Sutter Gold Mining Inc

Sutter Gold Mining — Investor Presentation (February 2013)

28 slides from Sutter Gold Mining's investor presentation, February 2013

  1. Slide 1: Advancing Toward Positive Cash Flow in California's Mother Lode

    Advancing Toward Positive Cash Flow in California’s Mother Lode February 2013 TSX-V : SGM OTCQX : SGMNF

  2. Slide 2: Forward-looking statements

    The following presenta1on may include certain “forward-­‐looking statements” within the meaning of applicable Canadian Securi1es Laws and the United States Private Li1ga1on Reform Act of 1995. All statements, other than statements of historical fact, included in the presenta1on , including, without

  3. Slide 3: Dominant land position in the most prolific portion of the Mother Lode

     We control a dominant land / mineral rights posi1on in the most prolific por1on of California’s famed Mother Lode  We are bringing into produc1on our Phase 1 Lincoln Mine Project, the first new commercial gold mine in the Mother Lode in more than 50 years  We intend to achieve steady-­‐state produ

  4. Slide 4: Executives and Management

    Execu&ves and Management Leanne Baker President & Chief Execu1ve Officer Bob Hutmacher Chief Financial Officer Ma` Collins Chief Opera1ng Officer -­‐ QP David Cochrane VP Environmental Health & Safety Edward McGoldrick General Manager Amanda Miller Controller Art Campo Chief Mine Geologist Sco` Briscoe Se

  5. Slide 5: Sutter 5 Year Stock Price and Capital Structure

    Sutter 5 Year Stock Price OTCQX TSX-­‐V 52 wk high $0.51 52 wk low $0.17 $0.17 Avg daily volume (2012) 32,400 33,200 Capital Structure (December 2013) Prepaid Gold Facility $20 million Available Credit $2.85 million RMB Facility Draws $9.15 million Shares Outstanding 120.4 million Op1ons 5.7 million

  6. Slide 6: Ingredients for Success

     Opportunity:  Build the Lincoln Mine Project while gold price fundamentals remain strong  Leverage our con1nued growth by genera1ng cash flow from opera1ons  Upside poten1al from explora1on, with built-­‐in capacity to expand mining and milling rates  Ingredients for Success:  Mining-­‐friendl

  7. Slide 7: Sutter controls a significant portion of the California Mother Lode vein system

    SuJer controls a significant por&on of the “California Mother Lode” vein system 7 TSX-­‐V:SGM OTCQX:SGMNF

  8. Slide 8: Location between Sutter Creek and Amador City

     Located between the towns of Su`er Creek (the historic Lincoln Mine) and Amador City (the historic Keystone Mine)  Accessible by Highways 49 and 104  45 miles southeast of Sacramento in Amador County  Power, communica1on, and transporta1on infrastructure established 8 TSX-­‐V:SGM OTCQX:SGMNF

  9. Slide 9: History of the project area

    • John Su`er explored for 1mber in mid 1840’s and briefly for gold in 1848 1848 along the banks of what is now Su`er Creek • First gold discovery came in June 1851 by the Amador Quartz Mining Company. 1851 Leland Stanford gained control of the mine in the late 1850’s, and renamed it the Lincoln 1851-

  10. Slide 10: Mineral resources: Lincoln-Comet and Keystone

    Uncut Grade Tons Contained Ounces Oz/ton Indicated: Lincoln-­‐Comet 511,700 0.37 188,481 Keystone 161,900 0.21 34,563 Total Indicated 673,600 0.33 223,044 Total Inferred 2,377,900 0.19 458,914 Total Indicated and Inferred contained ounces 681,958 Source: NI 43-­‐101 Technical Report, February 2008,

  11. Slide 11: The Lincoln Mine Project – Foundation for Continued Growth

     The Lincoln Mine Project – Founda&on for Con&nued Growth  NI 43-­‐101 Preliminary Economic Assessment (PEA), released in 2011, focused only on the upper por1on of the Lincoln-­‐Comet deposit  By incorpora1ng exis1ng mine infrastructure, we minimize development costs, accelerate start-­‐up, and a

  12. Slide 12: Phase One Scenario First Five Years

    Phase One Scenario First Five Years Indicated / Inferred Resource 210,300 t material 0.573 opt (19.6 gpt) Current Mining Plan 244,800 t material 0.46 opt (15.8 gpt) Cutoff Grade 0.22 opt (7.5 gpt) Mine Opera1ng Rate 150 tpd (7 days / week) Mill Opera1ng Rate 210 tpd (5 days / week) Annual Gold Produc

  13. Slide 13: Existing Portal and Surface Facilities mine design

    Existing Portal & Surface Facilities (@1200 foot elev.) ~4220 Feet • Colors Identify Stope Panels/Veins • Existing Workings in Brown • Current Mine Design Drifts/Declines in Red View Looking East at -5° Dip • Modeling and Design in Surpac™ software 13 TSX-­‐V:SGM OTCQX:SGMNF

  14. Slide 14: 2013 priorities: commissioning mill and developing stopes

     Complete commissioning of our new mill & other processing facili1es, and move staff into new building  Resolve delay and cost issues with underground development  Complete new raises (ven1la1on and secondary access), and become MSHA-­‐compliant  Develop eight working stopes by 3Q, and up to 13 w

  15. Slide 15: Closing out building permits; new mill ready for commissioning

    We are closing out building permits, & new mill is ready for commissioning in March 2013 Underground development behind prior schedule – key item on cri1cal path 15 TSX-­‐V:SGM OTCQX:SGMNF

  16. Slide 16: Underground mine development is key

     Underground mine development is key  Completed ven1la1on dris at 1300 level & secondary access at 1200 level  First raise is underway  Development con1nues on 900 and 1100 produc1on levels  With MSHA approval, we are developing our own in-­‐house mine rescue teams  Steady-­‐state gold produc1

  17. Slide 17: Financial advisor and bridge loan refinancing

     Engaged financial advisor  Our $12 million bridge loan facility matures in June 2013  We will pursue appropriate capital refinancing, liquidity enhancement, and project advancement funding 17 TSX-­‐V:SGM OTCQX:SGMNF

  18. Slide 18: Capital Requirements – Lincoln Mine Project

    Capital Requirements – Lincoln Mine Project Es&mated Cost USD$ 000’s Project to Es&mated Item Prior Budget Feb ‘13 Budget Date Spend Remaining Spend Mine Equipment 1,697 1,591 838 753 Mine Development 2,655 4,472 2,089 2,383 Process Plant 5,557 6,297 6,017 280 Waste Management 1,241 1,315 1,315 -­‐

  19. Slide 19: US$20 Million Prepaid Gold Facility

     US$20 Million Prepaid Gold Facility  Signed agreement with RMB Australia Holdings (RMBAH) in July 2011  Ini1al $6.6 million of the proceeds repaid a previous credit line, and the remaining $13.4 million was drawn down to fund the Lincoln Mine Project and other corporate expenses  Repayment of t

  20. Slide 20: US$12 Million Bridge Facility

     US$12 Million Bridge Facility  In October 2012, the Company signed an agreement with RMB Australia Holdings (RMBAH) to implement a $12 million bridge facility  The $12 million is being drawn down monthly to bring the Lincoln Mine Project into produc1on and other corporate expenses  As of Januar

  21. Slide 21: Historic mines quote from Meiklejohn

    “The outstanding fact that we must give credence to, is that no one mine of this en6re group was ever closed because of its being worked out.” D.F. Meiklejohn, 1930s, referring to historic mines in the Keystone area 21 TSX-­‐V:SGM OTCQX:SGMNF

  22. Slide 22: 2012 exploration program results

    Expand Area resources Between Aid in Best results include Lincoln & Underground 4.317 opt in 1.8-­‐foot Comet Development interval, 1.791 opt in 2.1-­‐foot interval, Two new gold-­‐ Program included 22 1.19 opt in 1.8-­‐foot bearing veins holes, drilling almost discovered. Will be 8,800 feet. interv

  23. Slide 23: Exploration Targeting

    A Exploration Targeting 23 TSX-V:SGM OTCOX:SGMNF

  24. Slide 24: Exploration Targeting

    A SUTTER ABM GOLD Exploration Targeting MINING INC. ne) 1000 2000 Interbedded “=a Sequence 3.6 miles Ve 24 TSX-V:SGM OTCOX:SGMNF

  25. Slide 25: Phase I Drilling Long Section

    ddh-­‐206 ddh-­‐196 N & 197 ddh-­‐199 ddh-­‐201 ddh-­‐198 & 200 & 202 ddh-­‐203 & 204 LINCOLN COMET ZONE ZONE 0 200’ Phase I Drilling (Southern) Long Sec1on: looking N30°E showing projec1on of completed drill holes (green lines) and planned drill holes (yellow lines). 25 TSX-­‐V:SGM OTCQX:SGMNF

  26. Slide 26: Lincoln Keystone Bunker Hill Eureka

    Lincoln Keystone Bunker Hill Eureka 26 TSX-­‐V:SGM OTCQX:SGMNF

  27. Slide 27: Potential for increase in per-ounce gold multiple

    Potential for a three-pronged increase in per-ounce gold multiple: = As we complete construction of the first commercial gold mine in the California Mother Lode in more than 50 years = As we complete the ramp-up to full production in 2013 = As we add to our near-term gold resource Longer-term upside

  28. Slide 28: Contact Information

    Contact Informa1on: 165 South Union, Suite 565, Lakewood, Colorado Robert Hutmacher, CFO Tel: 303-­‐238-­‐1438 www.suJergoldmining.com TSXV:SGM OTCQX: SGMNF 28