Enlight Renewable Energy Ltd · TASE:ENLT

Enlight Renewable Energy — Q1 2023 Earnings Presentation

19 slides from Enlight Renewable Energy's earnings presentation, May 2023

  1. Slide 1: Earnings Presentation First Quarter 2023

    Slide 1: Earnings Presentation First Quarter 2023

    EARNINGS PRESENTATION First Quarter 2023

  2. Slide 2: Legal disclaimer

    Slide 2: Legal disclaimer

    Legal disclaimer This presentation contains forward-looking statements within the meaning of the U.S. Private Securities Litigation Reform Act of 1995. We and disagreements with partners, investors and other counterparties that could reduce our right to cash flows generated by our projects; intend s

  3. Slide 3: Enlight at a glance

    Slide 3: Enlight at a glance

    Enlight at a glance Next generation global renewable energy platform Greenfield developer and IPP Global platform Wind, solar and energy storage Control over entire project life cycle Growing activity across Expertise across main renewable U.S., Europe and Israel technologies Extensive track record

  4. Slide 4: Strong quarter with focus on execution and returns

    Slide 4: Strong quarter with focus on execution and returns

    Strong quarter with focus on execution and returns 1 Delivering on execution Record Q1 Results • Growth in Mature Projects by 800 MWh, comprised of two stand-alone storage projects $71m • 2023 projects: 427 MW / 155 MWh expected to COD; Solar & Storage 1 brought forward to 2023 Revenues • 2024 proje

  5. Slide 5: Record quarterly results and rapid growth

    Slide 5: Record quarterly results and rapid growth

    Record quarterly results and rapid growth Growth driven by new operational projects Q1 2023 versus Q1 2022 ($m) 1,421 71 +98% 103% 54 55 118% +315% 717 35 33 +275% 25 13 9 1 Operational MW Revenue Net income Adjusted Cash flow from EBITDA Operations Q1/22 Q1/23 1Adjusted EBITDA is a non-IFRS measure

  6. Slide 6: Expected growth to continue apace in the coming years

    Slide 6: Expected growth to continue apace in the coming years

    Expected growth to continue apace in the coming years Operational capacity on track to triple to 4.5 GW and 3.5 GWh by the end of 2025 Mature Projects: Operational MW over time Status Today: Operational Under construction Pre construction 4,532 MW + 3,529 MWh CAGR +65% 2021A-2025E Co bar: 2,082 1,20

  7. Slide 7: Atrisco – continuing to focus on execution and returns

    Slide 7: Atrisco – continuing to focus on execution and returns

    Atrisco – continuing to focus on execution and returns Significant progress on financing; additional upside potential Location New Mexico, USA Development complete Technology Solar Advanced negotiations with leading financial institutions to provide a Generation capacity 360 MW $800m construction fa

  8. Slide 8: Co Bar Cluster – continuing to focus on execution and returns

    Slide 8: Co Bar Cluster – continuing to focus on execution and returns

    Co Bar Cluster – continuing to focus on execution and returns Incremental 475 MW contracted in the quarter; 1 GW of cluster now with signed PPAs Location Arizona, USA New PPA signed of 475 MW with local utility Technology Solar 1 GW contracted; remaining 200 MW in negotiations, in addition to 824 Ge

  9. Slide 9: U.S portfolio expected to benefit from energy community adders

    Slide 9: U.S portfolio expected to benefit from energy community adders

    U.S portfolio expected to benefit from energy community adders Energy communities to benefit from 10% tax credit adder on PTC and ITC Potential Potential Qualification Project Qualification Under Both Fossil Total Potential 25% of U.S. Portfolio Expected Classification (MW) Under Closed Fuel & Curre

  10. Slide 10: Portfolio snapshot: continued growth in the portfolio in the first quarter

    Slide 10: Portfolio snapshot: continued growth in the portfolio in the first quarter

    Portfolio snapshot: continued growth in the portfolio in the first quarter Generation, Storage, Graph, MW MWh scale Portfolio definitions Operational, under construction and pre- + + Mature construction (expected to start construction within 12 months) + 11,876 12,427 20,539 25,528 4,130 9,572 Proje

  11. Slide 11: Existing resources sufficient to complete Mature Project portfolio

    Slide 11: Existing resources sufficient to complete Mature Project portfolio

    Existing resources sufficient to complete Mature Project portfolio4 Mature Project portfolio fully funded… …Potential to generate substantial distributions from 2026+ ($m) 4.5 GW + 3.5 GWh Mature Projects Potential annual distributions from Mature Projects3 (Enlight share) $155m Excess 850 cash: 800

  12. Slide 12: Illustrative financing strategy for autonomous funding of 1.5 GW a year

    Slide 12: Illustrative financing strategy for autonomous funding of 1.5 GW a year

    Illustrative financing strategy for autonomous funding of 1.5 GW a year from 2026 onward3 1.5 GW per year anticipated uses: $270m per year 1.5 GW per year from cash flow and minority sell-downs: $270m per year 1 Annual potential cash flow: $100m Deployment Blended Capex 1 1.5 GW a year $0.9m per MW

  13. Slide 13: Reaffirming guidance for 2023

    Slide 13: Reaffirming guidance for 2023

    Reaffirming guidance for 2023 Operational Portfolio Revenue Adjusted EBITDA2 Proceeds for )MW( ($m) ($m) financial assets projects1 ($m) 290-300 Key Assumptions 54% 48% • Bjorn - Full COD by end of H1 192 188-198 • Genesis Wind – COD H2 +30% 130 1,848 102 • Apex Solar – COD by end of H1 99 No Materi

  14. Slide 14: Thank you

    Slide 14: Thank you

    en Thank you

  15. Slide 15: Gecama Solar – 250 MW + 200 MWh to COD by the end of 2024

    Slide 15: Gecama Solar – 250 MW + 200 MWh to COD by the end of 2024

    Gecama Solar – 250 MW + 200 MWh to COD by the end of 2024 Our flagship project in Europe secured via land and expand to commence construction in H2 2023 Gecama Wind is the largest operational wind farm in Spain, 329 MW Location Spain Gecama Solar would add solar and storage to existing site on the s

  16. Slide 16: 2.1 GW and 1.8 GWh of pre-construction projects largely de-risked

    Slide 16: 2.1 GW and 1.8 GWh of pre-construction projects largely de-risked

    2.1 GW and 1.8 GWh of pre-construction projects largely de-risked Project Total MW / MWh Real Estate Interconnection Permit Offtake Commentary Advanced interconnection; Co Bar Cluster 1,200 / 824 Final 200 MW and storage under negotiation n/a Negotiating environmental permits Gecama Solar 250 / 200

  17. Slide 17: Our portfolio possesses large portfolio of advanced interconnection positions

    Slide 17: Our portfolio possesses large portfolio of advanced interconnection positions

    Our portfolio possesses large portfolio of advanced interconnection positions Advanced Mature Development Development Projects 8.67GW System Impact Study Completed 55% of total portfolio in the United States 3.5 GW 3.2 GW 2.0 GW 17

  18. Slide 18: Q1 2023 EBITDA bridge: new projects drove most of the growth

    Slide 18: Q1 2023 EBITDA bridge: new projects drove most of the growth

    Q1 2023 EBITDA bridge: new projects drove most of the growth Itemizing the key drivers in Q1 2023 ($m) 1% Other Bjorn: 3 Project no longer Mainly higher hedged CPI indexation SG&A increase to classified as electricity prices in for PPA support future Gecama: Financial Asset as of Picasso (Sweden) co

  19. Slide 19: Appendix 1- Reconciliations between Net Income to Adjusted EBITDA

    Slide 19: Appendix 1- Reconciliations between Net Income to Adjusted EBITDA

    Appendix 1- Reconciliations between Net Income to Adjusted EBITDA ($ thousands) For the three months period ended 03/31/23 03/31/22 Net Income 33,276 8,871 Depreciation and amortization 13,140 7,015 Share based compensation 1,389 2,481 U.S. acquisition expense - - Other income - - Finance income (20

Source: Internet Archive copy of enlightenergy.co.il

More decks from Enlight Renewable Energy Ltd

All 58 Enlight Renewable Energy decks