Westgold Resources Ltd · ASX:WGX

Westgold Resources — Investor Presentation (July 2020)

10 slides from Westgold Resources's investor presentation, Jul 23, 2020

  1. Slide 1: Westgold Investor Presentation, 23 July 2020

    23rd July, 2020 Peter Cook - Executive Chairman Rod Corps – Investor Relations 1

  2. Slide 2: Q4 and 12 Month Gold Sales, Costs and Cash Flow

    Q4 Gold Sales: 66,234 oz’s 12 Months: 235,150 oz’s Q4 Cash cost of sales (C1) : A$1,299 / oz 12 Months: A$1,261 / oz Q4 AISC: A$1,638 / oz 12 Months: A$1,531 / oz Q4 Achieved Gold Price: A$2,294 / oz 12 Months: A$2,088 / oz Mine Operating Cash Flow: A$60.1 million 12 Months: A$142.5 million Net Mine

  3. Slide 3: Continued Divesting Non-core Assets, sale of share investments

    Continued Divesting Non-core Assets, sale of share investments Liquidity events in investments created opportunity for exit at good prices. Repaid debt in full, cashed up to close with $137.4m in cash and bullion. Patiently picking off last pieces in the Central Murchison jigsaw to aid and abet grou

  4. Slide 4: Cash and Gold on Hand - Q4 Movement

    WESTGOLD Cash and Gold on Hand - Q4 Movement June 2020 Quarter Results

  5. Slide 5: All costs quoted in Australian Dollars

    (All costs quoted Australian Dollars A$) For International comparison only: US$: A$ Exch Rate = 0.70 US$840 - $910/oz US$1,020 - $1090/oz 5

  6. Slide 6: Peter Cook - Executive Chairman

    Peter Cook –Executive Chairman 6

  7. Slide 7: Big Bell South Schematic Long-Section

    Schematic Long-Section < Big Bell South > WESTGOLD SOOmAL Big Bell Trend (2019) Total Resource 53.8Mt at 2.69/t for 4.4Moz Big Bell Underground (2019) Total Resource 11Mt at 3.7g/t for 1.3Moz Reserve 9.8Mt at 3.0g/t for 948Koz 1000mRL Reserve Previousty Mined — Existing Development Planned Developme

  8. Slide 8: Plan View (Generic Geology)

    Plan View (Generic Geology) WESTGOLD WESTGOLD RESOURCES LIMITED ——— 600E 560 RL Level 3370N 3460N 1 Potential Extension 2019 Converted with 2020 grade control Cave Block Extension Converted Extension Reserve Previously Mined Existing Development Planned Development Drillhole Intersection (Schematic)

  9. Slide 9: To 3200N still in ore

    3,400N 3,500N 3,600N 3,700N 3,800N 3,900N 4,000N SO H NOR H E IS ING CA E 485 S To 3200N still in ore 485 N 03/07/2020 12 ) 15305 10885 10,000 @ 510 S 3.0 / 510 N 36 C F 36 C 27/06/2020 1 4,200 @ 28984 20945 12,375 @ ACC H 3.0 / 3.0 / 535 S 535 N 08/08/2020 F F 12/07/2020 31781 48304 560 N F F 10,20

  10. Slide 10: JORC Compliance Statement

    JORC COMPLIANCE STATEMENT Competent Persons Statements • The information in this report that relates to Exploration Results and Mineral Resources and Ore Reserves is based on information compiled Mr Jake Russell B.Sc. (Hons) MAIG, Mr Paul Hucker B. Eng (Hons) MAIMM, and Anthony Buckingham B.Eng (Min