Slide 1: Duralie Coal CCC Meeting Presentation – Company Report & Overview of Activities
Duralie Coal CCC Meeting Presentation – Company Report & Overview of Activities February 2019 Michael Plain Environment & Community Superintendent
Slide 2: Table of Contents
Table of Contents 1. Agenda Item 7a - Progress at the Mine 2. Agenda Item 7b - Environmental Reporting 3. Agenda Item 7c - Environmental Management Plans & Monitoring 4. Agenda Item 7d - Community Complaints 5. Agenda Item 7e - Community Programs 2 15 February 2019 2
Slide 3: 1. Progress at the Mine
1. Progress at the Mine Mining 4th Quarter 2018 Overburden mined 2,280 BCM ROM Coal mined 3,280 tonnes Mining completed in Weismantel pit early October 2018. Last ROM coal railed on 4 October 2018. Rehandle of PAF material to Clareval Pit continued up to December 2018. Bulk shaping and reh
Slide 4: 2. Environmental Reporting & Regulators
2. Environmental Reporting & Regulators Management Project Status Area Reporting • Yancoal Environmental • Yancoal runs a program of environmental assurance audits across its operations to Assurance Audit – Stratford & assess the management of key environmental risks. The Stratford and Duralie sites
Slide 5: 3. Environmental Management Plans & Monitoring
3. Environmental Management Plans & Monitoring a) Air Quality Management b) Blast Management c) Noise Management d) Water Management e) Rehabilitation Management f) Biodiversity Management g) Mine Closure Planning 5 15 February 2019 5
Slide 6: 3a. Air Quality Management – Dust Deposition
3a. Air Quality Management Duralie Dust Deposition - Annual Rolling Average 12 Months to December 2018 8.0 Dust (g/m2/month) 6.0 4.0 2.0 0.0 Nov-2017 Dec-2017 Feb-2018 Apr-2018 May-2018 Jul-2018 Sep-2018 Oct-2018 Dec-2018 Feb-2019 D3 D4 D5 D5A D7 D8 D9 D10 D12 D13 DP&E limit Mar-18 D3 – 6.4 Very Hea
Slide 7: 3a. Air Quality Management – PM10 Monitoring
3a. Air Quality Management Duralie HVAS Monitoring (PM10) 12 Months to December 2018 60 50 PM10 (µg/m3) 40 30 20 10 0 1-Jan-18 1-Feb-18 1-Mar-18 1-Apr-18 1-May-18 1-Jun-18 1-Jul-18 1-Aug-18 1-Sep-18 1-Oct-18 1-Nov-18 1-Dec-18 High Noon Twin Houses Hattam Edwards DP&E Limit Duralie HVAS Monitoring (P
Slide 8: 3b. Blast Management
3b. Blast Management Management Project Status Area Blasting • Blast monitoring • Blast activities at the DCM were completed on 17 August 2018. No further blasting is proposed until further notice. • Note: Blast Compliance: No more than 5% of total blasts for annual monitoring period to exceed an ov
Slide 9: 3c. Noise Management
3c. Noise Management Management Project Status Area Noise • Routine Monitoring • Routine quarterly monitoring of operations was undertaken in January 2019. Noise Monitoring monitoring results have remained below the noise criteria. No operations were being undertaken at the time of the monitoring. N
Slide 10: 3d. Water Management
3d. Water Management Management Project Status Area Site Water • Annual water balance review. • The annual site water balance review is currently being prepared. A summary will be Management included in the Annual Review. Surface Water • Routine monitoring • Sporadic and low rainfall conditions pers
Slide 11: 3d. Water Management – Rainfall and Surface Water Monitoring
3d. Water Management Duralie Mine Site - Monthly Rainfall Duralie Surface Water Monitoring - pH 6 months to December 2018 10.0 300 Rainfall (mm) 9.0 200 8.0 7.0 100 6.0 5.0 0 May-2018 Jun-2018 Aug-2018 Sep-2018 Oct-2018 Dec-2018 Jan-2019 2018 JAN SW2 - DCPL (CSC) SW2 RC - Rail Culvert DCPL (CSC) MAR
Slide 12: 3e. Rehabilitation Management
3e. Rehabilitation Management Management Area Project Status Rehabilitated Waste • Final landforms designs • Final landform designs have been progressed for the waste emplacement areas in emplacements Clareval and Weismantel. • Bulk Shaping • A D11 Dozer has continued bulk shaping works on the Weism
Slide 13: 3e. Rehabilitation Management
3e. Rehabilitation Management Management Area Project Status Rehabilitation • Vegetation Monitoring - • Rehabilitation monitoring is scheduled for May 2019. Monitoring Ecosystem Function Analysis 13 15 February 2019 13
Slide 14: 3f. Biodiversity Management
3f. Biodiversity Management Management Project Status Area BMP • Biodiversity • A revision of the Biodiversity Management Plan has been prepared following the first 5 years of Management Plan implementation. A summary of the biodiversity offset works completed and the changes to the revision BMP is
Slide 15: 3f. Biodiversity Management
3f. Biodiversity Management Management Project Status Area Flora/Fauna • Nest Box Program • Annual monitoring of nest boxes was undertaken in September 2018. A summary of the nest box progress will be included in the next Annual Review. • The program now includes 211 nest boxes. The 2018 report is c
Slide 16: 3g. Mine Closure Planning
3g. Mine Closure Planning Note: *Refer to Duralie Mining Operations Plan & Rehabilitation Management Plan Table 14 Mine Closure Planning Schedule. *Further detail on mine closure planning progress is included in the Annual Review 2018. Management Project Status Area Mine Closure • Stakeholder • Comm
Slide 17: 4. Community Complaints
4. Community Complaints Duralie Complaint Summary Period: 1/10/2018 - 31/12/2018 Period: 3 Months Total No. of Complaints: 1 (0 noise, 0 blast, 1 air quality, 0 other) Total No. of Complainants: 1 Date/Time of Complainant Method of Nature of Complaint Location Complaint Complaint Investigation/Outco
Slide 18: 5. Community Programs
5. Community Programs Management Area Project Status Support Programs Stratford Coal Community • The Stratford Coal Community Support Program for 2019 has now closed. Support Program Advertising was undertaken during December 2018 and applications closed at the end of January 2019. • SCPL received a