Slide 1: Advanced Post Combustion CO2 Capture Technology for Coal & Natural Gas Fired Power Plants
Crown Conference Centre, Melbourne, 22 - 23 June 2010 Policy, investment and partnership for government, technology and primary industries Mitsubishi Heavy Industries, Ltd. (MHI) Advanced Post Combustion CO2 Capture Technology for Coal & Natural Gas Fired Power Plants Ronald Mitchell Project Managem
Slide 2: Mitsubishi Heavy Industries, Ltd. Corporate Overview
Mitsubishi Heavy Industries, Ltd. Corporate Overview FY2008 Corporate Data • World leading engineering, construction & technology provider • “Global Fortune 500” company • Foundation July 7, 1884 • Paid-in Capital $2.85 Billion USD • Employees 64,000 (Consolidated basis) • Net Sales $32 Billion USD
Slide 3: Contents
Contents 1) MHI’s Commercial CO2 Capture Plant Experiences 2) CO2 Capture Process Improvements 3) Coal Fired Flue Gas CO2 Capture Demonstration 4) CO2 Capture Demonstration Projects & Partnerships Insert file path on the 'Header and Footer' menu 3
Slide 4: MHI's Commercial Flue Gas Experiences
Part 1 MHI’s Commercial Flue Gas CO2 Capture Plant Experiences Insert file path on the 'Header and Footer' menu 4
Slide 5: MHI - Commercial Flue Gas Experiences
MHI - Commercial Flue Gas CO2 Capture Plant Experiences World leading LARGE-SCALE post combustion CO2 capture (PCC) technology licensor CO2 Recovery (CDR) Plant – CO2 Recovery (CDR) Plant – IFFCO AonlaUnit (India) IFFCO Phulpur Unit (India) 1999 2005 2006 2006 2009 200 t/d Malaysia 330 t/d Japan 450
Slide 6: Map of MHI Commercial Sites
Map of MHI Commercial CO2 Capture Plant Sites 33 2006 India (Aonla) 44 2006 India (Phulpur) 450 t/d 450 t/d 88 2010 Pakistan 340 t/d 22 2005 Japan 330 t/d 77 2010 Bahrain 450 t/d 99 2011 Vietnam 240 t/d KEY Plants under operation 66 2009 Abu Dhabi 55 2009 India 400 t/d 450 t/d 11 1999 Malaysia 200 t
Slide 7: Natural Gas CO2 Recovery – Ready to go!!
Natural Gas CO2 Recovery – Ready to go!! Completed basic design for large single train PCC Plant Offering this plant on a commercial basis with guarantees Contract negotiation for several CCS & CO2-EOR commercial projects Gas Boiler Gas Turbine CO2 Capture Plant CO2 Capture & Compression Plant 3,000
Slide 8: Process Improvements
Part 2 Process Improvements Insert file path on the 'Header and Footer' menu 8
Slide 9: First Commercial Plant in Operation Utilizing MHI's Improved Regeneration Process
First Commercial Plant in Operation Utilizing MHI’s Improved Regeneration Process - Commercialised Owner : Fertil Abu Dhabi CO2 Recovery Capacity : 400 t/d Start Up : Dec. 2009 Performance Test : Completed Use of CO2 : Urea Production Process : Improved KM CDRTM Process Solvent : KS-1T
Slide 10: New Process Improvement Confirmed in Nanko Pilot Plant
New Process Improvement Confirmed in Nanko Pilot Plant Plant location : Nanko Power Station CO2 Recovery Capacity : 2 t/d Test Period : 2009 Process Features: - Increased CO2 loading by KS-1TM solvent - Reduces Stripper Top Temperature Process Performance: - Steam consumption 1.22 Ton Stea
Slide 11: Coal Fired Flue Gas CO2 Capture Demonstration
Part 3 Coal Fired Flue Gas CO2 Capture Demonstration Insert file path on the 'Header and Footer' menu 11
Slide 12: Coal Fired Flue Gas Considerations
Coal Fired Flue Gas Considerations Coal Fired Flue Gas Impurities depend on coal type and flue gas pre- treatment conditions. The following impurities have to be carefully treated before CO2 capture; zSO2, SO3 zNO2 zDust & hydrocarbons zOthers Accumulation and effects of coal fired flue gas im
Slide 13: MHI's Long Term 10 t/d CO2 Capture Demonstration Plant
MHI’s Long Term 10 t/d CO2 Capture Demonstration Plant Tests from a Commercial Coal Fired Boiler Plant Outline Solvent : KS-1TM solvent Capacity : 10 t/d Feed Gas : Coal Fired Boiler operation : 2006 - 2008 Location : Nagasaki, Japan NOTE* Project funding support from RITE (50%) and cooperation Inse
Slide 14: MHI's Long Term CO2 Capture Demonstration Test Coal Fired Boiler Results
MHI’s Long Term CO2 Capture Demonstration Test Coal Fired Boiler Results (1) Operational Achievement - 3 test campaigns over 3 years - long term stable operation period: 5,842 hrs (2) Operational Results (Availability 99%) - CO2 recovery efficiency: >90% - CO2 product purity: >99.9% (3) Heat Consump
Slide 15: Demonstration Projects & Partnerships
Part 4 CO2 Capture Plant Demonstration Projects & Partnerships Insert file path on the 'Header and Footer' menu 15
Slide 16: Southern Company Project
Southern Company CO2 Capture Plant Project Alabama, United States Location : Alabama Power, James M. Barry Electric Generating Plant Project Partners : Southern Company, MHI & EPRI Project Status : Commenced construction James M. Barry Electric Generating Plant Start Up : Q2 2011 Flue Gas Source : B
Slide 17: Southern Company Project Scope Schematic
Southern Company CO2 Capture Plant Project Scope Schematic Insert file path on the 'Header and Footer' menu 17
Slide 18: Southern Company Project Progress Photos
Southern Company CO2 Capture Plant Project Progress Photos Ground breaking Intermediate module Insert file path on the 'Header and Footer' menu 18 Status as of mid April, 2010
Slide 19: Kingsnorth Project
Kingsnorth CO2 Capture Plant Project England, United Kingdom Location : Newly built 2 x 800MW super critical unit in Kingsnorth, Kent Project Partners : E.ON UK, Foster Wheeler & MHI Project Status : Completed Pre-FEED Start Up : 2014* Flue Gas Source : Black Coal Fired Boiler CO2 Capacity : ~ 2 mil
Slide 20: Loy Yang PCC Project
Loy Yang PCC Project Victoria, Australia Location : Loy Yang A Power Station (LYAPS), Latrobe Valley, Victoria Project Partners : LYP, TRUenergy, WorleyParsons, MHI & Mitsubishi Corp. Project Status : Pre-feasibility & Scoping Study*1 Start Up : 2014*2 2,200 MW Loy Yang A Power Station Flue Gas Sour
Slide 21: Loy Yang PCC Project Partnerships
Loy Yang PCC Project Partnerships ONE TEAM, MULTIPLE STRENGTHS AND RESOURCES The Loy Yang PCC Project led by LYP & TRUenergy, which forms part of the Victorian Government’s CarbonNet proposal to the Federal Government CCS Flagships Program, will be jointly supported by WorleyParsons, Mitsubishi Heav
Slide 22: Loy Yang PCC Project Scope
Loy Yang PCC Project Scope Loy Yang A Power Station Plant Scope of ~1,000 tpd PCC Demo Plant Storage Scope Boiler ESP CO2 Geo-sequestration Utilities Solvent CO2 CO2 Pipeline Flue gas CO2 regeneration Compression & treatment Recovery CO2 Injection Dehydration Slipstream wells Duct Insert file path o
Slide 23: Loy Yang PCC Project Schedule
Loy Yang PCC Project Schedule Phase 1: Preliminary Scoping Study (completed) Phase 2: Pre-feasibility & Scoping Study with +/-25% cost estimate (7 months) Phase 3: FEED Study with +/-10% cost estimate and PDP (8 months) Phase 4: EPC (20-24 months) Phase 5: Demonstration Operation/Technical proving (
Slide 24: Loy Yang PCC Project Benefits & Goals
Loy Yang PCC Project Benefits & Goals The project will deliver benefits to the Victorian & Australian economy, industry and the environment by demonstrating integrated carbon capture for brown coal fired boilers, in a pre-commercial environment • Proving flue gas treatment processes prior to carbon
Slide 25: MHI's Roadmap to Commercialization for Coal Fired Boilers
MHI’s Roadmap to Commercialization for Coal Fired Boilers Next Step is to operate the process at large enough scale to ensure trouble free, long term & reliable operation leading to the provision of commercial guarantees PCC Demo AUS MHI’s Operating Experiences PCC Demo •Pilot plants (1-2 tpd) US •S
Slide 26: Final Words
Final Words FOR THE SUSTAINED LONG TERM USE OF FOSSIL FUELS FOR CLEANER, SMARTER POWER GENERATION… Mitsubishi Heavy Industries can deliver integrated, reliable post combustion CO2 capture solutions Insert file path on the 'Header and Footer' menu 26
Slide 27: Further Information