5e Advanced Materials, Inc. · NASDAQ:FEAM

5e Advanced Materials — Corporate Update (December 2023)

11 slides from 5e Advanced Materials's corporate update, Dec 19, 2023

  1. Slide 1: Investor Update Call

    Investor Update Call Enabling America’s Clean Energy Economy : FEAM 5E Advanced Materials : 5EA December 19, 2023

  2. Slide 2: Disclaimer: Forward-Looking Statements

    Disclaimer FORWARD-LOOKING STATEMENTS The information in this Presentation includes “forward-looking statements” within the meaning of the Private Securities Litigation Reform Act of 1995, as amended. All statements other than statements of historical fact included in this presentation regarding our

  3. Slide 3: Disclaimer (Continued)

    Disclaimer (Continued…) No Offer or Solicitation This document is for information purposes only, and is not intended to and does not constitute an offer to sell or the solicitation of an offer to subscribe for or buy or an invitation to purchase or subscribe for any securities or the solicitation of

  4. Slide 4: Significant Milestones Achieved: 2HCY 2023

    December 12/6 – 5E Announces Restructuring Support Agreement September 9/21 – 5E Granted Approval from EPA to Conduct Step-Rate Testing (SRT) October 10/8 – Commencement of SRT Protocols 10/16 – Successful Completion of SRT 10/26 – SRT Results Delivered to EPA November 11/22 – 5E Receives EPA Author

  5. Slide 5: Expected Major Milestones for CYQ1 2024

    Expected Major Milestones for CYQ1 2024 Production provides design basis for the commercial plant and product to be qualified by strategic customers

  6. Slide 6: Transaction Highlights

    Transaction Highlights Key Terms Equity Up to $35 mm, $10 mm committed. $1.025 per share (50% discount). Note Amendments New conversion price, $1.5375 per share. Maturity extended one-year to August 15, 2028. Paid in-kind interest rate to 10% from 6%. Elimination of issuer conversion feature. Minimu

  7. Slide 7: Planned Project Schedule

    Planned Project Schedule CY Indicative Schedule 1H23 2H23 1H24 2H24 1H25 2H25 1H26 2H26 EPA Authorization to Inject Wellfield Commissioning Boric Acid/Gypsum Commissioning Initial Plant Operation / Data Collection FEL-2 Study FEL-3 Study Detailed Engineering & Construction Commission of Phase 1 - 90

  8. Slide 8: Target Long-Term Value Creation

    Target Long-Term Value Creation 8 Department of Energy (DOE) ATVM / Loan Program Office Department of Defense (DOD) Defense Production Act, DPA Title III U.S. Department of Agriculture (USDA) Inflation Reduction Act Royalty Structure Mineral Rights Traditional Equity Capital Market / Shareholders CO

  9. Slide 9: Executive Summary

    Executive Summary EPA approval authorizes 5E to commence mining and plant operations Proposed recapitalization plan is the optimal solution to solve short-term funding needs 5E has an aggressive three-month plan to commission the plant and start production Initial production supports the advancement

  10. Slide 10: The 5E Advanced Materials Team

    The 5E Advanced Materials Team

  11. Slide 11: Thank You

    Alpha IR Group Davis Snyder or Joseph Caminiti FEAM@alpha-ir.com (312) 445-2870 Thank You J.T. Starzecki CHIEF MARKETING OFFICER jstarzecki@5eadvancedmaterials.com

5E Advanced Materials — Corporate Update (December 2023) on 6ix