Nordic Mining Asa — Q1 2016 Earnings Presentation

29 slides from Nordic Mining Asa's earnings presentation, May 13, 2016

  1. Slide 1: Minerals for a sustainable future

    Ti Pt Lighter aircrafts Minerals for a Clean air Pd sustainable future Electric cars Li Renewable energy Si 1

  2. Slide 2: Q1 2016 Presentation

    OAX: NOM Q1 2016 Presentation Oslo, 13 May 2016 Exploration and production of high-end minerals and metals Nordic Mining ASA | N-0250 Oslo | Norway | Tel +47 22 94 77 90 | Fax +47 22 94 77 01 | Org. no 989 796 739 | post@nordicmining.com 2

  3. Slide 3: Disclaimer

    Disclaimer This document has been used by Nordic Mining during an oral presentation. Therefore, this document is incomplete without the oral explanations, comments and supporting instruments that were submitted during the referred presentation. To the extent permitted by law, no representation or wa

  4. Slide 4: Introduction, Financial status, Update on projects

    1. Introduction 2. Financial status 3. Update on projects - Nordic Rutile - Keliber - Nordic Ocean Resources 4. Questions

  5. Slide 5: Minerals for a sustainable future

    Platinum, Palladium Minerals for a sustainable future Reinfjord Nordic Rutile AS Lithium Titanium Nordic Quartz AS Quartz Nordic Ocean Resources AS (80%) Keliber Oy (25%) 5

  6. Slide 6: Introduction, Financial status, Update on projects

    1. Introduction 2. Financial status 3. Update on projects - Nordic Rutile - Keliber - Nordic Ocean Resources 4. Questions

  7. Slide 7: Consolidated Income Statements

    Consolidated Income Statements Q1-2016 Q1-2015 Acc. 2016 Acc. 2015 2015 Unaudited Unaudited Amounts in NOK million Unaudited Unaudited Audited - - Sales - - - (1.6) (1.7) Payroll and related costs (1.6) (1.7) (6.6) (1.6) (1.5) Other operating expences (1.6) (1.5) (6.1) (3.2) (3.2) Operating loss (3.

  8. Slide 8: Consolidated Statements of Financial Position

    Consolidated Statements of Financial Position 31.03.2016 31.12.2015 Amounts in NOK million Unaudited Audited ASSETS Evaluation and exploration assets 17.5 9.8 Property, plant and equipment 0.4 0.1 Investment in an associate 12.4 6.2 Total non-current assets 30.3 16.1 Cash 15.7 29.8 Other current ass

  9. Slide 9: Shareholder structure and share price development

    Shareholder structure and share price development Largest shareholders* Share overview and share price development* Name of shareholder No. of shares % Share overview 1 NORDNET BANK AB (NOMINEE) 30 299 980 7,9 % Stock symbol NOM 2 SKAGEN VEKST 15 819 516 4,1 % Stock exchange Oslo Axess 3 NORDEA BANK

  10. Slide 10: Introduction, Financial status, Update on projects

    1. Introduction 2. Financial status 3. Update on projects - Nordic Rutile - Keliber - Nordic Ocean Resources 4. Questions

  11. Slide 11: Engebø

    Engebø  One of the world’s largest deposits of natural rutile  Has the highest grade among current producers and projects  Impurities at background levels  Located next to tidal waters and European markets  Permitted for 50 years of operation 11

  12. Slide 12: Core and geo-stat drilling program completed in April 2016

    Core and geo-stat drilling program completed in April 2016 • 38 drill holes of approximately 6,400 meters, primarily in the open pit area • Geotechnical assessments are carried out by Wardell Armstrong, UK • Resource modeling and estimations by Competent Person Adam Wheeler, UK Resource estimations

  13. Slide 13: Ongoing activities towards PFS

    Ongoing activities towards PFS • Core logging, inspections, splitting and analysis • Geo-technical logging and ore model analysis • Garnet inspections and analysis • Resource analysis and modeling • Technical advisor, screening and evaluations • Mining plans, scenario reviews and lay-out • Infrastru

  14. Slide 14: Positive long-term price outlook for rutile

    Positive long-term price outlook for rutile Selected research reports from Q1 2016 2016 2017 Long-term (Price forecasts in USD per tonne rutile) Royal Bank of Canada (RBC) 813 900 1,100 UBS 800 875 1,300 J.P. Morgan 698 677 1,000 Credit Suisse 750 800 1,250 Investec 763 838 1,020 Maquarie 700 680 81

  15. Slide 15: Introduction, Financial status, Update on projects

    1. Introduction 2. Financial status 3. Update on projects - Nordic Rutile - Keliber - Nordic Ocean Resources 4. Questions

  16. Slide 16: Positive Pre-Feasibility Study financials

    Positive Pre-Feasibility Study financials Preliminary Keliber key figures Production capacity, Lithium Carbonate (Li2CO3) 9,000 tpy Ore processing capacity 400,000 tpy Operative time (current open pit deposits) 11 years CAPEX EUR 164 million NPV after tax @ 8% WACC EUR 97 million IRR after tax 21% P

  17. Slide 17: Prosperous lithium province provides exploration opportunities

    Prosperous lithium province provides exploration opportunities Ore Reserves Category Deposit kt Li2O% JORC Proven Länttä 470 0,95 2012 Probable Länttä 540 0,93 2012 Syväjärvi 1 480 1,19 2012 Rapasaari 1 750 1,09 2012 Outovesi 250 1,20 Proven and Probable 4 490 1,10  Keliber’s exploration drilling p

  18. Slide 18: Deutsche Bank has new report on Lithium

    Deutsche Bank has new report on Lithium (25%) 18

  19. Slide 19: Strong growth forecasted

    Strong growth forecasted (25%) 19

  20. Slide 20: Driven by the EV market

    Driven by the EV market (25%) 20

  21. Slide 21: Strong EV outlook in USA and China

    Strong EV outlook in USA and China (25%) 21

  22. Slide 22: Production window for Lithium remains open in Europe

    Production window for Lithium remains open in Europe (25%) 22

  23. Slide 23: Introduction, Financial status, Update on projects

    1. Introduction 2. Financial status 3. Update on projects - Nordic Rutile - Keliber - Nordic Ocean Resources 4. Questions

  24. Slide 24: Nordic Ocean Resources – Increased interest and momentum

    Nordic Ocean Resources – Increased interest and momentum 24

  25. Slide 25: Nordic Ocean Resources – MarMine ready for survey in August 2016

    Nordic Ocean Resources – MarMine ready for survey in August 2016 – vessel contracted

  26. Slide 26: Investment highlights

    Investment highlights OAX: NOM Titanium - Natural Rutile • World class rutile deposit; 50 years mine life and highest global TiO2 grade • Favourable location and logistics; competitive Capex/Opex Titanium – Natural Rutile • Internal NPV estimate (8%) of USD 466 million • Environmental permit for 50

  27. Slide 27: Summons to the ordinary general meeting 18 May 2016

    8.31 AM CET / 26-Apr-2016 / Nordic Mining ASA (OAX:NOM) Summons to the ordinary general meeting 18 May 2016 The ordinary general meeting of the shareholders in Nordic Mining ASA will be held at 16:00 on Wednesday 18 May 2016 at the Company's premises, Vika Atrium, Munkedamsveien 45 (Entrance A, 5th

  28. Slide 28: Introduction, Financial status, Update on projects

    1. Introduction 2. Financial status 3. Update on projects - Nordic Rutile - Keliber - Nordic Ocean Resources 4. Questions

  29. Slide 29: SAFETY – ENVIRONMENT - INNOVATION

    SAFETY – ENVIRONMENT - INNOVATION www.nordicmining.com 29