  1. Slide 1: Newcastle Gas Storage Facility

    Newcastle Gas Storage Facility Community Dialogue Group Meeting 5 14 March 2018

  2. Slide 2: Open and welcome

    Open and welcome 1 Previous minutes Business arising 4 NSW Generation Plan 2 Local Community Investment Update 5 Next meeting Close 3 Modification 3

  3. Slide 3: Previous minutes and business arising

    Previous minutes and business arising

  4. Slide 4: Local Community Investment Program funding recipients

    Following review of applications and further consideration by the CDG at our last meeting, we have determined that the following organisations will receive funding as part of the LCIP: 1. Native Animal Trust Fund - $5,000 2. Hunter Life Education - $5,000 3. Tanilba Bay & District Senior Citizens -

  5. Slide 5: Round 2 of the LCIP

    • Round 2 of the LCIP kicks off on 5 April 2018 and we will accept applications until 3 May 2018 This advertisement will appear on Thursday 29 March in the following newspapers: Port Stephens Examiner Bay News of the Area Raymond Terrace News of the Area • We will also look at using Facebook and Twi

  6. Slide 6: Modification 3 update and next steps

    Modification 3 Update and next steps

  7. Slide 7: Modification 3 approved

    On 27 February 2018, the Department of Planning and Environment (DP&E) approved the Newcastle Gas Storage Facility MOD 3 under Section 75W of the Environmental Planning and Assessment Act 1979. The modification includes constructing and operating a 4.5 kilometre low pressure liquid natural gas (LNG)

  8. Slide 8: Footer | Date (Format: X Month 2017)

    Footer | Date (Format: X Month 2017) 8

  9. Slide 9: Environment update

    Environment update

  10. Slide 10: Environmental monitoring

    • Offset Property annual monitoring and weed management • 6 monthly groundwater and surface water monitoring • Air emissions monitoring on H101 Footer | Date (Format: X Month 2017) 10

  11. Slide 11: NSW Generation Plan

    NSW Generation Plan

  12. Slide 12: Liddell replacement is AGL's preferred option

    Liddell replacement is AGL’s preferred option compared to the proposal to extend the life of Liddell Newcastle Gas Storage Facility Community Dialogue Group | 18 January 2018 12

  13. Slide 13: Stage 1 feasibility

    Stage 1 (feasibility during 2019 or earlier) Newcastle Gas Storage Facility Community Dialogue Group | 18 January 2018 13

  14. Slide 14: Feasibility of a gas peaker at the NGSF

    Feasibility of a gas peaker located at the NGSF or another suitable location in NSW Gas fired peaking/intermediate power stations will form part of the electricity market's response when old coal fired power stations are withdrawn from the market, playing an increasingly important role by providing

  15. Slide 15: Next meeting and close

    General Business Next meeting and close

  16. Slide 16: Contacts

    Lisa Andrews Marina Draper Independent Chairperson Newcastle Gas Storage Facility 0401 609 693 Community Relations Manager lisaandrews.ic@gmail.com 0498 020 244 MDraper@agl.com.au