Slide 1: Williams Capital Group Transmission Seminar
NEW YORK, NY • JANUARY 11, 2012 Williams Capital Group Transmission Seminar William Gausman Senior Vice President, Strategic Initiatives

Slide 2: Safe Harbor Statement
Safe Harbor Statement Some of the statements contained in today’s presentation with respect to Pepco Holdings, Pepco, Delmarva Power and Atlantic City Electric, and each of their respective subsidiaries, are forward-looking statements within the meaning of the U.S. federal securities laws and are su

Slide 3: Our Businesses
Our Businesses Power PHI Service Territory Delivery Forecast Business Mix* 90 - 95% Energy Services 5 - 10% * Percentages based on projected operating income for 2011 - 2015 Note: See Safe Harbor Statement at the beginning of today’s presentation. 2

Slide 4: Diverse, Stable Service Territory
Diverse, Stable Service Territory Regulatory Diversity, 2010 Rate Base Customer Diversity, 2010 MWh Sales Residential 37% Government 10% Industrial Commercial 6% 47% Diversified customer base and more stable employment trends help to minimize recessionary impacts on our service territory 3

Slide 5: Rate Base Summary
Rate Base Summary Distribution is 77% and Transmission is 23% of our 2010 year-end rate base Note: See Safe Harbor Statement at the beginning of today’s presentation. 4

Slide 6: Capital Expenditures - 2012 - 2016 Forecast
Capital Expenditures - 2012 - 2016 Forecast Distribution is 72% and Transmission is 28% of Power Delivery Capital Expenditures forecasted over the next five years (1) Assumes Mid-Atlantic Power Pathway (MAPP) in-service date of 2020. (2) Reflects the remaining anticipated reimbursement pursuant to a

Slide 7: Transmission Overview
Transmission Overview Note: See Safe Harbor Statement at the beginning of today’s presentation. 6

Slide 8: Generation Deactivations
Generation Deactivations Approximately 847 MW of generation within the PHI footprint and surrounding area have been retired in the last 5 years Approximately 2415 MW have announced future deactivation dates Source: http://www.exeloncorp.com/powerplants/oystercreek/Pages/profile.aspx http://www.pjm.c

Slide 9: Need for Transmission Enhancements
Need for Transmission Enhancements • Need for new transmission lines is not primarily driven by load growth • NERC reliability requirements have added new operating requirements and, as a result, are a significant driver for new transmission facilities across all three operating companies • Generati

Slide 10: Integrating Renewable Resources into the PHI System
Integrating Renewable Resources into the PHI System • The PHI service territory offers a unique opportunity with one of the greatest concentrations of strong off-shore wind resources existing along the Mid-Atlantic region • In order to develop large scale off-shore wind projects, additional transmis

Slide 11: Need For Advanced Technologies
Need For Advanced Technologies • The transmission systems of the future will incorporate advanced technologies to control flow, manage voltage variations and improve monitoring for operations and maintenance requirements • PHI is incorporating these technologies into the systems we are building toda

Slide 12: Benefits of New Technologies
Benefits of New Technologies SVCs and HVDC • High speed switching to respond to changing conditions on the transmission system • Increases grid voltage by supplying reactive power • Decreases grid voltage by consuming reactive power • Control flows on the system • HVDC can provide black start and Bi

Slide 13: Benefits of New Technologies
Benefits of New Technologies Aluminum Conductor Composite Reinforced • Stable, compatible (ACCR) • Less sag at high temperatures - maintain or Aluminum materials, Oxide improve clearances at high energy levels Fibers even at high temperatures • Higher strength-to-weight ratio - maintain or improve s

Slide 14: Benefits of New Technologies
Benefits of New Technologies Phasor Monitoring Units and Dissolved Gas Analysis • Measurements of voltages and currents, which are time-tagged with high precision via GPS time signal receivers • Operators can make better control decisions • Enhanced post-disturbance analysis • Continuous asset monit

Slide 15: Mid-Atlantic Power Pathway - Project Update
Mid-Atlantic Power Pathway - Project Update • PJM provided notice to PHI in August 2011 that the MAPP project in-service date will be delayed until 2019 - 2021 • PHI suspended most permitting, engineering, and environmental studies • Maryland PSC approved our request to delay the procedural schedule

Slide 16: PHI - Positioned for Growth
PHI - Positioned for Growth • $5.6 billion in planned infrastructure investment over 5 years, with 28% in transmission • Significant transmission growth to support generation retirements and NERC policy compliance • Timely transmission cost recovery by FERC formula and incentive rates • Reasonable r

Slide 17: Williams Capital Group Transmission Seminar
NEW YORK, NY • JANUARY 11, 2012 Williams Capital Group Transmission Seminar William Gausman Senior Vice President, Strategic Initiatives

Slide 18: Appendix
Appendix y Pepco Holdings Inc

Slide 19: Transmission Projects 2012 - 2016
Transmission Projects 2012 - 2016 ACE Notes: 1.Common Mode outages include line faults associated with stuck breaker, double circuit tower line, and faulted circuit breakers and buses 2.N-1-1 outages ensure facilities can be operated within normal thermal and voltage limits after N-1 (single) contin

Slide 20: Transmission Projects 2012 - 2016 (DPL)
Transmission Projects 2012 - 2016 DPL Note: See Safe Harbor Statement at the beginning of today’s presentation. 19

Slide 21: Capital Expenditures Forecast - Updated November 2011
Capital Expenditures Forecast - Updated November 2011 (1) Reflects the remaining anticipated reimbursement pursuant to awards from the U.S. DOE under the ARRA. (2) Installation of AMI in New Jersey is contingent on regulatory approval ($9 million in 2015, $92 million in 2016). (3) Assumes MAPP in-se

Slide 22: Forecast Capital Expenditures Comparison
Forecast Capital Expenditures Comparison * Amounts are net of anticipated reimbursement pursuant to awards from the U.S. DOE under the ARRA. Note: See Safe Harbor Statement at the beginning of today’s presentation. 21

Slide 23: Distribution Rate Cases - Pending Pepco - District of Columbia
Distribution Rate Cases - Pending Pepco - District of Columbia Regulatory lag mitigation measures proposed: • Reliability Investment Recovery Mechanism (RIM) • Fully forecasted test years Drivers of requested increase: •Rate base growth/reliability investments •Investment in Advanced Metering Infras

Slide 24: Distribution Rate Cases - Pending Atlantic City Electric - New Jersey
Distribution Rate Cases - Pending Atlantic City Electric - New Jersey Drivers of requested increase: • Rate base growth/reliability investments Regulatory lag mitigation measure proposed in a separate filing made October 18, 2011: • Request the continuance and expansion of the recently completed Inf

Slide 25: Distribution Rate Cases - Pending Delmarva Power - Delaware Electric
Distribution Rate Cases - Pending Delmarva Power - Delaware Electric Two regulatory lag mitigation measures proposed Drivers of requested increase: in filing: • Rate base growth/reliability investments •Reliability Investment Recovery Mechanism - provides full • Increase in operating expenses and ti

Slide 26: Distribution Rate Cases - Pending Delmarva Power - Maryland
Distribution Rate Cases - Pending Delmarva Power - Maryland Regulatory lag mitigation measures proposed in Drivers of requested increase: filing: • Rate base growth/reliability investments •Reliability Investment Recovery Mechanism (RIM) • Recovery of Hurricane Irene restoration • Fully forecasted t

Slide 27: Distribution Rate Cases - Pending Pepco - Maryland
Distribution Rate Cases - Pending Pepco - Maryland Regulatory lag mitigation measures proposed in Drivers of requested increase: filing: • Rate base growth/reliability investments •Reliability Investment Recovery Mechanism (RIM) • Recovery of Hurricane Irene restoration •Fully forecasted test years

Slide 28: Distribution Rate Cases - The Current Cycle
Distribution Rate Cases - The Current Cycle • Filing Cycle Status – Pepco DC Pending - Filed July 2011 – Atlantic City Electric NJ Pending - Filed August 2011 – Delmarva Power DE - Electric Pending - Filed December 2011 – Delmarva Power MD Pending - Filed December 2011 – Pepco MD Pending - Filed Dec

Slide 29: Pepco - Maryland Reliability Case 9240
Pepco - Maryland Reliability Case 9240 • Related to power outages caused by severe weather in Pepco’s service territory in 2010 • Public Service Commission initiated the proceeding for Pepco in August 2010 to investigate the reliability of the electric distribution system and the quality of service

Slide 30: Reliability Standards - Maryland
Reliability Standards - Maryland Maryland (PSC - RM43) - Rule making proceeding applying to all electric utilities in the state to establish comprehensive reliability and service standards • Following working group process and rule making hearings, Commission approved draft rules establishing requir

Slide 31: Reliability Standards - District of Columbia
Reliability Standards - District of Columbia District of Columbia - New reliability standards adopted in July 2011, further technical revisions proposed December 2011 • New rules require improvement in reliability performance (outage frequency and duration) on an annual basis beginning in 2013 and c

Slide 32: Cross-Border Energy Lease Status
Cross-Border Energy Lease Status • Equity investment as of September 30, 2011 of $1.3 billion • Annual tax benefits of $52 million • Annual net earnings of $21 million • Current Status: – IRS audit settlement approved in November 2010 for the 2001/2002 periods; disallowed net losses on the cross-bor
Source: SEC EDGAR · 8-K filed Jan 10, 2012
More decks from Pepco Holdings Inc
Merger or Acquisition (August 2014)15 slides · Aug 19, 2014
Merger or Acquisition (May 2014)44 slides · May 23, 2014
Q1 2014 Earnings Presentation14 slides · May 7, 2014
Williams Capital Group Midwest Utilities Seminar (April 2014)35 slides · Apr 9, 2014
Investor Day (March 2014)109 slides · Mar 21, 2014
Morgan Stanley Utilities Conference 201439 slides · Feb 28, 2014