Filo Mining — Investor Presentation (January 2022)
33 slides from Filo Mining's investor presentation, January 2022
Slide 1: Advancing the Filo del Sol Copper-Gold-Silver Project in South America
ADVANCING THE FILO DEL SOL COPPER-GOLD-SILVER PROJECT IN SOUTH AMERICA Corporate Presentation – January 2022 A Lundin Group Company www.filo-mining.com TSX: FIL | Nasdaq First North Growth Market: FIL | OTCQX: FLMMF
Slide 2: Cautionary Statement
CAUTIONARY STATEMENT Certain statements made and information contained in this presentation constitutes “forward-looking information” and “forward- Estimates of Mineral Reserves and Mineral Resources looking statements” within the meaning of applicable securities legislation (collectively, “forward-
Slide 3: Filo Mining Corp. Company Profile
FILO MINING CORP. COMPANY PROFILE SHARE OWNERSHIP Lundin Family Trusts South American Project – Filo del Sol (100% interest) Board & Management Current Indicated Resource of: Advanced Institutions Exploration » 4.4 Million oz Gold Other » 147 Million oz Silver Company » 3.1 Billion lbs Copper CAPITA
Slide 4: Filo del Sol Project
FILO DEL SOL PROJECT Filo del Sol hosts a high-sulphidation epithermal copper-gold-silver deposit associated with a large porphyry copper-gold system. Located in San Juan, Argentina & Chile » Vicuña – an emerging giant copper district » Mining Integration and Complementation Treaty for cross-border
Slide 5: Investment Highlights
INVESTMENT HIGHLIGHTS FILO DEL SOL: IMPOSSIBLE TO IGNORE Lukas Lundin comments, Existing Cu-Au-Ag resource, backstopped by a robust oxide “…the potential size and project. scale of the Filo del Sol deposit is unparalleled to any project I have been Outstanding drilling results, extending continuous
Slide 6: Why Copper?
WHY COPPER? » Copper fundamentals are strong; recent price movement upwards of $4.50/lb, declining global inventories • Lack of Investment: coming out of a cycle of depressed copper prices, limited new copper discoveries • Demand driving by Electrification, Infrastructure: copper is the “Green” meta
Slide 7: Exploration
EXPLORATION Filo Mining | Corporate Presentation
Slide 8: Filo del Sol – Geology
FILO DEL SOL – GEOLOGY A CLUSTER OF MINERALIZATION » Clustering of different types Secondary Cu-Au-Ag “Oxide” zone Epithermal Au-Ag-Cu of mineralization styles all in one deposit » Repeated, overlapping episodes of mineralization » Rare, large scale copper mineral upgrading process » A dumping groun
Slide 9: Results Summary
RESULTS SUMMARY HIGHLIGHT HOLES: FSDH032: FSDH041: total total intercept of intercept of 1,009m @ 858m @ 0.95% CuEq 1.80% CuEq FSDH046: FSDH048: total total intercept of intercept of 1,378m @ 1,081m @ 0.71% CuEq 0.88% CuEq FSDH054: FSDH055A: total partial intercept of intercept of 1,224m @ 64m @ 1.2
Slide 10: Jan 12, 2022 Results from FSDH055A
FILO DEL SOL – COPPER-GOLD-SILVER JAN 12, 2022 RESULTS FROM FSDH055A » Drilling over the past two 64m @ 1,214 g/t Ag seasons has extended the known, flat-lying silver zone over more than 3km strike » FSDH055A retuned this highest- grade intersection on the project to date: 64m @ 1,214 gpt Ag and 0.4
Slide 11: Vertical Sections (East-West)
VERTICAL SECTIONS (EAST-WEST) +400m North +200m North Slide 11 Filo Mining | Corporate Presentation
Slide 12: Filo in Manhattan, London, Stockholm, Toronto (scale comparison)
FILO IN MANHATTAN FILO IN LONDON 5 km 5 km FILO IN STOCKHOLM FILO IN TORONTO 5 km 5 km Slide 12
Slide 13: Filo del Sol – Size & Grade
FILO DEL SOL SIZE & GRADE From To Length Hole-ID Potro Cu % Au g/t Ag g/t CuEq %1 (m) (m) (m) Cliffs - One of the largest steam- FSDH041 Filo – 7km 188.0 1,046.0 heated 858.0 alteration 0.86 zones 0.70 in the Andes 1.80 48.1 incl 376.0 1,046.0 670.0 1.07 0.85 60.9 2.23 incl 780.3 943.3 163.0 2.31 2.
Slide 14: Comparison with Global Copper Intercepts
COMPARISON WITH GLOBAL COPPER INTERCEPTS Best holes over the past 2 years with Copper as the primary commodity Interval CuEq Grade x Date Hole Number Project Country Company From (metres) To (metres) CuEq (%) Source Document (metres) Interval¹ (%-m) 2020-02-24 VHD037 Onto Indonesia PT Sumbawa Timur
Slide 15: Development of an Exploration Target
DEVELOPMENT OF AN “EXPLORATION TARGET” BASED ON PREDICTED VOLUMES AND AVERAGED GRADES FROM SAMPLING THE DEEP DRILLING The quantity and grade of this exploration target is conceptual in nature, and there has been insufficient exploration to define a mineral resource in this area. It is uncertain if f
Slide 16: Positive PFS (Jan 2019)
POSITIVE PFS (JAN 2019) Filo Mining | Corporate Presentation
Slide 17: Filo del Sol – PFS Results Summary – Oxides Only
FILO DEL SOL – PFS RESULTS SUMMARY – OXIDES ONLY Cu Copper After-Tax NPV (8%) $1.28b Avg. Annual Cu Production 67 kt Au Gold After-Tax IRR 23% Payback 3.4 Yrs Avg. Annual Au Production 159 koz Ag Silver C1 Cash Cost $1.23/lb CuEq Avg. Annual Ag Production 8,653 koz Slide 17 Filo Mining | Corporate P
Slide 18: Filo del Sol Project Economics – Oxides Only
FILO DEL SOL PROJECT ECONOMICS – OXIDES ONLY PFS SENSITIVITY TO METALS PRICES Metals Prices After-Tax NPV8% After-Tax IRR (Cu $/lb) / (Au $/oz) / (Ag $/oz) ($) (%) PFS Case $3.00 / $1,300 / $20 $1.28 B 22.7% $3.50 / $1,550 / $23 $1.95 B 28.9% $4.00 / $1,800 / $26 $2.61 B 34.6% $4.50 / $2,050 / $29 $
Slide 19: Pre-Feasibility Results – Oxides Only
PRE-FEASIBILITY RESULTS – OXIDES ONLY FILO DEL SOL – PFS RESULTS – January 2019 Pre-Tax NPV (8%) ($B) $1.86 ANNUAL METAL Pre-Tax IRR (%) 27% PFS METALS PRODUCTION PROFILES After-Tax NPV (8%) ($B) $1.28 PRICES ASSUMED Payable Copper After-Tax IRR (%) 23% 90 80 70 Undiscounted After-Tax Cash Flow ($B)
Slide 20: Environmental, Social and Governance (ESG)
ENVIRONMENTAL, SOCIAL AND GOVERNANCE (ESG) SUPPORTED BY THE LUNDIN FOUNDATION - LAYING THE STRATEGIC GROUNDWORK FOR RESPONSIBLE MINERAL DEVELOPMENT PURPOSE Unlock a world-class asset for the green economy through responsible exploration Our commitment to responsible exploration involves engaging in
Slide 21: Proven Track Record – Management and Board
PROVEN TRACK RECORD EXPERTISE & LEADERSHIP DRAWN FROM THE LUNDIN GROUP OF COMPANIES Management JAMIE BECK BOB CARMICHAEL JEFF YIP TREVOR D’SA DIEGO CHARCHAFLIE President & CEO VP Exploration CFO VP Corporate South American GM Former VP, Corporate Senior exploration geologist. Senior financial execut
Slide 22: Next Steps
NEXT STEPS Filo Mining | Corporate Presentation
Slide 23: Exploration Plans
EXPLORATION PLANS 3 KEY EXPLORATION OBJECTIVES THIS SEASON Define the high-grade zone around Breccia 41 Aurora Zone - focus on developing a comprehensive geological model Exploration to the North & South – find the edges of the system. Slide 23 Filo Mining | Corporate Presentation
Slide 24: Next Steps & Outlook
NEXT STEPS & OUTLOOK YEAR-ROUND DRILLING THROUGHOUT 2022 WITH UP TO 11 RIGS WHAT’S NEXT » Drilling underway with 5 rigs on site. » Planning to add 2 additional rigs in Feb, and 4 more by mid-year, for a total of up to 11 rigs in 2022 » 5 holes currently underway (shown in red) will focus on Breccia
Slide 25: Vicuña: A Giant Copper District in the Making
VICUÑA: A GIANT COPPER DISTRICT IN THE MAKING WHEN YOU FIND SOMETHING BIG, THINK BIGGER Giant in size, rare by nature Potro Cliffs – One of the largest steam- heated alteration zones in the Andes » Vicuña is an emerging giant copper-gold- silver district controlled by Lundin Group junior companies.
Slide 26: Contact Us
Filo Mining | Corporate Presentation CONTACT US filo-mining.com Filo Mining Corp. Suite 2000 - 885 West Georgia Street Vancouver, BC, V6C 3E8 Canada FOR MORE INFORMATION CONTACT Trevor D’Sa Robert Eriksson Investor Relations Canada Investor Relations and Media Sweden info@filo-mining.com reriksson@r
Slide 27: Appendix
APPENDIX Filo Mining | Corporate Presentation
Slide 28: Indicated and Inferred Resource
INDICATED AND INFERRED RESOURCE Cu Cu INDICATED 3.1 Billion lbs Cu Copper INFERRED 1.0 Billion lbs Au Au INDICATED 4.4 Million oz Au Gold INFERRED 1.8 Million oz Ag Ag INDICATED 146.9 Million oz Ag Silver INFERRED 34.8 Million oz Refer to slide 31 for additional details regarding the reporting of th
Slide 29: Mineral Resource
MINERAL RESOURCE Tonnes Cu Au Ag Lbs Cu Ounces Au Ounces Ag Zone Cutoff Category (millions) (%) (g/t) (g/t) (millions) (thousands) (thousands) Indicated 349.6 0.34 0.32 12.6 2,656 3,623 141,364 Oxide * See notes Inferred 103.9 0.26 0.32 8.7 585 1,083 29,067 Indicated 75.5 0.27 0.34 2.2 451 813 5,374
Slide 30: Mineral Resource
MINERAL RESOURCE Slide 30 Filo Mining | Corporate Presentation
Slide 31: Pre-Feasibility Layout
PRE-FEASIBILITY LAYOUT Slide 31 Filo Mining | Corporate Presentation
Slide 32: Probable Mineral Reserves
PROBABLE MINERAL RESERVES FILO DEL SOL MINERAL RESERVE STATEMENT (@ 0.01 $/T NVPT CUT-OFF) Tonnage Grade Contained Metal Category (all domains) (Mt) Cu (%) Au (g/t) Ag (g/t) NVPT ($/t) Cu (M lbs) Au (K oz) Ag (K oz) Proven _ _ _ _ _ _ _ _ Probable 259.1 0.39 0.33 15.1 25.30 2,226 2,764 126,028 Total
Slide 33: Lundin Group
LUNDIN GROUP A HISTORY OF CREATING VALUE FOR SHAREHOLDERS IN ARGENTINA The Lundin Group of Companies has a record of creating substantial value for shareholders. Past projects have generated some $15.8 billion. Shareholder Return on Investment* 1757% 1041% 1091% 961% 850% 558% 609% 352% 139% Lundin