Euro Manganese, Inc. · TSXV:EMN

Euro Manganese — Investor Presentation (March 2023)

36 slides from Euro Manganese's investor presentation, Mar 23, 2023

  1. Slide 1: Poised to Support the Energy Transition

    For personal use only Poised to Support the Energy Transition INVESTOR PRESENTATION March 2023

  2. Slide 2: Legal Disclaimer: Forward-Looking Statements and Risks Notice

    LEGAL DISCLAIMER Forward-Looking Statements and Risks Notice For personal use only Certain statements in this presentation constitute “forward-looking statements” or “forward-looking information” within the meaning of applicable securities laws. Such statements and information involve known and unkn

  3. Slide 3: High-Purity Manganese 101

    For personal use only High-Purity Manganese 101 MARKET OVERVIEW

  4. Slide 4: Manganese is an essential raw material in most lithium-ion batteries

    MARKET OVERVIEW Manganese is an essential raw material in most lithium- ion batteries For personal use only Nickel-Manganese-Cobalt (NMC) cathodes are currently the dominant chemistry in EV batteries with ~50% market share Batteries make up ~30% of the total cost of EVs ABOUT HIGH-PURITY MANGANESE I

  5. Slide 5: Global manganese market: high-purity manganese is a niche product

    MARKET OVERVIEW Global manganese market: high-purity manganese is a niche product For personal use only Only 1% of manganese mined globally is processed into a grade suitable for EV batteries Specialty Alloys 5

  6. Slide 6: Global high-purity manganese production landscape

    MARKET OVERVIEW Global high-purity manganese production landscape Supply currently dominated by China; project pipeline inadequate to meet forecasted demand For personal use only Supply Forecast • Only x2 new projects at Feasibility stage • Demand for HP Mn forecasted to surpass supply in 2024-2025

  7. Slide 7: Industry tail winds benefitting high-purity manganese market

    MARKET OVERVIEW Industry tail winds benefitting high-purity manganese market For personal use only Macro factors aligning to drive increased demand for high-purity manganese Continued growth of global EV Development of manganese- EU & US regulation supports 1 market 2 rich chemistries 3 localization

  8. Slide 8: Lack of supply combined with increasing demand results in significant deficit

    MARKET OVERVIEW Lack of supply combined with increasing demand results in significant deficit For personal use only Opportunity for HPMSM price to rise as supply vs demand deficit bites Global High-Purity Manganese Demand & Supply to 2031 Battery Metal Prices (2018-2023) 1,200 500 Global production

  9. Slide 9: New EU Critical Raw Material Act an opportunity for EMN

    MARKET OVERVIEW New EU Critical Raw Material Act an opportunity for EMN For personal use only Chvaletice Project likely to benefit from proposed legislation Manganese included as a strategic raw material • Manganese added to the list of critical raw materials and identified as a strategic raw materi

  10. Slide 10: Who We Are

    For personal use only Who We Are COMPANY & PROJECT OVERVIEW

  11. Slide 11: Battery metals company set to be a leading producer of high-purity manganese

    COMPANY OVERVIEW Battery metals company set to be a leading producer of high-purity manganese For personal use only Focused on delivering fully-traceable, responsibly-produced manganese for the EV industry Strategically located asset; sole manganese resource in the EU Positioned to support shift to

  12. Slide 12: Chvaletice is a unique waste-to-value project

    PROJECT OVERVIEW Chvaletice is a unique waste-to-value project For personal use only Involves reprocessing historical mine tailings to produce high-purity manganese Recycling • Historic tailings containing easily-treated manganese carbonate (1) • Well-defined mineral reserve of 27Mt @ 7.4% Mn with u

  13. Slide 13: Flow sheet produces two high-purity manganese products: HPEMM & HPMSM

    PROJECT OVERVIEW Flow sheet produces two high-purity manganese products: HPEMM & HPMSM For personal use only Robust process uses proven, conventional and commercial technologies; adheres to strict European environmental regulations 1 Raw tailings excavated and 2 Magnetic 3 Leaching and 4 Electrolysi

  14. Slide 14: Project designed to deliver exceptional ESG benefits

    PROJECT OVERVIEW Project designed to deliver exceptional ESG benefits For personal use only Wide-ranging benefits for all stakeholders #3 ORE Use of Best Available Technologies to Minimize Footprint STOCKPILE • Net positive environmental benefits from remediation of historic tailings • MoU to use 10

  15. Slide 15: Chvaletice's products to have lowest CO2 footprint vs incumbent industry

    PROJECT OVERVIEW Chvaletice’s products to have lowest CO2 footprint vs incumbent industry For personal use only Results of benchmarked LCA of high priority to customers and financiers HPEMM / HPMSM CO2 Emissions Comparison (Scope 1+2+3) CMP HPEMM 64% lower than China 20 17.1 Kg CO2 eq. per kg HPEMM/

  16. Slide 16: Demonstration Plant installed and being commissioned

    PROJECT OVERVIEW Demonstration Plant installed and being commissioned For personal use only Enables large-scale product samples on batch basis • Installation complete in two fully refurbished buildings • Commissioning on track for completion by end Q1 2023 • Customer samples expected Q2 2023 • Facil

  17. Slide 17: Project has good cashflow and margins together with supply security for Europe

    PROJECT ECONOMICS Project has good cashflow and margins together with supply security for Europe Stable production over 25-year project life, supported by 27 Mt reserve base For personal use only Feasibility Study Base Case Highlights ($ figures in USD) Feasibility Study Base Case Price Forecast for

  18. Slide 18: Project operational costs based on cost environment in mid-2022

    PROJECT ECONOMICS Project operational costs based on cost environment in mid-2022 For personal use only Energy and reagents constitute ~68% of operational costs Operational Costs ($/t of Plant Feed) $214.5 Opex 19.8 Royalty, freight, insurance • Reagents and energy account for ~30% and 38% of opex r

  19. Slide 19: Project capital costs include robust contingency

    PROJECT ECONOMICS Project capital costs include robust contingency For personal use only Capex figure reflects post-COVID supply chain environment Capital Cost Breakdown ($M) $757.3 Capex 78.4 • Robust +$100M contingency (includes $78M contingency and $25M Contingency of growth capital on direct cos

  20. Slide 20: Superior nature of Chvaletice products demand price premium

    PROJECT ECONOMICS Superior nature of Chvaletice products demand price premium For personal use only Product quality, ESG credentials and localization aspects deliver a price premium Unique Aspects of Chvaletice HPEMM & HPMSM Ex-Works China HPMSM Price vs. Forecasted European HPMSM Price High-purity

  21. Slide 21: Permitting and next steps

    PROJECT TIMELINE Permitting and next steps For personal use only On track to deliver final investment decision by H2 2023 H1 2023 H2 2023 2024 2025 2026 2027 DEMONSTRATION PLANT Customer samples & ongoing supply chain qualification Available for testing other feedstocks ENGINEERING, PROCUREMENT & CO

  22. Slide 22: Chvaletice: Funding

    For personal use only Chvaletice: Funding PROJECT FINANCE

  23. Slide 23: Project financing strategy: mix of debt and equity

    PROJECT FINANCE Project financing strategy: mix of debt and equity For personal use only Staged equity strategy; structured to reduce dilution Strategic Investment Private Offering Public Offering At project level, based on NAV At corporate level, based on ▪ EMN shareholders ▪ OEMs & key off-takers

  24. Slide 24: First offtake term sheet announced; broader offtake tender process underway

    PROJECT FINANCE First offtake term sheet announced; broader offtake tender process underway For personal use only Increasing attention on high-purity manganese; Auto OEMs continue to invest in projects to secure critical raw materials Overview of Verkor Offtake Term Sheet • Lithium • Outlines minimu

  25. Slide 25: Our Growth Horizon: North America

    For personal use only Our Growth Horizon: North America GROWTH OPPORTUNITY

  26. Slide 26: Rationale for North American growth strategy

    GROWTH OPPORTUNITY Rationale for North American growth strategy For personal use only Opportunity to supply pCAM/CAM plants under development in North America with locally-produced high-purity manganese • Demand for HP Mn in NA expected to reach >250Ktpa by 2031* • No current HP Mn processing capaci

  27. Slide 27: Bécancour opportunity provides first-mover advantage in North America

    GROWTH OPPORTUNITY Bécancour opportunity provides first-mover advantage in North America For personal use only Bécancour overview • Option agreement in place to purchase site (subject to outcome of due diligence) • Site due diligence complete on land parcel Bécancour land parcel • Scoping study near

  28. Slide 28: Looking Forward

    For personal use only Looking Forward OUTLOOK

  29. Slide 29: 2023 Key catalysts

    OUTLOOK 2023 Key catalysts For personal use only Demonstration Plant Status Production of on-spec products Expected Q1 Shipments to interested parties Expected Q2 EPCM for Commercial Plant Appointment of EPCM contractor Expected Q1 Completion of front-end engineering design (FEED) Expected H2 Land A

  30. Slide 30: Poised to Support the Energy Transition

    For personal use only Poised to Support the Energy Transition TSXV: EMN | ASX: EMN | OTCQX: EUMNF | Frankfurt Stock Exchange: E06 info@Mn25.ca | www.Mn25.ca

  31. Slide 31: Executive leadership team

    COMPANY OVERVIEW Executive leadership team For personal use only Track record of raising capital and delivering large-scale projects; deep high-purity manganese processing experience Matt James Martina Blahova James Fraser Fausto Taddei Andrea Zaradic Jan Votava President & CEO CFO VP Commercial Com

  32. Slide 32: Euro Manganese capitalization

    CORPORATE INFORMATION Euro Manganese capitalization Euro Manganese is a BC Company incorporated in 2014 and listed publicly in 2018; its head office is located in Vancouver For personal use only Ownership Structure at Feb. 21, 2023 TRADING SYMBOLS CORPORATE MEMBERSHIPS Total 402,669,227 TSX-V and AS

  33. Slide 33: FQ1 2023 Financial highlights and position

    FINANCIAL POSITION FQ1 2023 Financial highlights and position Fully funded to final investment decision and 2023 corporate G&A For personal use only Fully funded to complete: Cash Balance – October 1, 2022 C$21.6 • Demonstration plant commissioning and up to 1-year operation Completion of Demonstrat

  34. Slide 34: Resources converted to Reserves with 98% classified in Proven category

    RESERVE STATEMENT Resources converted to Reserves with 98% classified in Proven category For personal use only Estimated in accordance with the CIM Definition Standards on Mineral Resources and Mineral Reserves adapted by CIM Council, as amended, which are materially identical to the JORC Code. Chva

  35. Slide 35: Notes to Mineral Reserve Statement

    RESERVE STATEMENT Notes to Mineral Reserve Statement For personal use only 1. Estimated in accordance with the CIM Definition Standards on Mineral Resources and Mineral Reserves adopted by CIM Council, as amended, which are materially identical to the JORC Code. 2. The Mineral Resource is inclusive

  36. Slide 36: Legal Disclaimer: Compliance Statements

    LEGAL DISCLAIMER Compliance Statements For personal use only Competent and Qualified Persons Statement All production targets for the Chvaletice Manganese Project referred to in this presentation are underpinned by estimated Proven and Probable Reserves prepared by competent persons and qualified pe

Euro Manganese — Investor Presentation (March 2023) on 6ix