  1. Slide 1: 31 December 2013 Half Year Conference Call Presentation

    P PALADI IN ENER RGY LTD D A CN 061 681 098 0 Ref: 332876 13 Februarry 2014 ASX Marke et Announce ements B Electroniic Lodgemen By nt Australian Securities S Exchange 20 Bridge S Street SYDNEY NSW N 2000 adam Dear Sir/Ma 31 December 2013 Half Year Confe erence Call Presentattion Attached please p fi

  2. Slide 2: December 2013 Half Year and Quarter Results Conference Call and Investor Update

    December 2013 Half Year and Quarter Results Conference Call and Investor Update 14 February 2014 John Borshoff – Managing Director/CEO Alan Rule – CFO Mark Chalmers – Executive General Manager, Production February 2014

  3. Slide 3: Disclaimer and Notes for JORC and NI 43-101 Mineral Resources and Ore Reserves

    Disclaimer and Notes for JORC and NI 43- 101 Mineral Resources and Ore Reserves This presentation includes certain statements that may be deemed “forward-looking statements”. All statements in this presentation, other than statements of historical facts, that address future production, reserve or re

  4. Slide 4: Presentation Outline

    Presentation Outline Key Achievements and Update Uranium Market Update Financial Review Project Update Positioning for the Future 2

  5. Slide 5: Material Achievements are Redefining Paladin

    Material Achievements are Redefining Paladin The 4 Key Company Initiatives Achieved Operations – solid production/unit cost reduction continues Minority Equity Sale - successful Project Refinancing – collateral utilisation KM Care & Maintenance – cost reduction / asset preservation Bottom line over

  6. Slide 6: Highlights

    Highlights Record combined production for Langer Heinrich and Kayelekera — 4.253Mlb (1,929t) U3O8 for six months to December 2013 Minority sale of Langer Heinrich — introduces a world class JV party with access to world’s fastest growing market — sale proceeds of US$190M including non refundable dep

  7. Slide 7: Presentation Outline

    Presentation Outline Key Achievements and Update Uranium Market Update Financial Review Project Update Positioning for the Future 5

  8. Slide 8: Supply Fundamentals Deteriorating

    Supply Fundamentals Deteriorating Mine suspension or closures — Kayelekera, Honeymoon, Priargunsky Mine No. 2 Supply disruptions — Ranger, Rossing, Somair, Cominak Production delays — Cigar Lake, Imouraren, Husab Suspension / Delays of future planned developments — Greenfield - Kintyre, Toro’s Wilun

  9. Slide 9: Price Catalysts – demand and shortage

    Price Catalysts – demand and shortage Reactors under construction continue to increase (now 70 and growing) Japanese reactor restarts — 16 reactors undergoing safety evaluations by Nuclear Regulation Authority (NRA) — economically unsustainable and uncompetitive without nuclear — political support s

  10. Slide 10: Presentation Outline

    Presentation Outline Key Achievements and Update Uranium Market Update Financial Review Project Update Positioning for the Future 8

  11. Slide 11: Profit & Loss December 2013 Half Year

    Profit & Loss December 2013 Half Year Revenue of US$171.4M — 4.448Mlb sold at average realised price of US$38.4/lb — sales of 2.775Mlb in December 2013 quarter Gross loss from operations (excluding impairments) of US$4.4M — average cost of sales of US$39.5/lb before KM inventory impairment — KM (inv

  12. Slide 12: Cash Flow December 2013 Half Year

    Cash Flow December 2013 Half Year Cash and cash equivalents of US$99.4M Cash inflow from operating activities of US$4.3M — includes interest paid of US$16.6M Cash outflow from investing activities of US$17.2M — US$15M plant and equipment acquisitions — US$2.6M exploration expenditure Cash inflow fro

  13. Slide 13: C1 Cost of Production - Positive Trends Continue

    C1 Cost of Production - Positive Trends Continue Langer Heinrich Significant cost reductions and production optimisation at site Focus also on corporate cost efficiencies Kayelekera T “Proven ability to reduce costs through production optimisation” 11

  14. Slide 14: Material Changes to Future Cashflows

    Material Changes to Future Cashflows Langer Heinrich/Kayelekera Refinancing — US$59M reduction in debt repayments over CY14 and CY15 — Langer Heinrich debt repayments reduced by US$5.5M pa — overall reduction in debt US$14.5M Minority Sale Proceeds — will be applied predominantly to debt reduction a

  15. Slide 15: Langer Heinrich Minority Sale

    Langer Heinrich Minority Sale 25% JV equity stake to China National Nuclear Corporation (CNNC) — consideration of US$190M US$20M non-refundable deposit to Paladin — currently held in escrow, with release upon receipt of: (i) Lenders consent (ii) Bank of Namibia approval to assign intercompany loans

  16. Slide 16: Presentation Outline

    Presentation Outline Key Achievements and Update Uranium Market Update Financial Review Project Update Positioning for the Future 14

  17. Slide 17: Langer Heinrich Project Update

    Langer Heinrich Project Update Three successful production capacity Actual Budget Actual expansions completed FY13 Dec’13 Dec’13 — 5.2Mlb with Stage 3 starting mid 2012 YTD YTD — currently producing above budget Ore processed 3.54Mt 1.84Mt 1.83Mt — Dec qtr >5.7Mlb pa rate Ore feed grade 812ppm 753pp

  18. Slide 18: Langer Heinrich Quarterly Production

    Langer Heinrich Quarterly Production LHM Quarterly Production & Feed Grade 1600 1200 U₃O₈ Production (000) 1400 1000 1200 Grade (ppm) 800 1000 800 600 600 400 400 1431 1429 1353 1419 1230 200 1290 1322 1193 1052 796 650 674 686 693 655 842 928 927 900 933 896 849 200 0 0 Oct-Dec Jan-Mar Apr-Jun Oct-

  19. Slide 19: Kayelekera Project Update

    Kayelekera Project Update First modern resin-in-pulp (RIP) uranium Actual Budget Actual processing facility FY13 Dec’13 Dec’13 YTD YTD Production capacity of 3.3Mlb U3O8 pa Ore 1.3Mt 0.67Mt 0.59Mt processed C1 cost initiatives for FY13 successful and better than target Ore feed 1,143ppm 1,181ppm 1,2

  20. Slide 20: Kayelekera – Care & Maintenance from May/June 2014

    Kayelekera – Care & Maintenance from May/June 2014 7 February 2014 decision to go to care and maintenance — unavoidable in current uranium price environment — preserve resource to allow better utilisation and future profitability Transition from operating to care and maintenance — processing will co

  21. Slide 21: Presentation Outline

    Presentation Outline Key Achievements and Update Uranium Market Update Financial Review Project Update Positioning for the Future 19

  22. Slide 22: New Joint Venture Partner for Langer Heinrich

    New Joint Venture Partner for Langer Heinrich CNNC is a major nuclear organisation of China — is engaged in the scientific research and development, construction and operation in such fields as nuclear power, nuclear fuel cycle, nuclear technology application and nuclear environmental engineering, a

  23. Slide 23: Positioned for the Future

    Positioned for the Future Solid reputable JV partner for LHM in place — Company now in strong position to achieve future goals Proven builder/operator — extensive uranium expertise in the group (technical, environmental, health, social) — only company in the world to have successfully developed two

  24. Slide 24: Conclusion

    Conclusion Paladin on track to continue solid production results – on track with revised guidance of 7.8Mlb to 8Mlb for FY14 Focused on further cost rationalisation and production optimisation Proven management team that has delivered on both operational and strategic goals Strategic initiatives to

  25. Slide 25: Paladin Energy Ltd Contact Details

    Paladin Energy Ltd Contact Details Head Office Level 4, 502 Hay Street Subiaco Western Australia 6008 PO Box 201, Subiaco Western Australia 6904 Telephone: +61 (0) 8 9381 4366 Facsimile: +61 (0) 8 9381 4978 Email: paladin@paladinenergy.com.au Website: www.paladinenergy.com.au Investor Relations Team