Fortescue Ltd · ASX:FMG

Fortescue — Fortescue Metals Group — Shareholder Meeting (November 2004)

19 slides from Fortescue's shareholder meeting presentation, November 2004

  1. Slide 1: Microplaty Hematite (MpH) The New Force in Iron Ore

    Fortescue Metals Group Ltd Fortescue Metals Group Ltd Fortescue House 50 Kings Park Road West Perth Western Australia 6005 PO Box 910 West Perth Western Australia 6827 Telephone: + 61 8 9266 0111 Facsimile: + 61 8 9266 0188 Website: www.fmgl.com.au Email: jmorrin@fmgl.com.au Microplaty Hematite (MpH

  2. Slide 2: China's Iron Ore import future - a calculation

    China’s Iron Ore import future - a calculation Population Assume - 1,500m people; only if population control policy holds Steel intensity Assume - 450kg/capita; Korea [750] Japan [590] USA [400] Recycling scrap metal Assume - 20%; currently 16%, growth will exceed scrap potential Fe content of impor

  3. Slide 3: And then there is India…

    And then there is India… - Population > 1 billion - May exceed China by 2040 - GDP doubling every 10-12 yrs - Steel intensity currently - 26 kg/capita If India matched only current Chinese levels of steel use (per capita) its steel use would be up by 150Mtpa = 250Mtpa extra iron ore demand on its ow

  4. Slide 4: The Pilbara, the lowest supply costs

    The Pilbara, the lowest supply costs Australia is the closest to China, able to serve it the most competitively 4

  5. Slide 5: Fortescue, Rio Tinto and BHPB

    Fortescue*, Rio Tinto and BHPB *Area length of FMG tenements in the Pilbara: 550km 5

  6. Slide 6: Meeting the demand for major independent supply

    Meeting the demand for major independent supply Wholly owned Iron Ore Regions West Pilbara Chichesters Central Pilbara 6

  7. Slide 7: Chichesters is a new multiple project iron ore region

    Chichesters is a new multiple project iron ore region 7

  8. Slide 8: FMG has two basic >60% Fe ore types

    FMG has two basic >60% Fe ore types • Direct ship (or high grade) requires little or no beneficiation, is already >60% Fe with low impurities • Beneficiated ore is processed (in common Pilbara practice) through a beneficiation plant to achieve >60% Fe • High moisture content is removed in the steel

  9. Slide 9: Christmas Creek Calcined Ore Types: Iron (Fe) against known products

    Christmas Creek Calcined Ore Types Competitive Iron (Fe) against known products 69.00 68.00 67.00 66.00 % Fe 65.00 Beneficiation Grade FMG - Potential 64.00 High Grade Zone HI - Premium BHPB - Premium BHPB - MM HI - MM FMG - 63.00 HI - Y BHPB - Y 62.00 J (RR) Mesa 61.00 9

  10. Slide 10: Christmas Creek Calcined Ore Types: Phosphorous (P) against known products

    Christmas Creek Calcined Ore Types Competitive Phosphorous (P) against known products 0.09 0.08 0.07 0.06 FMG - High Grade Zone FMG - Potential Beneficiation 0.05 BHPB - Premium %P HI - Premium 0.04 BHPB - MM HI - MM Grade Mesa J (RR) 0.03 HI - Y BHPB - Y 0.02 0.01 0.00 10

  11. Slide 11: Third Contract Signed: Ping Xiang Iron & Steel

    Third Contract Signed Ping Xiang Iron & Steel Co. Ltd www.fmgl.com.au 2million tonnes iron ore per annum Life of contract 22 years Prepayment of US$20million • US$10million prior to financial close • US$10million during construction Piang Xiang – a large mill - 4million tonnes per annum, 13,000 empl

  12. Slide 12: International Corporate Support for The New Force in Iron Ore

    International Corporate Support for The New Force in Iron Ore Binding Contract Signed & First Subcontractor Appointed Balance of Project : Discussions advancing The New Force in Iron Ore 12

  13. Slide 13: The Binding China Rail Contract

    The Binding China Rail Contract Mr Andrew Forrest, Chairman of Board of Directors of FMG & Mr Qin Jiaming Chairman of Board of Directors for CREC signed a binding contract with support of NDRC, SASAC & Ministry of Commerce 13

  14. Slide 14: CREC has US$13 billion work in hand

    CREC has US$13 billion work in hand 14

  15. Slide 15: CREC is a competent infrastructure provider

    CREC is a competent infrastructure provider 15

  16. Slide 16: Fortescue Corporate Summary

    Fortescue Corporate Summary Ticker: FMG.AX 218m Shares & Options @ recent placement price $1.00 ~ A$218m Market Cap Shareholder Fully Diluted Fully Diluted Percentage Shares (m) Directors and Management 118.2 54.3% Steel Mills & Institutions: 37.7 17.3% MLC JF Capital Partners JP Morgan Jiangsu Feng

  17. Slide 17: The Pilbara Infrastructure (TPI) Port & Rail

    The Pilbara Infrastructure (TPI) Port & Rail 17

  18. Slide 18: Fortescue Development Timeline

    Fortescue Development Timeline Current Status: Prefeasibility complete Final Feasibility on track Ship Commission Construction Tender Process Engineering Design Approvals Finance Definitive Feasibility Cash Flow Line Prefeas Study Interim Prefeas Study Scoping Study 18

  19. Slide 19: FMG: The New Force in Iron Ore

    FMG: The New Force in Iron Ore Distance equivalent: Los Angeles to San Francisco 19