Regis Resources Limited · ASX:RRL

Regis Resources — Diggers & Dealers Mining Forum 2018

35 slides from Regis Resources's conference presentation, Aug 6, 2018

  1. Slide 1: Regis Resources Ltd – Diggers & Dealers Mining Forum August 2018

    For personal use only 1 1 REGIS RESOURCES LTD DIGGERS & DEALERS MINING FORUM AUGUST 2018

  2. Slide 2: Disclaimer & Competent Persons Statement

    DISCLAIMER & COMPETENT PERSONS 22 STATEMENT For personal use only This presentation contains only a brief overview of Regis Resources Limited and its associated entities (“Regis or RRL") and their respective activities and operations. The contents of this presentation, including matters relating to

  3. Slide 3: Regis – Where Are We At?

    3 QUALITY AUSTRALIAN GOLD BUSINESS For personal use only REGIS – WHERE ARE WE AT?  Operational excellence continues to deliver strong cash-flow Industry leading dividend payer  Exploration has only scratched the surface at Duketon Rosemont UG is just the beginning  Significant value to be unloc

  4. Slide 4: Corporate: Capital Structure and Operations Snapshot

    44 CORPORATE CAPITAL STRUCTURE For personal use only Shares on issue 504m Last price A$4.24 Market capitalisation A$2,139m Daily turnover (no. shares) 7m Unlisted options rights 8m OPERATIONS SNAPSHOT Duketon operations (WA) 10Mtpa for 350kozpa Resources (total) 7.9Moz SHARE PRICE & VOLUME Reserves

  5. Slide 5: Review of FY2018 Operations

    REVIEW OF FY2018 OPERATIONS For personal use only 55 DUKETON CONTINUES TO DELIVER STRONG CASHFLOW FY18 FY17 Ore mined (Mbcm) 4.6 4.6 Waste mined (Mbcm) 20.1 25.6 Stripping ratio (w:o) 4.4 5.6 Ore mined (Mtonnes) 10.6 10.8 Ore milled (Mtonnes) 10.0 9.8 Head grade (g/t) 1.19 1.11 Recovery (%) 94 93 Go

  6. Slide 6: Industry Leading Dividends

    INDUSTRY LEADING DIVIDENDS For personal use only 66 COMMITMENT TO DIVIDENDS Dividends Declared  Regis has paid 57 cps - A$285 million 16 14 in fully franked dividends since Oct 13 12 cents per share 8  Dividend yield on those payments has 10 8 9 averaged 3.9%* (5.6% grossed up for 6 4 8 franking c

  7. Slide 7: The Duketon Growth Story

    THE DUKETON GROWTH STORY 7 For personal use only  The open pit growth is not finished:  Over the last 3 years we have more than replaced the >1Moz* of production in OP reserves  Reserves estimated at $1,400/oz GP so there is significant inherent leverage to further production given the low operat

  8. Slide 8: Rosemont Underground Project

    ROSEMONT UNDERGROUND 88 PROJECT For personal use only

  9. Slide 9: Rosemont Maiden Underground Resource

    ROSEMONT MAIDEN 99 UNDERGROUND RESOURCE For personal use only INFERRED RESOURCES AT 2.0G/T CUT-OFF GRADE Gold Gold  Resource extends to a maximum of only 150 metres Tonnes below open pit designs Project Grade Metal (Mt) (g/t) (koz)  Grade control drilling and detailed geological mapping in the act

  10. Slide 10: Rosemont Underground Mine: Board Approves Development

    ROSEMONT UNDERGROUND MINE For personal use only 10 10 BOARD APPROVES DEVELOPMENT Sept18Q Development commencing current quarter with permitting, ordering of long lead capital items and underground mining contract tendering process. Sept18Q Update MRE (and resource categories) for recent infill & ext

  11. Slide 11: Expanded Rosemont Operation: Mined Tonnes and Ounces

    ROSEMONT UNDERGROUND MINE For personal use only 11 11 EXPANDED ROSEMONT OPERATION Rosemont Rosemont Rosemont Total Open-pit South U/G Main U/G Total Mined Tonnes (kt) 8,485 1,145 666 10,296 Mined Grade (g/t) 1.3 3.0 4.8 1.7 Total Ounces (koz) 356 112 102 570

  12. Slide 12: Expanded Rosemont Operation: Operating Cost

    ROSEMONT UNDERGROUND MINE For personal use only 12 12 EXPANDED ROSEMONT OPERATION Operating cost Open-pit Underground Total $/ounce $/ounce $/ounce Mining 407 790 554 Operating mine development capital Nil 158 61 Milling 448 132 326 Royalties (at $1,650 gold price) 74 74 74 Total operating cost 929

  13. Slide 13: Expanded Rosemont Operation: Capital Cost

    ROSEMONT UNDERGROUND MINE For personal use only 13 13 EXPANDED ROSEMONT OPERATION Capital cost Open-pit Underground Total $M $M $M Preproduction capital Nil $29.4 $29.4 LOM development capital Nil $9.7 $9.7 Total capital cost Nil $39.1 $39.1 Maximum cumulative cash outflow Nil $38.5 $38.5

  14. Slide 14: Expanded Rosemont Operation: Mining Rate

    ROSEMONT UNDERGROUND MINE For personal use only 14 14 EXPANDED ROSEMONT OPERATION Open-pit Underground Total ‘000 tpa ‘000 tpa ‘000 tpa Average mining rate 1,500 – 1,620 480 – 600 2,100  At LOM grades of the OP and UG operation (once UG mining at full mining capacity) the combined operation is expe

  15. Slide 15: Rosemont Underground: Potential for Mine Extension

    ROSEMONT UNDERGROUND 15 15 POTENTIAL FOR MINE EXTENSION ROSEMONT UNDERGROUND LONG SECTION For personal use only EXPLORATION AND EXPANSION FROM WITHIN THE DRIVE  First phase underground operation approved  This business generates a good return & pays for all the start up and mine access capital  G

  16. Slide 16: Rosemont Underground: Potential for Resource Extension

    ROSEMONT UNDERGROUND 16 16 POTENTIAL FOR RESOURCE EXTENSION For personal use only  Resource covers less than 1.3km of 4km strike and max depth of 150m below open pit designs  Infill and extensional drilling continuing  Many target areas drilling would be best done from within an underground mine

  17. Slide 17: Rosemont Underground: Q4 Drilling – Confirming the Potential

    ROSEMONT UNDERGROUND 17 17 Q4 DRILLING – CONFIRMING THE POTENTIAL DRILL RESULTS IN Q4 For personal use only  Gold hosted in a steeply east dipping 345° trending quartz-dolerite unit  Gold mineralised quartz-dolerite unit is up to 80m wide.  Q4 drilling 71 DD & RC holes for 22,907m  Q4 Results: 

  18. Slide 18: Rosemont Underground: Q4 Drilling – Confirming the Potential

    ROSEMONT UNDERGROUND 18 18 Q4 DRILLING – CONFIRMING THE POTENTIAL DRILL RESULTS IN Q4 For personal use only  Gold hosted in a steeply east dipping 345° trending quartz-dolerite unit  Gold mineralised quartz-dolerite unit is up to 80m wide.  Q4 drilling 71 DD & RC holes for 22,907m  Q4 Results: 

  19. Slide 19: Garden Well Underground: Multiple High Grade Shoots

    GARDEN WELL 19 19 UNDERGROUND PROJECT For personal use only MULTIPLE HIGH GRADE SHOOTS BELOW GARDEN WELL PIT  At least 4 high grade zones below southern end of GW pit  Including a new high grade shoot 300m south of the current pit design, 200m below surface and open down plunge

  20. Slide 20: Garden Well Underground: Significant Underground Target

    GARDEN WELL 20 20 UNDERGROUND PROJECT For personal use only SIGNIFICANT UNDERGROUND TARGET  Very significant underground target below southern end of GW open pit  Zone of continuous mineralisation 4-10m true widths & 300m N-S strike  100 – 300m below surface, dipping east and open to south  Regi

  21. Slide 21: Garden Well Underground: Significant Q4 Results

    GARDEN WELL 21 21 UNDERGROUND PROJECT For personal use only SIGNIFICANT Q4 RESULTS  Programme continued in Q4 with 15 holes completed for 2,999 metres  Significant results during the quarter include:  11m @ 6.06 g/t Au from 340m  8m @ 5.52 g/t Au from 342m  9m @ 3.42 g/t Au from 358m  3m @ 7.8

  22. Slide 22: Duketon at Depth – Mature and Well Drilled?

    DUKETON AT DEPTH – THE NEXT CHAPTER For personal use only 22 22 DUKETON MATURE AND WELL DRILLED??  Since 2006 Regis has drilled 1,400,000 metres at Duketon  This drilling has built total resources (before mining depletion) to 7.7 million oz  7.5 of 7.7Moz have been open pit resources  Modest und

  23. Slide 23: Duketon at Depth – Mature and Well Drilled?

    DUKETON AT DEPTH – THE NEXT CHAPTER For personal use only 23 23 DUKETON MATURE AND WELL DRILLED??  Since 2006 Regis has drilled over 1,400,000 metres at Duketon  This drilling has built total resources (before mining depletion) to 7.7 million oz  7.5 of 7.7Moz have been open pit resources  Modes

  24. Slide 24: Drill Holes Deeper Than 100m

    DRILL HOLES DEEPER THAN 100M For personal use only 24 24

  25. Slide 25: Drill Holes Deeper Than 200m

    DRILL HOLES DEEPER THAN 200M 25 25 15% OF TOTAL METRES For personal use only

  26. Slide 26: Drill Holes Deeper Than 300m

    DRILL HOLES DEEPER THAN 300M 26 26 7% OF TOTAL METRES For personal use only

  27. Slide 27: Drill Holes Deeper Than 400m

    DRILL HOLES DEEPER THAN 400M 27 27 3% OF TOTAL METRES For personal use only

  28. Slide 28: Duketon at Depth – Pursuing This Opportunity

    DUKETON AT DEPTH – THE NEXT CHAPTER For personal use only 28 28 PURSUING THIS OPPORTUNITY  Very limited drilling below 300m at Duketon  Where we have drilled we see prospective geological settings and encouraging gold grades  Concerted campaign of drilling at Rosemont has proved the underground t

  29. Slide 29: Rosemont Seismic Survey

    ROSEMONT SEISMIC SURVEY For personal use only 29 29 SEISMIC SURVEY - INVESTMENT DECISION IN Q1  Rosemont high grade shoots associated with stockwork veining  % of stockwork veining highest within the thickest parts of the quartz dolerite  Initial synthetic modelling by HiSeis indicates variations

  30. Slide 30: McPhillamys (NSW) – Organic Growth Project

    30 McPHILLAMYS (NSW) For personal use only 30 ORGANIC GROWTH PROJECT  Located in Central-West NSW  Well established gold mining district  Cadia, Cowal, Northparkes +45Moz*  Gold resource 2.31Moz  Gold reserve 2.03 Moz  One of Australia’s larger undeveloped open pit opportunities  PFS complete

  31. Slide 31: McPhillamys: EIS and DFS Update

    31 McPHILLAMYS For personal use only 31 EIS AND DFS UPDATE  EIS – work continuing with most areas nearing completion subject to SEARs requirements  PEA formally submitted to DPE:  Triggers DPE to provide Regis with SEARs  SEARs allow EIS to be appropriately focussed to enable regulatory assessme

  32. Slide 32: McPhillamys: Discovery Ridge Expected to Deliver Significant Value

    32 McPHILLAMYS 32 DISCOVERY RIDGE EXPECTED TO DELIVER SIGNIFICANT VALUE TO MGP For personal use only  100% owned Discovery Ridge deposit located 32km away from McPhillamys by major highway  MRE of 13.84Mt @ 1.1g/t for 501koz*  Remaining results returned from Q3 RC drilling: • 35m @ 2.54g/t Au fro

  33. Slide 33: Recap of Presentation

    RECAP OF PRESENTATION For personal use only 33 33  Q4 gold production 92,008 ounces at AISC of A$982/oz  Another very strong operational quarter at the Duketon project  FY18 production 361,373 oz at AISC of $901/oz  Production at upper end of FY18 guidance & AISC below bottom of guidance  Recor

  34. Slide 34: Appendix: JORC Compliant Ore Reserve Estimates March 2018

    APPENDIX 1 JORC COMPLIANT 34 34 ORE RESERVE ESTIMATES 31 MARCH 2018 For personal use only Group Ore Reserves as at 31 March 2018 Gold Proved Probable Total Ore Reserve Competent Cut-Off Tonnes Gold Grade Gold Metal Tonnes Gold Grade Gold Metal Tonnes Gold Grade Gold Metal Project Type Person3 (g/t)2

  35. Slide 35: Appendix: JORC Compliant Mineral Resources March 2018

    APPENDIX 2 35 35 JORC COMPLIANT MINERAL RESOURCES 31 MARCH 2018 For personal use only Group Mineral Resources as at 31 March 2018 Gold Measured Indicated Inferred Total Resource Competent Cut-Off Tonnes Gold Grade Gold Metal Tonnes Gold Grade Gold Metal Tonnes Gold Grade Gold Metal Tonnes Gold Grade

Regis Resources — Diggers & Dealers Mining Forum 2018 on 6ix