Slide 1: Chapter 2: Growth and Sustainability
Chapter 2: Growth and Sustainability TZMI Congress 2023 Singapore 15-17 November 2023 Patrick Mutz Managing Director Image Resources 1 NL ASX: IMA
Slide 2: Disclaimer and Forward-Looking Statements
Disclaimer and Forward-Looking Statements This presentation/document has been prepared by the management of Image Resources NL ("Image”, “IMA“, or “the Company”). The information presented includes an indicative outlook of the business activities of Image for the calendar year (CY) 2023 and beyond a
Slide 3: Company History
Company History Successful Project Development Transitioned from advanced explorer to active miner in 2018 Boonanarring Project, 80km north of Perth in Western Australia On-time and on-budget construction Successful Project Operations Ramped to nameplate capacity in only 2nd month of ope
Slide 4: Project Area Location Map
Project Area Location Map PERTH 4
Slide 5: Project Location Map – Initial Portfolio
Project Location Map – Initial Portfolio Initial Tenement Portfolio (2017) 1,232 km2 ATLAS - planned mining to commence FY2024 12 Project Areas; 100%-owned 29Mt Ore Reserves Ore Reserves (Dec 2022) 93Mt dry mining Mineral Resources 5.5 million tonnes 236Mt dredge mining Mineral Resources 9.2% THM 20
Slide 6: Contributors to Success at Boonanarring
Contributors to Success at Boonanarring Development Contributors Pre-commissioned equipment (i.e.: USED) Simple business model (HMC only in bulk) Operational Contributors Very high grade; 8% THM, 80% VHM Zircon rich; 28% zircon in THM Coarse grained minerals; D50 180 micron Financial
Slide 7: Transition to Active Miner
Transition to Active Miner Active miner – Chapter 1 One mine, one product, one customer 2017 BFS plan; mine and process ore at Boonanarring then relocate equipment and mine and process ore at Atlas (series operations) Still working 2017 plan; completed ore processing at Boonanarring Sep 2023
Slide 8: Chapter 1 – Active Miner
Chapter 1 – Active Miner Chapter 1 Projects; operated in series Project Million THM Slimes Oversize Zircon Rutile Leucoxene Ilmenite VHM Strip Ilmenite Tonnes % % % % % % % % Ratio %TiO2 Boonanarring 15.8 8.0 15 4 28 2.5 2.0 47 80 7:1 55 (actual) Atlas 5.5 9.2 15 5 12 8 5 53 79 1:1 60 (Ore Reserve
Slide 9: Transitioning to Chapter 2
Transitioning to Chapter 2 Chapter 2 Philosophy and Ambitions Multiple mines, multiple products, global market + value-add Chapter 2 ambitions are possible following: Two strategic acquisitions of mineral sands projects in Western Australia in 1H 2022 • Eneabba Tenements added ~200mt of Mine
Slide 10: Project Location Map – Expanded Portfolio
Project Location Map – Expanded Portfolio Eneabba Tenements Acquisition 232 km2 Initial Portfolio of Tenements 1,232 km2 McCalls Project Acquisition 224 km2 10
Slide 11: Transitioning to Chapter 2
Transitioning to Chapter 2 Chapter 2 Philosophy and Ambitions Multiple mines, multiple products, global market + value-add Chapter 2 ambitions are possible following: Two strategic acquisitions of mineral sands projects in Western Australia in 1H 2022 • Eneabba Tenements added ~200mt of Mine
Slide 12: Growth & Sustainability Strategy
Growth & Sustainability Strategy Chapter 2 Projects Project Million THM Slimes Oversize Zircon Rutile Leucoxene Ilmenite VHM Strip Ilmenite Tonnes % % % % % % % % Ratio %TiO2 Bidaminna 123 1.8 4 4 5 4.1 13 72 94 1:1 65 (Ore Reserves) Yandanooka 61 3.0 15 11 12 3.5 3.6 70 89 <1:1 62 (Mineral Resour
Slide 13: Chapter 2 – Projects and Value-Adding Steps
Chapter 2 – Projects and Value-Adding Steps Diverse 100%-Owned Development Pipeline in Western Australia (JORC 2012) Bidaminna – 123mt Ore Reserves1 at 1.8% HM (DFS underway) 10 yrs.* Yandanooka2 – 60mt Mineral Resources1 at 3.0% HM (PFS underway) ?? yrs.** McCalls2 – 3,610mt Mineral Resourc
Slide 14: Changing Value Proposition
Changing Value Proposition (CY2021‐22 relative pricing) highest mass Convert ilmenite to synthetic rutile lowest price Line graphs of mass contribution in HMC added Bar graphs represent rough min and max commodity for various Image projects prices across CY2021-22 (for relative comparison only).
Slide 15: Preliminary Conceptual Plan
Preliminary Conceptual Plan Cautionary statement: The following conceptual plan should only be read in conjunction with the Disclaimer and Forward-Looking Statements at the beginning of this presentation. The information provided in the following preliminary plan is conceptual and aspirational and s
Slide 16: Preliminary Conceptual Development Plan – Chapter 1
Preliminary Conceptual Development Plan Image Resources NL Growth and Sustainability - Preliminary Conceptual Development Plan 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Boonanarring & Atlas Feasibility Study Boonanarr
Slide 17: Preliminary Conceptual Development Plan – Chapter 2
Preliminary Conceptual Development Plan Image Resources NL Growth and Sustainability - Preliminary Conceptual Development Plan 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 Boonanarring & Atlas Feasibility Study Boonanarr
Slide 18: Bidaminna Pre-Feasibility
Bidaminna Pre-Feasibility PFS Highlights: Pre-tax NPV8: A$192 million Pre-tax IRR8: 28% Capital estimate: A$194 million Capital payback (post first revenue): 3.8 years EBITDA: A$379 million Forecast mine-life: 10.5 years Total Heavy Mineral Concentrate (“HMC”) production: 2.1 Mt Ore Re
Slide 19: Corporate Snapshot
Corporate Snapshot ASX Code IMA Top Five Shareholders Board of Directors Murray Zircon PL 15.9% Bob Besley – Chair (Ind.) Share Price A$0.07 (24 Oct 23) Vestpro International Limited 13.2% Patrick Mutz – Managing Director Shares on Issue 1,081m HSBC Custody Nominees 8.0% Aaron Chong Veoy Soo – NED (
Slide 20: For further information
For further information Image Resources NL info@imageres.com.au Office: +61 8 9485 2410 Level 2, 7 Ventnor Avenue West Perth, WA 6005 PO Box 469, West Perth, WA 6872 www.imageres.com.au 20
Slide 21: Mineral Resources and Ore Reserves Statement
Mineral Resources and Ore Reserves Statement 21
Slide 22: Mineral Resources and Ore Reserves Statement
Mineral Resources and Ore Reserves Statement 22
Slide 23: Mineral Resources and Ore Reserves Statement
Mineral Resources and Ore Reserves Statement 23
Slide 24: Mineral Resources and Ore Reserves Statement
Mineral Resources and Ore Reserves Statement 24
Slide 25: Mineral Resources and Ore Reserves Statement
Mineral Resources and Ore Reserves Statement 25
Slide 26: Mineral Resources and Ore Reserves Statement
Mineral Resources and Ore Reserves Statement 26
Slide 27: Mineral Resources and Ore Reserves Statement
Mineral Resources and Ore Reserves Statement 27