  1. Slide 1: Red 5 Limited – Siana Gold Project

    Red 5 Limited * IFRIC 20 Standard and includes royalties (2%) and SDMP and EPEP commitments (4%) Siana Gold Project 20 January 2015 RED5 Limited

  2. Slide 2: Geographical location – Siana Gold Project

    Geographical location – Siana Gold Project RED5 Limited Slide 2

  3. Slide 3: Red 5 at a glance

    Red 5 at a glance  RED – ASX: (Share price at 19 January 2015) A$0.11  Issued shares 759 m  Market capitalisation $83.5 m  Cash (at 19 January 2015) $16.9 m  Secured Debt & Hedging nil  Substantial shareholders • Baker Steel Capital Managers LLP 19.8% • Franklin Resources Inc. 16.2% • Acorn Ca

  4. Slide 4: Recent activities

    Recent activities  Cease and Desist Order (CDO) lifted over milling operations at Siana Gold Project  Construction, upgrade and sign-off for stage I of three Tailing Storage Facilities  Construction of Thickener and Cement addition plant  Estimated 195,000 tonnes of ore mined at 2.43 g/t current

  5. Slide 5: Construction and upgrade of tailings storage facilities

    Construction and upgrade of tailings storage facilities RED5 Limited Slide 5

  6. Slide 6: Construction of HDPE lined tailings storage facility (TSF 5)

    Construction of HDPE lined tailings storage facility (TSF 5) RED5 Limited Slide 6

  7. Slide 7: Construction of HDPE lined tailings storage facility (TSF 5)

    Construction of HDPE lined tailings storage facility (TSF 5) RED5 Limited Slide 7

  8. Slide 8: Upgrade existing tailings storage facilities (TSF 3 and 4)

    Upgrade existing tailings storage facilities (TSF 3 and 4) RED5 Limited Slide 8

  9. Slide 9: Upgrade existing tailings storage facilities (TSF 3 and 4)

    Upgrade existing tailings storage facilities (TSF 3 and 4) RED5 Limited Slide 9

  10. Slide 10: Upgrade existing tailings storage facilities (TSF 3 and 4)

    Upgrade existing tailings storage facilities (TSF 3 and 4) RED5 Limited Slide 10

  11. Slide 11: Construction, upgrade and sign-off for stage I of three tailing storage facilities

    Construction, upgrade and sign-off for stage I of three tailing storage facilities  Capital cost to date A$12.1  Capacity of 375,000 tonnes (currently at Stage I)  Sign off received from Knight Piésold confirming that construction was accomplished to the approved design and technical standard and

  12. Slide 12: Construction of a thickener and cement addition plant

    Construction of a thickener and cement addition plant RED5 Limited Slide 12

  13. Slide 13: Construction of a thickener and cement addition plant

    Construction of a thickener and cement addition plant RED5 Limited Slide 13

  14. Slide 14: Construction of a thickener and cement addition plant

    Construction of a thickener and cement addition plant RED5 Limited Slide 14

  15. Slide 15: Construction and commissioning of a thickener and cement addition plant

    Construction and commissioning of a thickener and cement addition plant  Construction of a thickener and cement addition plant completed in November 2014  Capital cost A$3.7 Million  Process plant - an extensive systematic process was undertaken to inspect and rehabilitate all the mechanical, ele

  16. Slide 16: Restart of mining activities

    Restart of mining activities  Mining activities re commenced in June 2014; since then • total material movement is over 1.1 million BCM, of which 716,000 BCM is ex pit • majority has been used for TSF construction, with the balance used for the RoM Pad expansion and delivered to various stockpiles

  17. Slide 17: Ore mined – December 2014

    Ore mined – December 2014 RED5 Limited Slide 17

  18. Slide 18: Status of dewatering and de-pressurizing wells – phase I

    Status of dewatering and de pressurizing wells – phase I  7 wells operational Part Operating Operating Operating Well construction issue - TBD Operating 3 Wells Operating RED5 Limited Slide 18

  19. Slide 19: Power supply upgrade

    Power supply upgrade  The Siana Gold Project was connected to the external grid mains power in June 2014 and is no longer solely reliant on the site-generated power  To date the external grid mains power has largely remained stable, however potential availability concerns remain.  Installation of

  20. Slide 20: Next steps …

    Next steps …  Recommence commercial gold production  Recommence exploration  Underground in-fill drilling  Open pit and Underground mining review  Long term tailing storage facility solution RED5 Limited Slide 20

  21. Slide 21: Potential 2015 exploration activities

    Potential 2015 exploration activities  Siana Gold Project – near mine exploration  Alegria – within Siana tennements  Siana Gold Project – U/G in-fill drilling  Mapawa LSY and St Nino targets – regional exploration RED5 Limited Slide 21

  22. Slide 22: Surigao del Norte Province – highly prospective

    Surigao del Norte Province – highly prospective RED5 Limited Slide 22

  23. Slide 23: Alegria - tenement opportunities

    Alegria - tenement opportunities RED5 Limited Slide 23

  24. Slide 24: Mapawa – key drill results to date

    Mapawa – key drill results to date MDD001 167m @ 1.06g/t Au, 0.17% Cu MDD003 156m @ 1.23g/t Au, 0.19% Cu MDD007 69m @ 1.06g/t Au, 0.16% Cu MDD008 22m @ 1.10g/t Au, 0.09% Cu MDD015 45m @ 1.90g/t Au, 0.03% Cu (hole ended in mineralization) MDD017 33m @ 3.40g/t Au, 0.08% Cu (>550m away from above holes

  25. Slide 25: Underground Mining

    Underground Mining  Commence an infill drilling program  Review underground mining strategy and feasibility study by third party specialist  Update underground resource and reserve model RED5 Limited Slide 25

  26. Slide 26: Long term tailings storage facility

    Long term tailings storage facility  Review prior work  Evaluate through a multi criteria analysis matrix  Decide on best long term tailings storage strategy and options  Prepare detail design for new facility  Acquire land for new facility and obtain necessary permits  Construct and operate n

  27. Slide 27: On-going community support

    On-going community support Support continues in the areas of:  Health  Education  Welfare  Agricultural  Infrastructure  Clean water RED5 Limited Slide 27

  28. Slide 28: Environmental Responsibility

    Environmental Responsibility  Committed to high environmental standards  Continual water quality monitoring  Water drainage systems  Silt ponds  Cyanide destruction  Tree planting RED5 Limited Slide 28

  29. Slide 29: Siana Mining Reserve (JORC 2004)

    Siana Mining Reserve (Jorc 2004) Mineral Reserve (as at June 2013) Contained Contained Tonnes Gold Grade Gold Silver Grade Silver Category (millions) (g/t) (‘000 oz) (g/t) (‘000 oz) Stockpiles 0.04 2.8 4.0 Open Pit 3.59 2.79 322 5.7 658 Underground 1.94 5.82 363 9.1 566 Total Reserve 5.57 3.83 689 6

  30. Slide 30: Siana Resource (JORC 2004)

    Siana Resource (Jorc 2004) Mineral Resource (as at June 2014)) Tonnes Gold Contained Silver Contained Category (million) Grade Gold Grade Silver (g/t) (‘000 oz) (g/t) (‘000 oz) Indicated Resource Open Pit 9.3 2.5 740 4.2 1,254 Underground 0.9 6.7 199 12.2 359 Total Indicated Resource 10.2 2.9 939 4.

  31. Slide 31: Competent Persons Statement

    Competent Persons Statement The information in this report relating to Mineral Resources and Drilling Results is based on information compiled by Mr. Byron Dumpleton, Member of the Australian Institute of Geoscientist (Member No 1598). This information was prepared and first disclosed under the JORC

  32. Slide 32: RED 5 Limited

    RED5 Limited Slide 32

  33. Slide 33: Summary & Questions

    Summary & Questions  Cease and Desist Order lifted  Production re-started  Asset quality and tenement growth potential remains  Exploration to re-start RED5 Limited Slide 33

  34. Slide 34: Contact details

    Contact details Australia Philippines  Red 5 Limited  Greenstone Resources Corporation Level 2, Level 5, 35 Ventnor Avenue NOL Tower, Commerce Ave West Perth Muntinlupa City Western Australia Manila 6005 1770  Ph: + 61 8 9322 4455  Ph: + 63 2 807 2790  Mark Williams (Managing Director)  Kevin