  1. Slide 1: Egoli Project Feasibility Study Presentation July 2020

    Egoli Project FEASIBILITY STUDY PRESENTATION JULY 2020

  2. Slide 2: Disclaimer and Forward Looking Statements

    DISCLAIMER AND FORWARD LOOKING STATEMENTS The name 'Presenter' refers to Pan African Resources PLC and its advisors, subsidiaries or affiliated companies. This presentation has not been filed, lodged, registered or approved in any jurisdiction and viewers of this document should keep themselves info

  3. Slide 3: Overview of Presentation

    OVERVIEW OF PRESENTATION • Egoli Project - Overview > History and background > Highlights > Financial matrix • Development plan and mine design • Infrastructure • Way forward • Appendix 3

  4. Slide 4: Egoli Project - Overview

    PAN AFRICAN @ RESOURCES ) —— Egoli Project - Overview

  5. Slide 5: Egoli Project – Overview: History & Background, Location

    EGOLI PROJECT – OVERVIEW History & background Location • Harmony Gold previously exploited Evander Mines’ No.7 Shaft orebody, EGM Evander Gold Assets with development towards the Egoli orebody Evander Gold Mining Operation Evander Gold Underground Projects Evander Gold Tailings Projects > In 2009, d

  6. Slide 6: Egoli Project – Overview: Highlights

    EGOLI PROJECT – OVERVIEW Highlights • Long-life, low cost brownfields asset, capitalising on established infrastructure • Initial Life of Mine (LOM) of 9 years - annual gold production of approximately 72,000 ounces at an average head grade of 6,61g/t - based on current Measured and Indicated (M&I)

  7. Slide 7: Egoli Project – Overview: Financial Matrix

    EGOLI PROJECT – OVERVIEW Financial matrix • Materially lower capital investment when benchmarked against other development projects of similar scale • Compelling and robust economic returns: > Payback period from project inception – 3,8 years > NPV10,71 - R2,010 million ($131,25 million) > Project I

  8. Slide 8: Development plan and mine design

    Development plan and mine design

  9. Slide 9: Egoli Project - Schematic

    EGOLI PROJECT - SCHEMATIC • The Egoli orebody is approximately 1,75 km in tramming distance from No.7 Shaft > No.7 Shaft is currently utilised for hoisting run-of-mine material from No. 8 Shaft Pillar mining to the Kinross metallurgical plant > Proximity to No.7 Shaft results in better Mine Call Fac

  10. Slide 10: Gold Production Profile (Current Reserves)

    GOLD PRODUCTION PROFILE (CURRENT RESERVES)* *Potential to extend LOM to 14 years by converting Inferred Resources to Measured and Indicated Resources as underground development proceeds MCF = 85% PCF = 95% Gold Produced (kOz) 120 100 80 60 ’000 Oz 40 20 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Ye

  11. Slide 11: Infrastructure

    PAN AFRICAN@ RESOURCES ) —— Infrastructure

  12. Slide 12: Utilising Existing Infrastructure

    UTILISING EXISTING INFRASTRUCTURE • Upgrades to: > Change house and laundry > Offices and workshop • Refurbishment of: > Ventilation fan > Compressors > Lamp room > MV consumer substation > Security, fencing and access control Kinross Plant Fence 7 Shaft Complex Fence Access Roads 12

  13. Slide 13: Way forward

    PAN AFRICAN@ RESOURCES ) —— Way forward

  14. Slide 14: Way Forward

    WAY FORWARD • Development plan > Detailed project scheduling and planning – to be completed: Q1 FY21 • No.7 Shaft and Kinross Plant infrastructure: > Dewatering to commence: Q1 FY21 > Preliminary refurbishment: Q1 FY21 > Placing orders for long-lead equipment: Q2 FY21 > Commence with underground equ

  15. Slide 15: Appendix

    PAN AFRICAN@ RESOURCES ) —— Appendix

  16. Slide 16: Evander Mines - History

    EVANDER MINES - HISTORY • 1951 Evander goldfield discovered • 1956 Sinking of first shafts (Winkelhaak No.1 & No.3 Shaft) • 1958 (July) First gold pour Three other mining complexes developed afterwards namely: Leslie, Bracken and Kinross • 1996 Four mining companies consolidated to form Evander Gold

  17. Slide 17: Evander Basin – World Class Orebody

    EVANDER BASIN – WORLD CLASS OREBODY Pipeline of organic growth projects 17

  18. Slide 18: Mineral Resources and Reserves Statement – Egoli Project

    MINERAL RESOURCES AND RESERVES STATEMENT – EGOLI PROJECT Mineral Resources Category As at 30 June 2019 Mt Grade g/t Tonnes Au Moz Au Measured 0.44 8.60 3.8 0.12 Indicated 2.94 9.85 28.9 0.93 Total M & Ind. 3.38 9.69 32.7 1.05 Inferred 6.26 9.68 60.6 1.95 Total 9.64 9.69 93.3 3.00 • All Mineral Resou

  19. Slide 19: Development plan and mine design

    Development plan and mine design

  20. Slide 20: Project Development Plan

    PROJECT DEVELOPMENT PLAN To commence with operations at the Egoli Project will require: • Refurbishment of the existing Kinross gold processing plant, No.7 and No.7A vertical shafts and winders • Re-equipping of the 15 Level tramming path to access the No.3 Decline system and re-equip to 19 Level wh

  21. Slide 21: Mining Layout

    MINING LAYOUT Development Sequence • Main Development (Decline dip conveyor, No.3 Decline and East block Decline and Incline) > Use of a double boom electrohydraulic drill rig – broken rock hauled by LHDs to dip conveyor loading point > The No.3 Decline conveyor will tip broken rock into main declin

  22. Slide 22: Mining Layout – Conventional Breast Mining

    MINING LAYOUT – CONVENTIONAL BREAST MINING Stope establishment Crosscut dev = 6 mnth Raise Dev = 9 mnth Ledging (3 crews) = 3.8 mnth Total = 18.8 mnth 22