El Paso Electric Company

El Paso Electric — Q1 2014 Earnings Presentation

16 slides from El Paso Electric's earnings presentation, May 7, 2014

  1. Slide 1: First Quarter 2014 Earnings Conference Call

    First Quarter 2014 Earnings Conference Call

  2. Slide 2: Safe Harbor Statement

    Vision Mission Integrity Safe Harbor Statement This presentation includes statements that may constitute forward-looking statements made pursuant to the safe harbor provisions of the Private Securities Litigation Reform Act of 1995. This information may involve risks and uncertainties that could cau

  3. Slide 3: Significant Development: Montana Power Station air permit

    Vision Mission Significant Development Environmental Protection Agency (EPA) air permit to build Montana Power Station (MPS) in Far East El Paso issued on March 25, 2014 No appeals were filed by deadline and the permit became effective on April 25, 2014 Commence construction on MPS Units 1 & 2 in ea

  4. Slide 4: EE's Pillars of Value

    Vision Mission EE’s Pillars of Value EE is dedicated to the long-term success and well-being of our region and our stakeholders EE’s long-term strategic plan incorporates four Pillars of Value as a foundation Operational Excellence Stakeholder Satisfaction People/Technology Development Financial/Reg

  5. Slide 5: Recent Accomplishments

    Vision Mission Recent Accomplishments Obtained final approval from the EPA for the MPS air permit Macho Springs solar project is under testing and has begun delivering power to EE Received highest customer satisfaction rating in 5 years Ranked #1 in reliability in Texas third year in a row Restructu

  6. Slide 6: Near-Term Goals

    Vision Mission Near-Term Goals Complete construction of MPS Units 1 & 2 by the summer peak of 2015 Complete construction of Eastside Distribution Operations Center by early 2015 Obtain Certificates of Convenience & Necessity in Texas & New Mexico for MPS Units 3 & 4 Support Four Corners participants

  7. Slide 7: Executive Additions

    Vision Mission Executive Additions Michael D. Blanchard elected as the new Vice President of Regulatory Affairs Michael brings over 30 years of legal, regulatory and rate making experience John Boomer elected as Vice President and Treasurer John returns to EE after previously serving as assistant ge

  8. Slide 8: Expected Rate Case Timeline

    1/2014 1/2015 1/2016 1/2014 1/2015 1/2016 May 7, 2014 8 Expected Rate Case Timeline New Mexico December 2014 Historical Test Year End for NM Rate Case May 2015 File NM Rate Case (Includes MPS 1 & 2 in rate base)1 April 2016 NM Rate Increase effective April 2014 Final MPS Air Permit became effective

  9. Slide 9: Pro forma Rate Base Balances for Future Rate Case Filings

    9 Pro forma Rate Base Balances for Future Rate Case Filings ($000) (1) Includes Palo Verde Unit 3 rate base of approximately $36mm for each pro-forma filing (2) Rate Base totals exclude year end CWIP balances (3) Represents a pro-forma rate base amount that EE would use in rate filings for the test

  10. Slide 10: 2014 Financial Results

    Vision Mission 2014 Financial Results 1st Quarter 2014 net income of $4.6 million or $0.11 per share, compared to 1st Quarter 2013 net income of $7.6 million or $0.19 per share May 7, 2014 10

  11. Slide 11: 1st Quarter Key Earnings Drivers

    Vision Mission 1st Quarter Key Earnings Drivers May 7, 2014 11 Basic EPS Description March 31, 2013 0.19$ Changes In: Retail Non-Fuel Base Revenue (0.08) Decreased mainly due to milder weather in 2014 compared to 2013 Taxes other than income taxes (0.04) Increased primarily due to adjustment to the

  12. Slide 12: Historical Weather Analysis

    Vision Mission Historical Weather Analysis 1st Quarter 2014 Heating Degree Days (HDD) were 19.2% below the 10 year average and 28.4% below 1st Quarter 2013 May 7, 2014 12 1,207 1,024 1,288 1,191 1,030 1,396 1,265 1,159 1,338 958 700 900 1,100 1,300 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 1

  13. Slide 13: Changes in Revenue and Sales

    Vision Mission May 7, 2014 13 Non-Fuel Base Revenue (000's) Percent Change MWH Percent Change Residential 45,594$ (8.1%) 543,030 (9.3%) C&I Small 32,121 (2.0%) 493,919 (1.6%) C&I Large 8,328 (2.6%) 226,552 (7.4%) Public Authorities 17,656 0.5% 343,028 (4.5%) Total Retail 103,699$ (4.4%) 1,606,529 (5

  14. Slide 14: Capital Requirements and Liquidity

    Vision Mission Capital Requirements and Liquidity EE has expended $48.3mm for additions to utility plant for the three months ended March 31, 2014 Capital expenditures for utility plant in 2014 are anticipated to be approximately $316.4mm EE made $10.7mm in dividend payments for the three months end

  15. Slide 15: 2014 Earnings Guidance

    Vision Mission 2014 Earnings Guidance We are affirming our earnings guidance range for 2014 of $2.10 to $2.50 per share May 7, 2014 15

  16. Slide 16: Q & A

    Vision Mission Q & A May 7, 2014 16