  1. Slide 1: Investor Presentation – Transitioning to Development

    Slide 1: Investor Presentation – Transitioning to Development

    Investor Presentation Transitioning to Development LON:OMI TSX.V:OMI AGM Presentation, November 2026

  2. Slide 2: Forward Looking Statements and Disclosures

    Slide 2: Forward Looking Statements and Disclosures

    Forward Looking Statements and Disclosures This document and any information contained herein (together, the "Presentation") is strictly private and confidential and is being provided to you solely in connection with a potential fundraising by Orosur Mining Inc. (the "Company"). By receiving this Pr

  3. Slide 3: Forward Looking Statements and Disclosures

    Slide 3: Forward Looking Statements and Disclosures

    Forward Looking Statements and Disclosures This Presentation does not constitute a prospectus, offering memorandum or similar document for the purposes of any applicable laws in any jurisdiction and has not been approved by or filed with any regulatory authority in any jurisdiction. The distribution

  4. Slide 4: Corporate Snapshot

    Slide 4: Corporate Snapshot

    Corporate Snapshot 452m Shares 23.6m Options/RSU/DSU pence 38m Warrants US$65m Cash Board of Directors Key Management US$80m Market Cap Louis Castro: Executive Chairman Joaquin Sarroca: VP Commercial and Legal Brad George: CEO and Director Liliana Munoz: Colombia Manager Thomas Masney: Non-Executive

  5. Slide 5: Key Projects

    Slide 5: Key Projects

    Key Projects Anzá - Colombia • 530km2 of licenses and applications in Mid-Cauca Belt • 100% owned. • Pepas maiden resource completed – NI43-101 report filed. • Pepas PTO completed. • APTA prospect soon to enter resource drilling phase • Drilling just commenced on El Cedro porphyry system. El Pantano

  6. Slide 6: Investment Highlights

    Slide 6: Investment Highlights

    Investment Highlights 100% ownership of High grade gold Second high-grade Major porphyry two major projects resource entering prospect entering systems being feasibility and resource drill out drilled. permitting phase. Growing Resource Base Dual Strategy – Develop and Explore  Pepas High grade ope

  7. Slide 7: Mid-Cauca – Colombia’s elephant country

    Slide 7: Mid-Cauca – Colombia’s elephant country

    Mid-Cauca – Colombia’s elephant country • Mid-Cauca – Colombia’s primary copper/gold belt. • Close to road network, power, water • Trend includes giants: • Buritica - Zijin • Quebradona - Anglo Gold • Marmato – Aris • Guayabales - Collective • Porphyry and Epithermal systems • OMI huge permit holder

  8. Slide 8: Anza Project, Colombia

    Slide 8: Anza Project, Colombia

    Anza Project, Colombia Returned to 100% ownership in Dec 2024 Holding 530km2 - 170km2 licenses - 360km2 applications Immediate success at Pepas – MRE defined. Pepas moving into feasibility and permitting. Limonera drilling starting. APTA deposit being advanced. El Cedro drilling 8 underway

  9. Slide 9: Pepas – High Grade Resource

    Slide 9: Pepas – High Grade Resource

    Pepas – High Grade Resource Category Tonnes Gold Grade Contained (Mt) (g/t) Gold (ozs) MRE released in February 2026. Indicated 1.14 5.46 201,000 Inferred 0.19 2.99 18,000 High grade, shallow, low strip, close to highway, power to site – near term production potential Truncated by post-mineralisatio

  10. Slide 10: What does permitting mean?

    Slide 10: What does permitting mean?

    What does permitting mean? Building a mine is as much a political and social challenge as Technical Environmental a technical one. PTO EIA Three parallel, ANM ANLA/Corantioquia independent but interlinked streams. Keep options open as long as we can. Social/Community 10

  11. Slide 11: Parallel Streams

    Slide 11: Parallel Streams

    Parallel Streams PTO EIA SOCIAL Summary Document Most important Combination of Start now document reports and background work. Positive view of mining • Outlines main • Requires scope and scale comprehensive • Began informally 12 Build upon our long- • Triggers the EIA studies. months ago. standing

  12. Slide 12: PEA/PFS

    Slide 12: PEA/PFS

    PEA/PFS What and Why?  Based on PTO scope  More detail, more granular  Develop options around base case - 500t per day, 25,000oz pa, 10 yr mine life:  A. Toll treating  B. Dedicated plant  Modularised, small scale  Verification of PTO  Publicly disclosable and opens funding options.  Commen

  13. Slide 13: Exploration – Camp Scale

    Slide 13: Exploration – Camp Scale

    Exploration – Camp Scale Pepas Miocene reactivation of older structural La Virgincita corridor Structures wrap around older cretaceous intrusion APTA Younger Miocene intrusions exploit El Yarumo dilation zones and pressure shadows Northern side not yet El Cedro explored. 13

  14. Slide 14: Exploration – Beyond Pepas

    Slide 14: Exploration – Beyond Pepas

    Exploration – Beyond Pepas New mineralisation already found around Pepas. Now looking for Pepas repetitions PEPAS Drilling Zone Miocene sinistral reactivation opens dilation zones PEPAS Swapping over rigs, South South Pepas (Limonera) requires heli access. Mobilised to South Pepas two days ago, dril

  15. Slide 15: APTA – Next Resource?

    Slide 15: APTA – Next Resource?

    APTA – Next Resource? +40,000m of drilling New geological model developed 15

  16. Slide 16: APTA – MRE Drill out plan

    Slide 16: APTA – MRE Drill out plan

    APTA – MRE Drill out plan Changing drill rigs Developing access Plan to start MRE drillout early 2027 – rig changeover Start in high grade and step out – add maximum ounces for minimum metres Initial plan, 21 holes for 6500m 16

  17. Slide 17: El Cedro - first results confirm mineralisation

    Slide 17: El Cedro - first results confirm mineralisation

    El Cedro - first results confirm mineralisation CED001 – mineralised from surface (61.35m @ 0.93g/t Au) New Rig Mineralisation continued to over 300m. Hole terminated at 400m. CED002 started two days ago - drilling back in toward porphyry Negotiation for second rig advanced. Planned start early Dece

  18. Slide 18: Tentative Timeline - Colombia

    Slide 18: Tentative Timeline - Colombia

    Tentative Timeline - Colombia CED002 Commence started PFS Social PFS programs Drilling El complete Yarumo? Submit PTO Nov 2026 Dec 2026 Jan 2027 Feb 2027 Mar 2027 Apr 2027 MRE Northern Land access Commence drilling field completion? EIA APTA programs Limonera drilling Second rig starts to El Cedro 1

  19. Slide 19: El Pantano - Argentina

    Slide 19: El Pantano - Argentina

    El Pantano - Argentina Deseado Massif -prolific gold and silver province. Cerro Negro exploration model. Earned 100% with trailing NSR to vendors. One of the largest land packages in the region. First drilling campaign concluded Major mineral system identified. Plans for next phase being developed 1

  20. Slide 20: Thank You

    Slide 20: Thank You

    Thank You LON:OMI TSX.V:OMI Tel: +1 778-373-0100 | info@orosur.ca | www.orosur.ca