronic package Up to 5 business days – Hydro One to June 7 – information June 8 – electronic package and advise proponent of application issues

  37. Slide 37: CIA Turnaround Time

    CIA Turnaround Time • If a project requires multiple Local Distribution Companies (LDC) to be involved Hydro One must – work in conjunction with the other involved LDC(s) – incorporate the assessment the LDC is required to produce into a combined CIA report for the project • Maximum CIA turnaround w

  38. Slide 38: Important Contact Information

    Important Contact Information Hydro One Web: www.HydroOne.com E-mail: DXGenerationConnections@HydroOne.com Phone: 1-877-447-4412 (Option #2) Ontario Power Authority Web: www.powerauthority.on.ca Phone: 1-888-387-3403 38

  39. Slide 39: Questions

    Next Webinar – Fall 2010 Questions 39