Sutter Gold Mining — Investor Presentation (May 2012)
27 slides from Sutter Gold Mining's investor presentation, May 2012
Slide 1: Building a New Gold Mine in California's Mother Lode
MAKING HISTORY . . . AGAIN Building a New Gold Mine in California’s Mother Lode May 2012 TSX-V:SGM OTCQX:SGMNF
Slide 2: Disclaimer
Disclaimer The following presentation may include certain “forward‐looking statements” within the meaning of applicable Canadian Securities Laws and the United States Private Litigation Reform Act of 1995. All statements, other than statements of historical fact, included in the presentation , inclu
Slide 3: Why Sutter Gold?
Why Sutter Gold? One of the few precious metals juniors that will transition to gold production in 2012 Fast‐tracking the first phase of the high‐grade Lincoln Mine Project in Amador County, California – the first commercial gold mine in the Mother Lode in more than 50 years Development philos
Slide 4: Experienced Management Team
Experienced Management Team Leanne Baker President & Chief Executive Officer Bob Hutmacher Chief Financial Officer Matt Collins Chief Operating Officer ‐ QP David Cochrane VP Environmental Health & Safety Steve Zahony VP Exploration and Geology ‐ QP Art Campo Chief Mine Geologist Amanda Miller Contr
Slide 5: Sutter at a Glance
SUTTER AT a Glance Sutter 5 Year Stock Price OTCQX TSX‐V 52 wk high $0.52 $0.51 52 wk low $0.11 $0.11 Avg g dailyy volume ((2012)) 45,300 3 50,000 Capital Structure (March 31, 2012) Cash Position $3.8 million RMB Gold Facility Draws $14.1 million Shares Outstanding 117.5 million Options 5.8 million
Slide 6: Investment Highlights
Investment Highlights Opportunity: Fast‐track the first phase of the Lincoln Mine Project while gold price fundamentals remain strong Share price starting to reflect our initial exploration success and recent progress on permitting and development Upside potential from current exploration dr
Slide 7: Lincoln Mine Project
Lincoln mine project adjacent to historic hwy. 49 Sutter controls a significant portion of the “California Mother Lode” vein system TSX--V:SGM OTCQX:SGMNF TSX
Slide 8: Lincoln Mine Project located in the prolific California Mother Lode gold belt
Lincoln mine Project excellent infrastructure Located between the towns of Sutter Creek (the historic Lincoln Mine) and Amador City (the historic Keystone Mine) Accessible by Highways 49 and 104 45 miles southeast of Sacramento in Amador County Power, communication, and transportation infras
Slide 9: Lincoln Mine Project History
Lincoln mine project HISTORY •John Sutter explored for timber in mid 1840’s and briefly for gold in 1848 1848 along the banks of what is now Sutter Creek •First gold discovery came in June 1851 by the Amador Quartz Mining 1851 Company. Leland Stanford gained control of the mine in the late 1850’s, a
Slide 10: Mineral Inventory
Mineral INVENTORY NI 43-101 compliant resource Uncut Grade Tons Contained Ounces Oz/ton O /to Indicated: Lincoln‐Comet 511,700 0.37 188,481 Keystone 161,900 0.21 34,563 Total Indicated 673,600 0.33 223,044 Total Inferred 2,377,900 0.19 458,914 Total Indicated and Inferred contained ounces 681,958 So
Slide 11: Lincoln Mine Project PEA
Lincoln mine project pea NI 43‐101 Preliminary Economic Assessment (PEA): Focused d only l on the h upper portion off the h Lincoln‐Comet l d deposit Utilizing existing mine infrastructure to minimize development costs and timing Base Case IRR of 20.5% at $1,100/ounce gold Sutter Gold Mini
Slide 12: Lincoln Mine Project Parameters
Lincoln mine project parameters High‐Grade Scenario Five‐Year Plan Indicated / Inferred Resource 210,300 210 300 t material 0.573 opt (19.6 gpt) Current Mining Plan 244,800 t material INSERT 0.46 opt (15.8 gpt) PHOTOS Cutoff Grade 0.22 opt (7.5 gpt) HERE Mine Operating Rate 150 tpd (7 days / week) M
Slide 13: Current Geologic Block Model & Workings
current geologic Block model & workings Grade Shell & Design at o.22 opt Au cut-off Existing Portal • Colors Identify Gold Veins • Existing Workings in Brown • Current Mine Design Strings (Drifts/Tunnels) Blue Lines • Modeling and Design in Surpac™ View Looking North at -25° Dip TSX- TSX-V:SGM TSX-
Slide 14: Capital Requirements
Capital requirements Capital Requirements – Lincoln Mine Project Estimated Cost USD$ Item 000’s Mine Equipment q p 4,213 Mine Development 2,680 Process Plant 4,120 Waste Management 2 052 2,052 Infrastructure 1,691 Engineering 463 Owners Cost 4,716 TOTAL $19,934 Expenditures to Mar 31, 2012 $2,800 TS
Slide 15: RMBAH Prepaid Gold Facility
rmbAH prepaid gold facility US$20 Million Prepaid Gold Facility In July l 2011, the h Company signed d an agreement with h RMB Australia l Holdings ld ((RMBAH)) to implement a $20 million prepaid gold facility The Company used the initial $6.6 million of the proceeds to repay a previous credit
Slide 16: Potential Cash Flow Model
Potential cash flow model Sutter Gold PEA Base B 10% % Above Ab 20% % Above Ab Cash Flow Sensitivity Mining Case Base Case Base Case Plan2 Pretax Cash Flow($000's)1 12,217 17,135 26,243 49,096 Internal Rate of Return, (% p.a.) 20.5% 38.9% 50.2% 69.6% Gold Selling Price ($/oz) 1 100 1,100 1 210 1,210
Slide 17: Path to Production
Path to production Site Preparation Completed in Winter 2011‐12 Mill Building g Permit Received March 2012 TSX--V:SGM OTCQX:SGMNF TSX
Slide 18: Critical Path to Gold in Q4 2012
Critical path to gold in Q4 2012 Underground mine development to begin in June 2012 Contract for f underground d d mining to b be awarded d d MSHA approval of ventilation plan and emergency contingency plan is required Surface Fill Unit construction during summer 2012 Section 404 (Wetlands
Slide 19: 2012 Priorities & Beyond
2012 Priorities & beyond Preparing for production: Completing mine development and building construction Obtain remaining construction financing Targeting production this year Planning for resource expansion ‐ Exploration Completed Ground Completed p Production Expand p Initial Breaking 43
Slide 20: Pipeline of Projects
Pipeline of Projects California mother lode Exploration potential on other projects adjacent to the Lincoln project 2012 focus is to advance exploration within existing land holdings:: Eureka Lincoln Keystone Bunker Hill TSX--V:SGM OTCQX:SGMNF TSX
Slide 21: 2012 Exploration Program
2012 exploration program Goal of the Program: INSERT PHOTO HERE Expand d gold ld resources at the h Lincoln l Mine Project Drill the under‐explored area between the Lincoln and Comet ore zones Better define the initial stage of underground mining TSX--V:SGM OTCQX:SGMNF TSX
Slide 22: Phase 1 Exploration Program Highlights
Exploration Program Highlights Phase 1 Phase 2 As of April p 10 Will include 13 drill holes Includes 17 diamond Results have been in the northern Comet drill holes in the southern announced for the first segment, where drilling in Lincoln segment, seven holes. Best results the past was inclined in i
Slide 23: Exploration Targeting
EXPLORATION TARGETING TSX--V:SGM OTCQX:SGMNF TSX
Slide 24: Exploration Targeting
EXPLORATION Targeting TSX--V:SGM OTCQX:SGMNF TSX
Slide 25: Phase 1 of Exploration Program
Phase 1 of exploration program 9 of 17 holes completed Lincoln and Southern portion of Comet resource (shown in red) at a 0.22 opt Au cut‐off. ddh‐206 ddh‐196 N & 197 ddh‐199 ddh‐201 ddh‐198 & 200 & 202 ddh‐203 ddh 203 & 204 LINCOLN COMET ZONE ZONE 0 200’ Phase I Drilling (Southern) Long Section: lo
Slide 26: Investment Opportunity
Investment Opportunity Potential for a three‐pronged increase in per‐ounce gold multiple: As we receive the rest of our permits and complete construction of the first commercial gold mine in the California Mother Lode in more than 50 years As we complete the ramp‐up to full production in 2013
Slide 27: Sutter Gold Mining Contact Information
SUTTER GOLD MINING Contact Information: 165 South Union, Suite 565, Lakewood, Colorado Robert Hutmacher, CFO Tel: 303‐238‐1438 www.suttergoldmining.com TSXV:SGM OTCQX: SGMNF