Petrofac Limited · OTC:POFCY
Petrofac — H1 2011 Earnings Presentation
30 slides from Petrofac's earnings presentation, Aug 22, 2011

Slide 1: Interim Results 22 August 2011
Interim Results 22 August 2011

Slide 2: Important Notice
Important Notice • This document has been prepared by Petrofac Limited (the Company) solely for use at presentations held in connection with the announcement of its results for the six months ended 30 June 2011. The information in this document has not been independently verified and no representati

Slide 3: Headlines
Headlines • Good operational and financial performance in 1H 2011 • Backlog of US$11.4bn at 30 June 2011 (i3% versus 31 December 2010, h66% versus 30 June 2010); maintains our outstanding revenue visibility • Engineering & Construction net margin in-line with medium-term guidance (around 11%) and su

Slide 4: Backlog
Backlog • Backlog continues to give outstanding revenue visibility • New projects awarded in Algeria, Iraq and Malaysia contributed to the broad maintenance of Engineering & Construction backlog at US$8.7bn in 1H 2011 (Dec 2010: US$9.0bn) • Offshore Engineering & Operations backlog remained steady a

Slide 5: Group reorganisation and reporting segments
Group reorganisation • Organisational restructure will take effect from 1 January 2012 • Maroun Semaan appointed President, leading development of major strategic initiatives Divisions Engineering, Construction, Operations & Integrated Energy Services (IES) Maintenance (ECOM) Chief Executive, Andy I

Slide 6: Progressing our IES strategy – Mexico
Progressing our IES strategy – Mexico Magallanes and Santuario blocks, Mexico • Selected bidder for two 25 year Production Enhancement Contracts (PEC) for Magallanes and Santuario blocks • Current production approximately 14,000 bpd • Tariff of US$5.01 per barrel for incremental production (lower ta

Slide 7: Progressing our IES strategy – projects update
Progressing our IES strategy – projects update Ticleni field, Romania (PEC) • Oil production ahead of budget • Well workovers undertaken to improve production • Commenced pilot water flood programme; results expected end 2011 Ticleni field, Romania Berantai field, Malaysia (RSC) • Good progress made

Slide 8: Progressing our IES strategy – West Desaru
Progressing our IES strategy – West Desaru • We have signed an MOU to accelerate production from Block PM304 with a third phase of development - West Desaru • Aim to achieve first oil by end 2012 by utilising current export facilities and upgrading and deploying a Mobile Offshore Production unit • W

Slide 9: Progress on major projects – South Yoloten
Progress on major projects South Yoloten field, Turkmenistan • Good progress with construction of the temporary facilities completed and the majority of orders for procurement placed • Expect to reach profit recognition threshold in 2H 2011 • 1,800 employees and subcontractors on-site with more than

Slide 10: Progress on major projects – Laggan Tormore
Progress on major projects Laggan Tormore gas processing plant, Shetland Islands • First lump-sum contract in the UKCS; dynamic project management and continuous engagement at all levels of the client team • Leveraging offshore skills to build modular design onshore • Stella Ness accommodation block

Slide 11: Progress on major projects – El Merk and Asab
Progress on major projects El Merk gas processing facility, Algeria • Engineering and procurement now substantially complete, more than 50% of construction completed • Around 5,000 workers on-site of whom ~90% are Algerian • First graduates through the recently opened training centre El Merk gas pro

Slide 12: Geographical expansion – South-East Asia
Geographical expansion – South-East Asia Indonesia: existing capability Malaysia: deepening strategic relationship • JV with Indonesia’s Inti Karya Persada • Worked with PETRONAS since 2004; Tehnik (IKPT) recent awards on Sepat and Berantai and • Engineering office with > 200 employees signed MOUs f

Slide 13: Geographical expansion – recent country entries
Geographical expansion – recent country entries • Currently working on two projects in-country for Shell and BP Iraq • Strong bidding pipeline for further opportunities in late 2011 and 2012 • Strategic opportunity to develop local workforces • Invested additional funds into Seven Energy taking our

Slide 14: Income Statement
Income Statement US$m 1H 2011 1H 20101 Variance Restated Revenue 2,711.1 2,165.8 25% Operating profit 298.5 290.9 3% Profit before tax 299.6 291.4 3% Income tax expense (53.1) (61.2) Profit for the period 246.5 230.2 7% Profit for the period attributable to Petrofac Limited shareholders 246.3 231.0

Slide 15: Cash flow and gross cash balances
Cash flow and gross cash balances Cash position very strong at US$1.8bn: • Net working capital inflows of US$906m due to an increase in advance payments and a reduction in WIP on Engineering & Construction • Investing activities include US$99m for the acquisition of three FPSOs, further investment i

Slide 16: IES capital expenditure
IES capital expenditure • Approximately US$140m deployed on IES projects in 1H 2011; expect the rate of capital deployment to increase in 2H 2011 • Continue to envisage gross investment of between US$0.5 – 1.0bn per year • Projects are typically either fast-track developments (time frame of 1 – 3 ye

Slide 17: Backlog – inclusion of Risk Service Contracts
Backlog – inclusion of Risk Service Contracts Rationale • Updated in response to the creation of Integrated Energy Services and the increasing proportion of earnings that will come from Risk Service Contracts • Reflects the service nature of this business and removes inconsistency in treatment among

Slide 18: Engineering & Construction
Engineering & Construction Financial performance in 1H 2011 affected by timing of profit recognition: • Revenue h17% - higher activity levels particularly on Asab and South Yoloten projects • Net profit flat - due to margin dilution from early stage contracts (which have not reached profit recogniti

Slide 19: Offshore Engineering & Operations
Offshore Engineering & Operations Very strong performance in 1H 2011: • Net revenue h98%, net profit h703% – significant increase in activity levels particularly on the SEPAT development and the FPSO Berantai – provision release following completion of a long-term maintenance services contract • Net

Slide 20: Engineering, Training, Production Solutions
Engineering, Training, Production Solutions Mixed results across the business units: • Revenue h20% due to an increase in activity in Engineering Services in support of internal work and strong growth in number of delegates in Training Services • Net profit broadly unchanged • Net margins on net rev

Slide 21: Energy Developments
Energy Developments Lower contribution during ‘development phase’: • Revenue h50% - primarily due to commencement of the Berantai RSC, partially offset by demerger of Don assets in April 2010 • Net profit i56% – lower contribution from Cendor due to lower production and demerger of Don assets – no c

Slide 22: Summary and outlook
Summary and outlook • Good operational performance achieved across our portfolio of projects • Backlog of US$11.4 billion gives outstanding revenue visibility • Encouraging progress against our Integrated Energy Services strategy • Sector-leading net margins in Engineering & Construction at around 1

Slide 23: Appendices
Appendices

Slide 24: Appendix 1: Largest current EPC contracts
Appendix 1: Largest current EPC contracts Customer key: Original contract NOC/NOC led company/consortium Joint NOC/IOC company/consortium IOC/IOC led company/consortium value to Petrofac Asab onshore oil field development, Abu Dhabi US$2,300m Karan cogeneration and utilities, Saudi Arabia Undisclose

Slide 25: Appendix 2: Effective tax rate
Appendix 2: Effective tax rate Tax charge by segment 1H 2011 2010 reported reported Engineering & Construction 14% 17% Offshore Engineering & Operations 19% 27% Engineering, Training and Production Solutions 7% (4%) Energy Developments1 63% 50% • Engineering & Construction and Offshore Engineering &

Slide 26: Appendix 3: Segmental performance
Appendix 3: Segmental performance • Engineering & Construction earned 67% of revenue and 80% of net profit • Middle East and Africa: remains a key geographic market for Engineering & Construction • CIS & Asia: primarily relates to activity in Malaysia across the group, with an increasing contributio

Slide 27: Appendix 4: Employee numbers
Appendix 4: Employee numbers • 14,600 people in 6 key operating centres and 21 offices worldwide • EPC headcount includes the engineering offices in Mumbai, Chennai and Delhi, which although reported in ETSPS principally support E&C activities • Approximately 4,500 employee shareholders or participa

Slide 28: Appendix 5: EPC risk management
Revenue recognition 28 acceptance Profit recognition certificate Final Project risk Warranty phase acceptance Provisional certificate 100% Mechanical completion Robust Completion systems to facilitate smooth startup Manage/support local construction contractors (typically 2-4 years) Appendix 5: EPC

Slide 29: Notes
Notes • EBITDA means earnings before interest, tax, depreciation and amortisation and is calculated as profit from operations before tax and finance costs adjusted to add back charges for depreciation, amortisation and impairment. • Net profit (for the group) means profit for the period from operati

Slide 30: Contact information
Contact information: Jonathan Low Tess Palmer Head of Investor Relations Investor Relations Officer ir@petrofac.com ir@petrofac.com 020 7811 4900 020 7811 4900
Source: Internet Archive copy of petrofac.com
More decks from Petrofac Limited
Investor Presentation (2025)22 slides · Aug 15, 2025
H1 2024 Earnings Presentation25 slides · Sep 30, 2024
FY2023 Earnings Presentation29 slides · May 31, 2024
H1 2023 Earnings Presentation27 slides · Aug 10, 2023
FY2022 Earnings Presentation33 slides · Apr 27, 2023
Investor Presentation (2023)20 slides · 2023