Slide 1: Advancing Emerita’s IBW Project in the Historic Iberian Pyrite Belt
Advancing Emerita’s IBW Project in the Historic Iberian Pyrite Belt November 2026 TSXV: EMO OTCQX: EMOTF FSE: LLJA

Slide 2: Forward-Looking and Cautionary Statements
Forward-Looking and Cautionary Statements Forward-looking information Technical information and qualified persons This presentation contains “forward-looking information” within the meaning of applicable Canadian securities The PFS was prepared by SLR Consulting (SLR) in accordance with National Ins

Slide 3: Emerita Investment Highlights
Emerita Investment Highlights 1 Robust Iberian Belt West (“IBW”) PFS economics 5 Exploration upside at IBW and across the Iberian Pyrite Belt • After-tax NPV (8%) of US$776M1, IRR of 23.5%, and payback of 1.9 years from • Indicated tonnage up 86% and Inferred up 110% since the first estimate in firs

Slide 4: Addressing Key Investor Questions
Addressing Key Investor Questions The four topics raised most often since the PFS results 1 F LOWS H E E T 2 PY R I T E CO N C E N T R AT E 3 O P T IM I ZATI ON 4 D E V E LO PM E N T T I M E L I N E Why sell the pyrite concentrate What is pyrite concentrate, and What could improve on the PFS Why doe

Slide 5: Iberian Belt West at a Glance
Iberian Belt West at a Glance A royalty-free, 100%-owned polymetallic project with a completed PFS, three deposits open at depth and along strike, and a 21-year reserve life 100% 3 Owned and royalty-free High-grade deposits, open at depth and along strike, producing four concentrates 23.4 Mt 21 year

Slide 6: Near-Term Key Goals for IBW
Near-Term Key Goals for IBW Four priorities that take risk off IBW and target a shorter path to production Optimization studies Metallurgical test work Non-discretionary exploration Permitting The work The work The work The work Engineering studies on Continued testing and trade-off Infill drilling

Slide 7: Company Overview
Company Overview Emerita was reset in 2026, with new leadership, independent oversight, and a focus on Iberian Belt West development Company Overview Iberian Belt West Forward Work Plans and Exploration

Slide 8: Emerita in 2026
Emerita in 2026 Since April 2026 the Company has changed its leadership, its board, and its controls, and has delivered the pre-feasibility study What Changed in 2026 Where the Focus Is for 2027 New leadership and a renewed board Advancing, optimizing, and de-risking IBW toward a feasibility study J

Slide 9: Board of Directors
Board of Directors A board built for the next phase, with mine development and operations, capital markets, and legal experience added in 2026 Joseph Belan Joaquín Merino-Marquez Agne Ahlenius Oscar Cabrera Peter McRae Executive Chairman President and CEO Independent Director Independent Director In

Slide 10: Management and Project Team
Management and Project Team A management and project team with mine development, operating, and permitting experience in the Iberian Pyrite Belt, led from Seville Joaquín Merino-Marquez, P.Geo. Ian Hardesty President and Chief Executive Officer Vice President, Exploration Based in Seville, with more

Slide 11: Capital Structure and Liquidity
Capital Structure and Liquidity Capital Structure1 Nebari credit facility Common shares outstanding 296,623,968 With Nebari Natural Resources Credit Fund, agreed in August 2024 and upsized to US$50M in September 2025 Warrants 31,430,283 US$50M US$6M US$44M Options 11,403,870 Total facility Drawn on

Slide 12: Iberian Belt West
Iberian Belt West Three high-grade deposits in an established operating district in Spain, now with a reserve and a study behind them Company Overview Iberian Belt West Forward Work Plans and Exploration

Slide 13: Project Overview
I B E R I A N B E LT W E S T Project Overview Project Overview PFS Results Pyrite Concentrate Market

Slide 14: Strategic Relevance
Strategic Relevance A European source of base-metal concentrates and of sulphur, with strategic project status from the Regional Government of Andalusia European supply Copper, zinc, and lead concentrates and sulphur produced within the European Union. The 2026 disruption in the Strait of Hormuz has

Slide 15: Project Overview
Project Overview Three high-grade VMS deposits within one 1,546 ha permit, feeding a single plant Location of the Three Deposits Within the Permit, with the Proposed Mine Design and Surface Facilities Overview • The Iberian Belt West permit of 1,546 ha, La Romanera Surface facilities approximately 1

Slide 16: Existing Infrastructure
Existing Infrastructure Established transport routes, grid power, water, and the Port of Huelva, approximately 80 km by road 22 km 220 kV Road and site access Access to grid power Paved road access, with the HU-5401 road through Access to the grid through Red Eléctrica’s 220 kV the site. By road fro

Slide 17: Mineral Resources
Mineral Resources Indicated tonnage up 37% and Inferred up 46% since the 2025 estimate, supporting a 21-year mine life, with all three deposits open for growth La Romanera: Lenses in 3D El Cura: Lenses in 3D Mineral Resource Estimate, Effective July 17, 20261,2 NSR Deposit Class Mt Zn % Pb % Cu % Ag

Slide 18: Mineral Reserves
Mineral Reserves A maiden Probable reserve of 23.4 Mt converts approximately 90% of Indicated tonnes into a 21-year mine plan Reserve Category Tonnes (Mt) Zn % Pb % Cu % Ag g/t Au g/t S% Probable: La Romanera 20.4 2.19 1.05 0.38 54 1.13 36.2 Probable: El Cura 1.8 1.23 0.58 1.01 31 1.01 26.3 Probable

Slide 19: Built on Proven Methods
Built on Proven Methods Every method in the Base Case is in use at mines today. No unproven technology and no post-flotation plant are required Long-hole open stoping Railveyor haulage Conventional milling and flotation Transverse and longitudinal stopes on 30 m sublevels, with Rail-based haulage fr

Slide 20: Mine Design
Mine Design Long-hole open stoping, reached by an approximately 7 km decline routed to safeguard a protected area, with Railveyor haulage to surface Mine Design: Workings at the Three Deposits, with Twin Declines, Ramps, and Raises Mining method Long-hole open stoping on 30 m La Romanera sublevels,

Slide 21: Mineral Processing
Mineral Processing One conventional plant turns ore from three deposits into four saleable concentrates 1.2 Mtpa Crush and grind Sequential flotation Filter and ship Ore from three deposits, Jaw crusher, then SAG, ball, and tower Copper, lead, and zinc in turn, then Concentrates trucked approximatel

Slide 22: Metallurgical Evolution to PFS Base Case
Metallurgical Evolution to PFS Base Case Optionality demonstrated by metallurgical testing; process optimization is the next step for implementation Flotation Flowsheet Precious-Metal Recovery Routes Trade-Off and Decision November 2023 to early 2025 2025 to early 2026 May 2026 to present Nov 2023 t

Slide 23: From Tailings to Product
From Tailings to Product The flowsheet turns what was post-flotation tailings into a saleable concentrate carrying approximately 78% of the gold and 47% of the silver Why Direct Sale Was Selected What Happens to the Gold and Silver What Stays Open • The leach routes need more metallurgical testing •

Slide 24: Permitting Status
Permitting Status A defined Spanish process, advanced step by step since 2021. Public consultation is complete and the Environmental Opinion is next Key Regulatory Milestones (Indicative Schedule) Completed Upcoming Key approval 2023 2024 2025 2026 2027 2028 2029 Environmental permit (AAU) Applicati

Slide 25: Emerita in the Community
Emerita in the Community The Fundación Emerita Compromiso Sostenible is the social and community pillar of IBW, already at work in the Andévalo Areas of Action Culture and heritage Environment and sport Preservation and promotion of local Healthy and sustainable lifestyles, respect for traditions, c

Slide 26: PFS Results
I B E R I A N B E LT W E S T PFS Results Project Overview PFS Results Pyrite Concentrate Market

Slide 27: Key Results: IBW Project PFS
Key Results: IBW Project PFS Robust economics, a 21-year mine life, low execution risk, and significant optionality US$776M 23.5% 1.9 years After-tax NPV (8%) After-tax IRR Payback from first production US$7.5B US$4.6B US$2.7B Life-of-mine revenue Life-of-mine EBITDA1 After-tax free cash flow1 US$56

Slide 28: What the Pre-Feasibility Study Establishes
What the Pre-Feasibility Study Establishes A long-life polymetallic mine based on simple, proven methods that lower execution risk, with a defined path to a feasibility study The Base Case US$776M / 23.5% 21 years 775 ktpa 69.2% After-tax NPV (8%) / IRR1 Mine life on Probable Mineral Four concentrat

Slide 29: Pre-Feasibility Study: Process and Review
Pre-Feasibility Study: Process and Review PFS by SLR under NI 43-101, reviewed in several stages, including a Technical Committee of two Independent Directors 1 2 3 4 5 Independent consultants Company technical review Technical Committee review Expanded quality-assurance Qualified-person sign-off an

Slide 30: What IBW Sells
What IBW Sells Diversified revenue exposure from four concentrates carrying six payable revenue streams LOM Payable Revenue by Commodity Concentrate Grade Precious credits Tonnes per year Who buys it Non-ferrous smelters, acid Pyrite concentrate 50.7% S Au / Ag 694,620 15% producers, traders Pyrite

Slide 31: Production and Cost Profile
Production and Cost Profile Each tonne of ore generates ~US$281 of net smelter return1 against US$86.49 of site operating cost, with 775 ktpa of concentrate at steady state Total Concentrate Production (kt) Concentrate Production by Deposit (kt) Ramp Ramp- La Romanera (~714 ktpa) El Cura (~43 ktpa)

Slide 32: Recovered Metal Value Benchmarking
Recovered Metal Value Benchmarking IBW ore carries US$347 of recovered value per tonne from six payable revenue streams, ahead of three of four operating peers Recovered Metal Value per Tonne of Ore (US$/t)1,2 $901 $465 $347 $332 $265 $234 $231 Vareš El Domo IBW3 Errington Chelopech Cozamin McIlvenn

Slide 33: Capital Cost
Capital Cost Initial capital of US$567M, including US$63.6M of contingency, paid back 1.9 years from first production Initial capital Initial Capital Capital Expenditures (US$M, rounded) Initial Sustaining & closure Total Mine-related Mine-related (development/equipment/Railveyor) $189.1 $249.8 $438

Slide 34: Capital Intensity Benchmarking
Capital Intensity Benchmarking Competitive capital intensity for a 21-year mine, with initial capital paid back 1.9 years from first production Initial Capital per Tonne of Annual Processing Capacity (US$/t)1,2 US$472/t1 Čoka Rakita (0.85 Mtpa) $527 IBW initial capital per tonne of annual processing

Slide 35: Cash Flow Profile
Cash Flow Profile Compelling cash generation, with US$4.6B of life-of-mine EBITDA and US$2.7B of after-tax free cash flow1,2 Annual EBITDA and EBITDA Margin (US$M)2 EBITDA EBITDA Margin $400 100% 74% 73% 76% 74% 76% 74% 71% 72% 68% $300 68% 67% 68% 65% 66% 65% 66% 75% 63% 62% 62% 64% $200 44% 50% $3

Slide 36: Resilient Economics
Resilient Economics After-tax NPV holds at US$491M with the pyrite concentrate price 30% lower, and stays positive down to approximately US$52/t US$776M Change in After-Tax NPV (8%) for 10% Changes in Key Drivers (US$M) Unfavourable 10% change Favourable 10% change After-tax NPV (8%), Base Case1 Pyr

Slide 37: Leverage to Metal Prices
Leverage to Metal Prices At September 2026 average spot prices, after-tax NPV (8%) rises 31% to US$1,019M, with an after-tax IRR of 27.1%1 NPV (8%) (US$M) IRR Payback from first production (years) $776 $1,019 23.5% 27.1% 1.9 1.5 Base Case Spot price deck1 Base Case Spot price deck1 Base Case Spot pr

Slide 38: What De-risks IBW from Here
What De-risks IBW from Here Each gate in 2027 lowers risk in the project. The work leads to a feasibility study Feasibility study The basis for a Environmental construction decision, authorization Concessions and built on the completed power Environmental Opinion, work Resource confidence then the f

Slide 39: 2027 Catalysts
2027 Catalysts What investors can expect to see from IBW in 2027, with each result lowering risk to the project Completed PFS results released on October 29, 2026 Technical report filed on SEDAR+ on November 3, 2026 Environmental Opinion and the final Infill drilling results from La Infanta and envi

Slide 40: Pyrite Concentrate Market
I B E R I A N B E LT W E S T Pyrite Concentrate Market Project Overview PFS Results Pyrite Concentrate Market

Slide 41: Pyrite Concentrate: The Product and Its Market
Pyrite Concentrate: The Product and Its Market An established, globally traded feedstock for sulphuric acid, priced on its sulphur content, with gold and silver paid on top From IBW Ore to Sulphuric Acid 19.7 Mt 82% Estimated global demand for Share of demand that goes to 1 IBW ore 2 Flotation 3 Pyr

Slide 42: How a Tonne of Pyrite Concentrate Is Priced
How a Tonne of Pyrite Concentrate Is Priced Sulphur-based pricing plus gold and silver credits. The study’s terms result in approximately US$349 per tonne Payable Value From the Sulphur-Based Price to the Net Smelter Return (US$ per dry tonne)1,2 What one tonne is worth $48 $27 $349 ($19) ($8) $322

Slide 43: The Sulphur and Sulphuric Acid Markets
The Sulphur and Sulphuric Acid Markets Demand is structural, supply is a by-product of oil and gas, and the study expects the market to stay tight Demand Is Structural Supply Is a By-Product What 2026 Has Shown • Sulphuric acid is a critical reagent in fertilizer • Sulphur mainly comes from oil refi

Slide 44: Two Value Streams, Two Different Markets
Two Value Streams, Two Different Markets Sulphur and precious metals are priced in separate and non-correlated markets, and pricing sensitivity continues to demonstrate strong economics After-Tax NPV (8%) by Sulphur-Based Price and Gold and Silver Prices (US$M)1 At project level, after-tax NPV (8%)

Slide 45: Forward Work Plans and Exploration
Forward Work Plans and Exploration The study values IBW on what the test work supports today. The work from here is aimed at increasing confidence levels and optionality Company Overview Iberian Belt West Forward Work Plans and Exploration

Slide 46: Next Steps & Improving PFS Optionality
F O R WA R D W O R K P L A N S A N D E X P LO R AT I O N Next Steps & Improving PFS Optionality Next Steps & Improving PFS Optionality Growth & Exploration

Slide 47: Beyond the Base Case
Beyond the Base Case The US$776M after-tax NPV1 counts none of the following Work under way Up to 20% faster Faster development rates 87.5% gold, 94.6% silver2 On-site precious-metal recovery The PFS adopts conservative development rates pending geotechnical & hydrogeological Albion test work return

Slide 48: The Work Plan to a Feasibility Study
The Work Plan to a Feasibility Study The program is defined by discipline, and the data collection that drives the schedule is already under way Required for the Feasibility Study Optimization Opportunities Geotechnical model Under way Development rates and schedule Under way Geotechnical drilling a

Slide 49: Five Years of Development, and What May Shorten It
Five Years of Development, and What May Shorten It Five years of development results in over 23 km of underground access & process plant. Work to reduce development timeline has already started The Study Schedule and Initial Capital by Year What Could Shorten It Year -5 Year -4 Year -3 Year -2 Year

Slide 50: Growth & Exploration
F O R WA R D W O R K P L A N S A N D E X P LO R AT I O N Growth & Exploration Next Steps & Improving PFS Optionality Growth & Exploration

Slide 51: Exploration: Capital Allocation Priorities
Exploration: Capital Allocation Priorities Prioritizing drilling that could shorten IBW development. Greenfield exploration across Iberian Pyrite Belt to follow as capital becomes available Exploration Capital Allocation Prioritization Non-discretionary La Infanta resource Brownfield drilling that 1

Slide 52: Growing IBW
Growing IBW Indicated tonnage up 86% and Inferred up 110% since 2023, with all three deposits open and 9.9 Mt of Inferred outside the mine plan Mineral Resource Growth from 2023 to 2026 (Mt)1 High exploration efficiency Indicated Inferred Under US$1 per resource tonne Approximately US$34M of explora

Slide 53: Infanta Sur
Infanta Sur Immediately south of the high-grade La Infanta deposit Infanta Sur Permit, First-Year Geological Mapping (May 2024) Overview 848 ha • Immediately south of the high- grade La Infanta deposit Immediately south of La Infanta, a discovery could dramatically • Mapping shows older PQ1 cover en

Slide 54: San Antonio Project
San Antonio Project Contiguous with the IBW concession with known historic mineralization, San Antonio has strong potential for exploration discovery San Antonio Project, IBW, and Historic Workings Overview 5,755 ha • Proven high-grade historic production (15% Cu average mined District-scale land pa

Slide 55: Nuevo Tintillo Project
Nuevo Tintillo Project Strategic land position between two world-class mines in the heart of the Iberian Pyrite Belt Nuevo Tintillo Project, Historic Workings, and Surface Sampling Why It Matters 6,875 ha • Prime location in one of the world’s most prolific VMS belts, Large contiguous block in the b

Slide 56: Emerita: Proof Over Promotion
Emerita: Proof Over Promotion emeritaresources.com TSXV: EMO OTCQX: EMOTF FSE: LLJA
Source: company website
More decks from Emerita Resources Corp.
Investor Presentation (July 2026)26 slides · July 2026
Investor Presentation (April 2026)27 slides · April 2026
Investor Presentation (February 2025)32 slides · February 2025
Investor Presentation (August 2024)31 slides · August 2024
Investor Presentation (October 2023)27 slides · October 2023
Investor Presentation (September 2022)31 slides · September 2022