Slide 1: Inspection and Maintenance of Emergency Lighting Systems
Inspection and Maintenance of Emergency Lighting Systems Eaton´s CEAG Emergency Lighting Business © 2015 Eaton, All Rights Reserved.
Slide 2: Every safety luminaire is important, protecting life and health
Every safety luminaire is important, protecting life and health. © 2015 Eaton, All Rights Reserved. 2
Slide 3: Workplaces Ordinance
Workplaces Ordinance Special requirements for operation § 4 (3) • The employer has safety devices to prevent or eliminate hazards, especially security lighting, fire fighting equipment, signal systems, emergency systems and emergency switches, as well as air conditioning systems, that must be proper
Slide 4: Sample Test-Regulation
Sample Test-Regulation Application Area § 1 • Shopping facilities • Congregational areas • Hospitals and care-homes • Accommodation • Skyscrapers • Car parking facilities • General educational and vocational schools Testing § 2 (1) • Technical systems must be test by a Specialist for effectiveness a
Slide 5: Sample Test-Regulation
Sample Test-Regulation Testing § 2 (2 - 4) • Tests are required: • Before first use • Immediately after a technical change in the physical structure • Immediately after a significant change in the technical system • Within a period of 3 years (recurring tests) • The tests are to be undertaken by the
Slide 6: VOB Part B
VOB Part B Defect claims § 13 (Section. 4) • For parts of mechanical and electrical/electronic systems, where maintenance has an influence on the safety and functionality, the period of limitation for defect claims is two years unless agreed otherwise, providing the contracting authority has decided
Slide 7: DIN VDE 0100-718
DIN VDE 0100-718 Installation of low voltage electrical installations - Requirements for special installations or locations – With the introduction of DIN VDE 0100-560, most sections of the DIN VDE 0100-718, which have been associated with safety lighting, have been replaced. The following sections
Slide 8: DIN VDE 0100-718
DIN VDE 0100-718 Initial tests (718.61) • The following additional tests are to be performed in addition to the DIN VDE 0100-600 (Installation of low-voltage systems Part 6: Testing): Inspect (718.61.1) • Compliance to operational norms? • Ventilation in battery areas, in accordance with EN 50272-2
Slide 9: DIN VDE 0100-718
DIN VDE 0100-718 Testing and Measurement (718.61.2) • Measuring the changeover behavior of power generation units • Inspecting the switching, control and monitoring functions • Assessing the starting and switching time during a power failure Recurring Tests (718.62) Inspection(718.62.2.1) • Annual t
Slide 10: DIN VDE 0100-718
DIN VDE 0100-718 Testing and Measurement (718.61.2.2) • Annual Test: Function switching set-up • Monthly Test: Function of combustion engines Minimum 1h with at least 50% rated power of power source • Annual Test: Capacity of battery system • Bi-annual Test: Insulation monitoring system Test Reports
Slide 11: DIN EN 50172 - Preliminary Standard DIN V VDE V 0108-100
DIN EN 50172 Emergency Lighting Systems As well as - Preliminary Standard- DIN V VDE V 0108-100 Emergency Lighting Systems © 2015 Eaton, All Rights Reserved. 11
Slide 12: DIN V VDE V 0108-100
DIN V VDE V 0108-100 General: Maintenance and Testing (7.1) • For automatic test equipment, the test results must be recorded monthly in the log book. • For all other systems, the tests are to be carried out under 7.3 and the results must be logged. • The operator of the building must designate a co
Slide 13: DIN V VDE V 0108-100
DIN V VDE V 0108-100 Recurring visual inspections and tests (7.3) • Where labour law or national technical rules are not otherwise determined, the following requirements must be met: General (7.3.1) • Tests of longer duration may only be undertaken during periods of low risk. © 2015 Eaton, All Right
Slide 14: DIN V VDE V 0108-100
DIN V VDE V 0108-100 Daily Tests (7.3.2) • Visual inspection: Correct function (only for non-maintained operation - no function test) of the display of the main power supply. The date of the test and its results must be included in the system logbook. • This can be achieved with a central signalling
Slide 15: DIN V VDE V 0108-100
DIN V VDE V 0108-100 Weekly Tests (7.3.3) • The function of the emergency lighting by switching on the power source for safety purposes, provided this is a battery-supported system. The function of all luminaires must be tested. • Automatic test equipment must adhere to DIN EN 62034 • The date of th
Slide 16: DIN V VDE V 0108-100
DIN V VDE V 0108-100 Monthly Tests (7.3.4) • The switching of every emergency lighting luminaire to battery-/SV- operation by simulating a failure in the supply of general lighting for a duration of sufficient length to ensure that every luminaire lights up. • For central battery systems, the monito
Slide 17: DIN V VDE V 0108-100
DIN V VDE V 0108-100 Annual Tests (7.3.5) • When using automatic test equipment, the results of the rated duration test must be recorded. • The annual test is not allowed to be triggered automatically. • For all other systems, tests must be undertaken annually in line with 7.3.4 and the following te
Slide 18: DIN V VDE V 0108-100
DIN V VDE V 0108-100 Annual Tests (7.3.5) • Inspection of each indicator lamp and signalling device • Inspection of the charging device • For generator sets, the following requirements are also applicable ISO 8528-12 und DIN 6280-13 • Testing of the batteries in line with DIN EN 50272-2 (VDE 0510-2)
Slide 19: DIN EN 50171
DIN EN 50171 Central power supply systems © 2015 Eaton, All Rights Reserved. 19
Slide 20: DIN EN 50171
DIN EN 50171 Automatic Test facility (6.11.4) • If automatic test equipment with means of recording the state of the system is used in place of a manual test, the test apparatus is required to have the following features: a) Continuous monitoring of charging; if the monitoring is done periodically,
Slide 21: DIN EN 50171
DIN EN 50171 Automatic Test facility (6.11.4) c) Registration of all errors in the central battery power supply system and all errors in the test facility or central monitoring area d) Fault indication that includes errors during transmission to the central monitoring area e) The means for undertaki
Slide 22: DIN EN 50171
DIN EN 50171 Installation of Batteries and Measures for maintenance (6.13) • The installation of batteries and measures for their maintenance must be carried out according to EN 50272-2 and in line with the manufacturers recommendation Manufacturers Instructions (bi-annual/ annual) • The testing and
Slide 23: DIN EN 50171
DIN EN 50171 When do batteries need to be replaced? • The following applies to systems installed before 08 / 2003: Replacing the batteries with less than 2/3 rated operating time (VDE 0108 10 /89 Part 1 Paragraph 9.3.1) • The following applies to systems installed after 08 / 2003 Replacing the batte
Slide 24: DIN EN 50272-2
DIN EN 50272 - 2 Safety requirements for batteries and battery systems Part 2: Static Batteries © 2015 Eaton, All Rights Reserved. 24
Slide 25: DIN EN 50272-2
DIN EN 50272-2 Inspection and Monitoring (14) • Batteries and their operating conditions must be checked for proper function and safety. In accordance with the requirements of the manufacturers, an inspections is designed to check: • Voltage settings of the charger • Voltage of the cells or monobloc
Slide 26: Monitoring methods for Luminaires
Monitoring methods for Luminaires © 2015 Eaton, All Rights Reserved. 26
Slide 27: Monitoring methods for Luminaires
Monitoring methods for Luminaires Circuit monitoring Automatic circuit monitoring: Circuit Influencing factors: monitoring • Fluctuating battery voltage (186 - 275 V) • Ageing lamps • Fluctuations in ambient temperature • Mixed configuration (large and small power) No reliable information on functio
Slide 28: Monitoring methods for Luminaires
Monitoring methods for Luminaires Automatic monitoring of single luminaires Automatic monitoring of single luminaires: The only option of a secure conclusion over the entire system. When considering testing costs, a return on investment is achieved from between 2-3 years, compared to standard system
Slide 29: CEWA GUARD Technology
CEWA GUARD Technology 3-wire technology with 3-wire technology request optic request by current measurement Request Request 2000 - 4. Generation 2-wire technology, request Mixed battery Gemischte type in Betriebsarten by current measurement, one in final circuit einem Endstromkreis reverse polarity
Slide 30: CEAG Notlichtsysteme GmbH, Soest