British Land Company PLC · LSE:BLND
British Land — Corporate Update (May 2022)
21 slides from British Land's corporate update, May 31, 2022
Slide 1: Canada Water Development Construction Liaison Forum
Canada Water Development Construction Liaison Forum Plot K1 (and surrounding area) 31 May 2022
Slide 2: Introductions and meeting code of conduct
Introductions and meeting code of conduct Canada Water development Construction management Updates from contractors - Construction of Plot K1 (McAleer & Rushe) Ove rview of - Construction of substation (Galldris) tonight's ~ OBA presentation
Slide 3: Our presenters
Our presenters SARAH WARD Construction Neighbour Liaison Manager STUART MCLEISH Contractor, Galldris Construction of substation at rear of Printworks JAMIE CASSIDY Contractor, McAleer & Rushe JOHN CZERNOBAY British Land Construction of Plot K1
Slide 4: Wider Canada Water development works
Wider Canada Water development works ee pn we Pictured: Plan showing details of work site locations
Slide 5: Common working practices
Common working practices Noise, dust and vibration monitoring and reporting Standard construction working hours: * Monday - Friday: 8am - 6pm * Saturday: 8am - 2pm (no noisy works before 9am) « When work outside of standard hours is needed, this will be agreed with Southwark Council and communicated
Slide 6: McAleer & Rushe
McAleer & Rushe
Slide 7: Key
Key Canada Water Development boundary First phase of the development ¢ 4 - s g Towards Canada Water station A
Slide 8: Plot K1 - Current site activity
Plot KL - Current site activity * The tower crane was installed in the centre of the site in March. * Works to lay the ground floor slab are ongoing, expected to finish in June 2022. * Work has begun on the vertical elements of the main building.
Slide 9: Plot K1 - Site photos
Plot K1 - Site photos x 4
Slide 10: Plot K1 - Upcoming works
Plot KL - Upcoming works * Tree/vegetation trimming will be undertaken where required along the perimeter of the site to enable work on the concrete frame of the building to begin. * Once the ground floor slab and above works are complete, the concrete frame will start to be installed. The construct
Slide 11: Plot K1 — Indicative timeline
Plot K1 — Indicative timeline ring 2023 agade works continue, internal fit out and public realm works begin Winter 2022/23 Summer 2023 er led, groundwork, Facade works (exterior of Expected completion date foundations and substructure building) work ongoing, concrete frame build begins
Slide 12: Zone L GALLDRIS
Zone L GALLDRIS (rear of Printworks site by Quebec Way)
Slide 13: Zone L - site location
Slide 14: Zone L - Site activity
Zone L - Site activity Progress continues to be made to build a 10m deep basement for a new below-ground electricity substation for UKPN. Bulk excavation works have recently been completed. . Work has begun to construct the basement slabs - concrete pours for 8 different elements of the building wil
Slide 15: Site Photos
Site Photos
Slide 16: Site Layout
Site Layout
Slide 17: Zone L — Indicative timeline
Zone L — Indicative timeline Winter 2021/22 through to Winter 2022/23 Spring 2023 2025 Winter 2022/23 UKPN take possession to Galldris install covers over UKPN expected to Galldris building basement begin fit out and install transformer bays complete fit out box of substation and transformers suppor
Slide 18: Printworks Infrastructure
Printworks Infrastructur * Installation of new below ground infrastructure (drainage, ducting, gas and water pipes, etc) and the construction of new access roads. * Project currently within the design stage. * Indicative construction period - Oct 2022 to July 2023. Much more detail will be available
Slide 19: Contact us
CANADAANATER Contact us You can contact the Canada Water Masterplan team at: Tel: 0800 +70 4593 (freephone) Email: team@canadawater.co.uk Website: www.canadawater.co.uk
Slide 20: Roberts Close hoarding line
ROBERTS CLOSE Hoarding wal not hinder footpat ‘on the opposite side of the road. |— Not service entrance to school th Hoarding Line (red) . Unloading zone eS Ome > <8 (pas) eu Bupeoy wy Hoarding Line (red) >rIvM VISSM
Slide 21: Plot K1 - vehicle movements