Poseidon Nickel Ltd

Poseidon Nickel — Diggers & Dealers Mining Forum 2015

36 slides from Poseidon Nickel's conference presentation, August 2015

  1. Slide 1: Australia’s New Nickel

    Australia’s New Nickel Diggers & Dealers Mining Forum David Singleton, MD & CEO August 2015

  2. Slide 2: Indonesian Ore Stocks in China are well down as predicted

    Indonesian Ore Stocks in China are well down as predicted Private & Confidential 2

  3. Slide 3: Philippines Ore exports up - but not much

    Philippines Ore exports up - but not much Private & Confidential 3

  4. Slide 4: Chinese NPI reducing as predicted albeit more slowly

    Chinese NPI reducing as predicted albeit more slowly Private & Confidential 4

  5. Slide 5: As a result Ferronickel and Refined Nickel imports up

    As a result Ferronickel and Refined Nickel imports up Private & Confidential 5

  6. Slide 6: Australia’s New Nickel

    Australia’s New Nickel Diggers & Dealers Mining Forum David Singleton, MD & CEO August 2015

  7. Slide 7: Projects within 300kms centred around Australia’s Major Nickel Region

    Projects within 300kms centred around Australia’s Major Nickel Region Private & Confidential 7

  8. Slide 8: 3 Production ready nickel projects in Western Australia

    3 Production ready nickel projects in Western Australia • Windarra Nickel Project • Black Swan Nickel Project • Lake Johnston Nickel Project Private & Confidential 88

  9. Slide 9: Windarra Nickel Project

    Windarra Nickel Project Commercial in Confidence 9

  10. Slide 10: Long section of Mt Windarra at mine closure

    Long section of Mt Windarra at mine closure Original Long Section Pre Drilling Mineralisation Private & Confidential 10

  11. Slide 11: Upper G Shoot Mineralisation

    Upper G Shoot Mineralisation Commercial in Confidence 11

  12. Slide 12: H Shoot Mineralisation

    H Shoot Mineralisation Private & Confidential 12

  13. Slide 13: C & G Deeps Mineralisation

    C & G Deeps Mineralisation Private & Confidential 13

  14. Slide 14: D Deeps Mineralisation

    D Deeps Mineralisation Private & Confidential 14

  15. Slide 15: F Shoot Mineralisation

    F Shoot Mineralisation Private & Confidential 15

  16. Slide 16: Windarra Nickel Project Discovery of Cerberus

    Windarra Nickel Project Discovery of Cerberus Commercial in Confidence 16

  17. Slide 17: Development of the Windarra Project

    Development of the Windarra Project Mt Windarra Cerberus Greenfields South Windarra Orebody Open Pit Private & Confidential 17

  18. Slide 18: Cerberus: Further Developments

    Cerberus: Further Developments Modelled Resource Positions Extensions With Limited to No Drill Testing Private & Confidential 18

  19. Slide 19: Mt Windarra - Operational Site

    Mt Windarra - Operational Site Private & Confidential 19

  20. Slide 20: Black Swan Nickel Project

    Black Swan Nickel Project Commercial in Confidence 20

  21. Slide 21: The Black Swan Process Plant and open pit resource bought from Norilsk

    The Black Swan Process Plant and open pit resource was bought by Poseidon from Norilsk in July 2014 Private & Confidential 21

  22. Slide 22: Black Swan pit showing smeltable reserves

    Black Swan pit showing smeltable reserves Ore for smeltable grade concentrate Private & Confidential 22

  23. Slide 23: Black Swan resources available for non-traditional uses

    Black Swan resources available for non-traditional uses Private & Confidential 23

  24. Slide 24: Lake Johnston Nickel Project Maggie Hayes

    Lake Johnston Nickel Project Maggie Hayes Commercial in Confidence 24

  25. Slide 25: Lake Johnston includes 2 mines, a concentrator and camp in operational ready condition

    Lake Johnston includes 2 mines, a concentrator and camp in operational ready condition Concentrator and Administration Emily Ann Mine Maggie Hays Mine Tailings Dam Windy Hill Camp Private & Confidential 25

  26. Slide 26: Maggie Hays - Increasing Life by over 3 times

    Maggie Hays - Increasing Life by over 3 times Suture Zone MINED North Shoot OUT SLC Remaining SLC Private & Confidential 26 26

  27. Slide 27: Maggie Hays initial resource extension targets

    Maggie Hays Initial resource extension targets Maggie Hays South Potential for Future North Shoot Production Western Zone Expansion Opportunity Opportunity Private & Confidential 27 27

  28. Slide 28: Lake Johnston Nickel Project Emily Ann

    Lake Johnston Nickel Project Emily Ann Commercial in Confidence 28

  29. Slide 29: Emily Ann was a 4% Ore Body truncated by Toolangi Fault

    Emily Ann was a 4% Ore Body truncated by Toolangi Fault Surface Decline Structurally Offset Targets Fault Movement=into page (westward) Fault Movement=out of page (eastward) Commercial in Confidence 29

  30. Slide 30: Electromagnetics support strong targets dislocated from the original ore body

    Electromagnetics support strong targets dislocated from the original ore body. Supporting Modelled DHEM Targets Private & Confidential 30

  31. Slide 31: EIS Grant will support drilling these targets

    EIS Grant will support drilling these targets. Planned Drill Holes Private & Confidential 31

  32. Slide 32: High Quality Process Plant

    High Quality Process Plant Processing capacity of 1.5m tonnes per annum 3 stage crushing circuit operating Grinding Mills operating Flotation Cells inspected Concentrate Filtration & Storage facilities tested Private & Confidential 32

  33. Slide 33: Windy Hill Camp

    Windy Hill Camp 277 Rooms available 180 required Private & Confidential 33

  34. Slide 34: Published Resources

    Poseidon has the second largest published nickel sulphide resource in Australia* 500 450 400 350 Published Resources (‘000 tonnes Nickel) 300 250 200 150 100 50 0 *Australian nickel sulphide producers and developers excluding BHP(B). Data compiled from Deutsche Bank report dated 28.07.14. Private &

  35. Slide 35: Summary

    Summary • Lake Johnston can be in production in 4 months • Definitive Feasibility Study completed • Fully permitted • Major contracts either signed or nearing signature • Offtake Contracts and working capital loans agreed subject to final contract • 8,000 tonnes in nickel concentrate • All in sustai

  36. Slide 36: Poseidon

    POSEIDON » | & ="