TGK-1 · RUS:TGKA
TGK-1 — Tgc-1 — VTB Capital Investment Forum "Russia Calling!" 2010
16 slides from TGK-1's conference presentation, Oct 7, 2010
Slide 1: TGC-1: Unique Power Generation Company of Russia
TGC-1: UNIQUE POWER GENERATION COMPANY OF RUSSIA October 7, 2010 VTB Capital Investment Forum “Russia Calling!” Moscow
Slide 2: TGC-1 at a glance
TGC-1 at a glance St. Petersburg and Murmansk region Karelia Leningrad region • 11 CHPPs: 2,805 MW / • 2 CHPPs: 345 MW /1,846 • 1 CHPP: 280MW/689 11,827 GCal-h GCal-h GCal-h • 6 HPPs: 664 MW • 17 HPPs: 1,595 MW • 17 HPPs: 633 MW • 1 diesel PP: 2 MW 2009 key figures Position in the industry Electrici
Slide 3: Regions of operation
Regions of operation Economically developed St. • Population of 0.9 million Petersburg and Leningrad region consume c.2/3 of electricity • Strong industrial presence, particularly, metals and mining produced in the North-West region Murmansk companies region • Low temperatures drives high Major
Slide 4: Shareholders
Shareholders Share capital – RUR 38.5 bn Over 320,000 shareholders Shares listed on MICEX (A1 quotation list) and on RTS Standard&Poor’s corporate governance score since 2006 (GAMMA-5 for 2009) One of the most professional IR and shareholders relations team in Russian utilities (Thomson Re
Slide 5: CAPEX
CAPEX Total investment program provides for capacity additions of over 1.6 GW until 2015 CAPEX financing in 2009 – RUR 20.4 bn (incl. VAT), in 2010 – RUR 17.9 bn (incl. VAT) Highly-effective combined-cycle (CCGT) technology to take up c.30% of thermal capacity by 2015 IRR for new CHPs - 14-1
Slide 6: Major outstanding projects
Major outstanding projects 2 new gas-fired CCGT-units (360 MW) at Pervomayskaya CHPP-14 in St. Petersburg CAPEX: RUR 15,7 bn (ex. VAT) Commissioning in winter 2010 - 180MW/160Gcal; 2011 - 180MW/160Gcal New gas-fired 450 MW CCGT-unit at Yuzhnaya CHPP-22 in St. Petersburg CAPEX: RUR 11.6 bn (ex.
Slide 7: Spin-off of heat transmission business
Spin-off of heat transmission business City of Heat output breakdown in St. Petersburg TGC-1 St.Petersburg 16% ≤75% ≥25% 43% District networks (“last mile”) Transmission grids in in areas supplied by TGC-1, St.Petersburg (mostly large St. Petersburg Heating Grid currently owned by GUP transmission p
Slide 8: Export
Export TGC-1 is the only company among TGKs/OGKs exporting electricity directly Operational capacities to export electricity to Estonia (c. 40MW) Export sales serve as a natural hedge for loans and contracts denominated in foreign currency Borisoglebskaya HPP max. export capabilities up to 56
Slide 9: 1H 2010 operational results
1H 2010 operational results The increase in demand of electricity in regions of operations: + 6.2% in St. Petersburg and Leningrad region, +7.6% in Karelia, +0.3% in Murmansk region Capacity utilization factor increased 0.5 p.p. to 52.6% Improvement of heat rates as a result of higher generati
Slide 10: Key 1H 2010 IFRS financials (mn RUR)
Key 1H 2019 IFRS financials (mn RUR) Largely positive half yearly results: very good 1Q and a not bad 2Q Margins were heavily influenced by high-base effect 1H 2010 1H 2009 Revenue 27 203,2 21 245,6 Electricity sales 9 519,7 6 878,6 Capacity sales 4 195,6 3 229,3 Heat sales 13 200,0 10 616,8 Oth
Slide 11: Outlook for 2010
Outlook for 2010 FY2010 financial results to be well above the plan 2H 2010 – commissioning of 180MW at Pervomayaskaya CHPP, 450MW at Yuzhnaya CHPP, 30MW at Svetogorskaya HPP Heating grids in St. Petersburg to fully transferred to St. Petersburg Heating Grid company in early 2011, evaluation o
Slide 12: Key earnings drivers
Key earnings drivers Steady stream of revenues from new capacity commissioned under Capacity Supply Agreement (DPM) Growth of unregulated electricity sales from efficient gas-fired plants and low-cost hydropower plants on the back of spot prices growth and further deregulation Prospect of introducti
Slide 13: Corporate governance
Corporate governance STRUCTURAL Disposal of hydro assets or merger of TGC-1 with Mosenergo is not on agenda INTEGRITY TGC-1 is one of the few Russian utilities to start paying dividend as of 2009 RESPONSIBILITY Gazprom to adopt uniform dividend policy for its electric utilities by year end MINOR
Slide 14: Investment case
Investment case EFFICIENT COGENERATION EXPOSURE TO HYDRO OPERATIONS IN DEVELOPED RUSSIAN REGIONS WITH STEADY CONSUMPTION EXPOSURE TO ELECTRICITY EXPORT INVESTMENT PROGRAM ON TRACK, VALUE-ACCRETIVE CAPEX POWERFUL STRATEGIC SHAREHOLDERS LOW CORPORATE GOVERNANCE RISKS EFFICIENT AND EXPERIENCED MANAGEME
Slide 15: Thank you!
THANK YOU! TGC-1: UNIQUE POWER GENERATION COMPANY OF RUSSIA
Slide 16: IR contacts
IR contacts Olga Solomina Head of Corporate Management Department Telephone: +7 (812) 901-3113 Fax: +7 (812) 494-3670 Е-mail: Solomina.ON@tgc1.ru Timur Akhmedzhanov Head of Investor Relations Telephone: + 7 (812) 901-3296 Fax: +7 (812) 901-3298 E-mail: Ahmedzhanov.TG@tgc1.ru E-mail: ir@tgc1.ru TGC-1
Tgc-1 — VTB Capital Investment Forum "Russia Calling!" 2010 on 6ix