30 slides from Petrofac's earnings presentation, Feb 24, 2016

Slide 1: Final Results 2015
FINAL RESULTS 2015 24 February 2016 1

Slide 2: Important notice
Important notice • This document has been prepared by Petrofac • Certain statements in this presentation are Limited (the Company) solely for use at forward looking statements. Words such as presentations held in connection with its Final "expect", "believe", "plan", "will", "could", Results 2015 on

Slide 3: Financial headlines
Financial headlines • Net profit1 of US$440m before Laggan-Tormore loss, in line with market expectations; net profit of US$9m after Laggan-Tormore loss • Exceptional items and certain re-measurements of US$358m, primarily due to lower oil and gas prices; IES portfolio carrying value now US$1.7bn •

Slide 4: Group reorganisation
Group reorganisation • Group reorganisation aims to improve our efficiency through de-layering and centralising back office services, while maintaining our focus on delivery and our responsiveness segments reporting 2016 Engineering & Engineering & Production Services Integrated Energy Construction

Slide 5: Laggan-Tormore project update
Laggan-Tormore project update • Achieved major milestones with completion of construction activities and transfer of care and custody of the plant in December 2015 • Pipeline gas introduced before end of 2015 and commercial production has now commenced • Recorded additional post-tax loss of US$168m

Slide 6: Greater Stella Area development update
Greater Stella Area development update • Making good progress with topside systems on FPF1 floating production facility • Onshore topsides commissioning expected to be completed before end of Q1 2016 • Marine work expected to be completed to enable sailaway during Q2 2016 • First production from Gre

Slide 7: Our backlog stands at record year-end levels
Our backlog stands at record year-end levels • Our backlog is secure and stands at record year-end levels at 31 December 2015 of US$20.7bn (OEC US$12.5bn; OPO US$3.2bn; ECS US$1.9bn; IES US$3.1bn) • Driving for best in class operations and project delivery • Maintaining our relentless focus on risk

Slide 8: Our backlog is focused in our core markets
Our backlog is focused in our core markets • Our ECOM backlog is predominantly with National Oil Companies, who are continuing to invest in large strategic projects in our core markets despite the lower oil price environment • Our existing backlog gives us excellent revenue visibility for 2016 and b

Slide 9: Our pipeline of bidding prospects remains robust
Our pipeline of bidding prospects remains robust • Onshore Engineering & Construction (OEC) bidding pipeline remains robust • Majority of opportunities are in our core OEC 2016 prospects by geography markets, particularly in the Middle East and North Africa: Oman • with NOCs, who are committed to on

Slide 10: We continue to drive operational efficiencies
We continue to drive operational efficiencies • Continue to drive operational efficiencies to maintain our cost-competitiveness • Maintained focus on operational excellence and cost efficiencies with annual savings of US$80 million delivered in 2015 • Targeting further annualised efficiency savings

Slide 11: Results
RESULTS Petrofac ©

Slide 12: Income statement
Income statement 20151 20141 US$m US$m 6,844 6,241 Revenue Operating profit2 112 691 Profit before tax 20 634 Income tax expense (6) (33) Non-controlling interests (5) (20) Profit for the year attributable to 9 581 Petrofac Limited shareholders Profit for the year before Laggan- 440 Tormore losses E

Slide 13: Exceptional items and certain re-measurements
Exceptional items and certain re-measurements Exceptional items and certain re- Pre-tax Tax Post-tax US$m measurements predominantly relate to IES impairment impairment portfolio GSA 214 - 214 PM304 53 (20) 33 • As part of our normal year-end process we Goodwill 33 - 33 reviewed carrying value of IE

Slide 14: Onshore Engineering & Construction
Onshore Engineering & Construction • Revenue h35% – reflecting an increase in activity levels as we moved into the execution phase on a number of projects • Net loss of US$59m after recognising a post-tax loss of US$431m on Laggan-Tormore • Underlying net margin, before Laggan-Tormore loss, was 8.5%

Slide 15: Offshore Projects & Operations
Offshore Projects & Operations • Revenue i26% – predominantly reflecting lower levels of activity on capital projects and lower levels of brownfield engineering activity; cost savings enabled the delivery of services to clients at a lower cost • Net profit increased to US$68m • Net margin increased

Slide 16: Engineering & Consulting Services
Engineering & Consulting Services • Revenue h64% and net profit h52% – reflecting activity on the Rabab Harweel project in Oman and high utilisation across our Indian engineering offices • Net margin marginally lower at 7.0%, reflecting higher levels of low margin procurement pass-through revenue on

Slide 17: Integrated Energy Services
Integrated Energy Services • Revenue i32% – predominantly reflecting the lower oil price environment and lower investment in our Production Enhancement Contracts (PECs) in Mexico as we work through the contract migration process • Lower net profit reflects the lower oil price environment, lower inve

Slide 18: Movement in net debt
Movement in net debt Net debt decreased in 2H 2015 to US$0.7bn, following strong cash collection in Q4 2015 • Cash generated from operations and net working capital inflows of US$0.9 billion (2014: US$0.9 billion) • Net investing activities of US$0.3 billion (2014: US$0.5 billion) • Financing activi

Slide 19: Working capital
Working capital Working capital* has improved in each of • Group working capital has grown over a 5- the last three six-month periods (2H 2014, year view due to: 1H 2015, 2H 2015) – Unusually favourable position in OEC in 2009 to 2012 due to cash advances compared to WIP • Working capital in OEC at

Slide 20: Investing activities
Investing activities Priority to reduce our capital-intensity and deliver value from our IES portfolio • IES capex in 2015 and 2016 predominantly on Group capex (US$m)1 completion of Greater Stella Area development 854 827 812 827 • Invested around US$300m to end 2015 on JSD6000 project, where we ar

Slide 21: Financial position
Financial position Balance sheet remains robust and prudently managed, reflected in Credit ratings investment grade credit ratings Moodys Baa3 (stable) • Internal gearing ratio target of net debt/EBITDA S&P BBB (negative outlook) < 1X (excluding net finance leases) • Covenants: net debt/EBITDA of <

Slide 22: Outlook
Outlook • Our backlog is secure and stands at • We continue to drive operational record year-end levels of US$20.7 efficiencies to maintain our cost billion, giving excellent revenue visibility competitiveness and protect our for 2016 and beyond margins • Our backlog is focused in our core • We rema

Slide 23: Appendices
APPENDICES Petrofac ©

Slide 24: Appendix 1: Key E&C/EPS projects
NOC/NOC led company/consortium Appendix 1: Key E&C/EPS projects Joint NOC/IOC company/consortium IOC/IOC led company/consortium Original contract value to Petrofac In Salah southern fields development, Algeria US$1,200m Badra field, Iraq US$330m Petro Rabigh, Saudi Arabia Undisclosed Jazan oil refin

Slide 25: Appendix 2: Key IES projects
Appendix 2: Key IES projects Production Enhancement Contracts (PEC)* END DATE Magallanes and Santuario, Mexico 2037 Pánuco, Mexico** 2043 Arenque, Mexico 2043 Risk Service Contracts (RSC)*** Berantai development, Malaysia 2020 Equity Upstream Investments Block PM304, Malaysia 2026 Chergui gas plant,

Slide 26: Appendix 3: IES book value
Appendix 3: IES book value Petrofac @ Intangible oil Oil and gas facilities and gas assets Oil and gas per note 10 per note 13 assets per note (Ohanet, OML119 (Block PM304, 10 (Block (both fully OML119 and Greater Stella PM304, depreciated) and other pre- Area Chergui and floating production develop

Slide 27: Appendix 4: Effective tax rate
Appendix 4: Effective tax rate Effective tax rate (ETR) by segment1 2015 2014 Onshore Engineering & Construction (2)% (7)% Offshore Projects & Operations (1)% 28% Engineering & Consulting Services 28% 15% Integrated Energy Services (350)% 22% Group 30% 5% • Group’s effective tax rate (ETR) is depend

Slide 28: Appendix 5: employee numbers
Appendix 5: employee numbers Aberdeen Woking London Mumbai Chennai Kuala Lumpur Sharjah Abu Dhabi Main operational centres Other operating locations Corporate services 100 • Approximately 19,000 people in 2,900 7 key operating centres and 24 6,900 OEC offices OPO ECS • Around 30% of our employees IE

Slide 29: Appendix 6: segmental performance
Appendix 6: segmental performance 2015 revenue by reporting segment 2015 revenue by geography 7% 14% 21% 10% Oman 5% UAE OEC Algeria OPO 8% United Kingdom ECS Kuwait 21% Malaysia IES Saudi Arabia 62% 8% 20% Other 12% 12% • Onshore Engineering & Construction earned 62% of Group revenues in 2015 • Mid

Slide 30: For further details, please contact
For further details, please contact Jonathan Low Head of Investor Relations jonathan.low@petrofac.com +44 20 7811 4930 Jonathan Edwards Investor Relations Officer jonathan.edwards@petrofac.com +44 20 7811 4936 30
Source: company website
More decks from Petrofac Limited
Investor Presentation (2025)22 slides · Aug 15, 2025
H1 2024 Earnings Presentation25 slides · Sep 30, 2024
FY2023 Earnings Presentation29 slides · May 31, 2024
H1 2023 Earnings Presentation27 slides · Aug 10, 2023
FY2022 Earnings Presentation33 slides · Apr 27, 2023
Investor Presentation (2023)20 slides · 2023