Slide 1: Northwestern Energy ETAC Meeting #5, 2025 MT IRP Planning Cycle
Northwestern Energy ETAC Meeting # 5 2025 MT IRP Planning Cycle December 9, 2024
Slide 2: Modeling Inputs
Thank you Modeling Inputs
Slide 3: Base Portfolio
Base Portfolio • NorthWestern’s current generation portfolio • Includes 222MW Avista acquisition and 370MW Puget Acquisition in Colstrip Units 3 and 4 starting January 2026 • Colstrip operates until 2042 • Does not include QF’s in the current queue as NorthWestern cannot accurately project which QFs
Slide 4: Capacity Position Spreadsheet
Depreciable life of owned assets or expiration of contracted assets • Capacity Position Spreadsheet • CAO August 2024 • https://reddi.mt.gov/prweb/PRAuth2/app/reddi/69MPqGeS_UTZWHGFH6YedHAuE3y JxESf*/!STANDARD
Slide 5: Candidate Resources
"Candidate Resources Generation Storage Duration Capability No. Resource Type Scale (MW,,.) Scale (MW.,,) fiecweai (MWh) 1 |Wind 100 - - - 2 [Wind 300 - - - 3 |Solor pv 100 4 |Solar PV 300 - - - 5 |BESS - 25 2 50 6 |BESS - 25 5 125 7 =|BESS - 50 4 200 8 |BESS* - 50 5 250 9 |BESS : 50 g 400 10 |BESS
Slide 6: Forward Curves
Forward Curves • Gas • AECO • CIG • Electric • Mid-C Heavy Load • Mid-C Light Load • Coal
Slide 7: Accreditations
Accreditations • Western Resource Adequacy Program – Qualifying Capacity Contributions • WRAP Business Practice Manuals • Primarily WRAP BPM 105-Qualifying Resources • https://www.westernpowerpool.org/private- media/documents/V1.0_BPM_105_Forward_Showing_Qualifying_Resourc es_12-07-2023.pdf
Slide 8: Constraints
Constraints • Transmission • Technology • Overbuild
Slide 9: Load Forecasting
Thank you Load Forecasting
Slide 10: New Resource Cost Modeling
Thank you New Resource Cost Modeling
Slide 11: 2023 MT IRP New Resource Chart
2023 MT IRP New Resource Chart
Slide 12: Construction Timelines
Construction Timelines General Estimating Assumptions Cost Estimate Earliest NTP Earliest In- Construction Owner's Resource Type (Year) (Year) Service (Year) Schedule (Months) Costs (%) Wind 2022 2024 2026 24 10 Solar PV 2022 2024 2025 18 10 BESS 2022 2024 2025 14 5 Wind + BESS 2022 2024 2026 24 10
Slide 13: Modeling Scenarios
Thank you Modeling Scenarios
Slide 14: 2023 MT IRP Scenarios
"023 MT IRP Scenarios No. Scenario Base Case Description NorthWestern’s current portfolio including the Colstrip 222 MW acquisition beginning Jan 1, 2026. Colstrip Retirement in 2030 Colstrip 222 MW acquisition occurs in 2026 and then Colstrip retires in 2030. The model indicates replacement resourc
Slide 15: PowerSimm Access
Thank you PowerSimm Access
Slide 16: Required Information for PowerSimm Access
Required Information for PowerSimm Access • Full Name • Email Address • Cell Phone Number • Access to authenticator app
Slide 17: Questions/Comments?
Thank you Questions/Comments?