Riot Platforms, Inc. · NASDAQ:RIOT

Riot Platforms — Q3 2025 Earnings Presentation

44 slides from Riot Platforms's earnings presentation, Oct 30, 2025

  1. Slide 1: Riot Platforms Q3 2025 Update

    NASDAQ: RIOT Riot Platforms (NASDAQ: RIOT) Q3 2025 Update October 30, 2025 Corsicana data center conceptual rendering

  2. Slide 2: Forward Looking Statements

    Forward Looking Statements Statements in this presentation that are not statements of historical fact are forward-looking statements that reflect management’s current expectations, assumptions, and estimates of future performance and economic conditions, and are not guarantees of future performance

  3. Slide 3: Table of Contents

    •I Q3 2025 KEY HIGHLIGHTS •II BUSINESS UPDATE: DATA CENTERS Table of • RIOT POWER PORTFOLIO III Contents • Q3 2025 FINANCIAL UPDATE IV •V RIOT’S CLOSING REMARKS

  4. Slide 4: Q3 2025 Key Highlights

    -Q3.2025 KEY HIGHLIGHTS

  5. Slide 5: Riot Announces Initiation of Core & Shell Development at Corsicana

    Riot Announces Initiation of Core & Shell Development at Corsicana Initiating Core & Shell development of first 2 buildings at Corsicana Data Center campus, representing 112 MW of critical IT load capacity Corsicana data center conceptual rendering Enabled By 1 Acquired 67-Acre Parcel Adjacent to Co

  6. Slide 6: Business Update: Data Centers

    BUSINESS UPDATE: II DATA CENTERS

  7. Slide 7: Significant Progress in the Data Center Business Continues

    Significant Progress in the Data Center Business Continues Completed Progressing 01 Engaged Consultants Ongoing Build Advance Future 05 Infrastructure Development 06 Internal Expertise 07 Leasing Discussions 08 Pipeline Added 02 Experience the Board to Engaged 03 Financial Advisors Initiated develop

  8. Slide 8: Riot's Basis of Design for Data Centers Completed

    Riot’s Basis of Design for Data Centers Completed Exterior Building: Two-story design Enable maximization of campus capacity with single, two & three story designs 7-MOD Centered Dual-Level: Tri-Level: Design • 56 MW Critical IT • 84 MW Critical IT Standards • ~325,000 SF • ~500,000 SF • (4) 7-MODs

  9. Slide 9: Establishing an Industry-Leading Team with Proven Experience and Results

    Establishing an Industry-Leading Team with Proven Experience and Results Key hires made across design, engineering, sales, procurement, construction, operations, marketing & administration to deliver at scale Key Roles Added Riot Data Center Team ▪ Chief Data Center Officer ▪ Senior Vice President o

  10. Slide 10: Corsicana Site Now Ideally Positioned to Fully Utilize 1 GW of Power

    Corsicana Site Now Ideally Positioned to Fully Utilize 1 GW of Power Corsicana Land Holdings Now Total 925 Acres In September 2025, Riot entered a contract to acquire an additional 67-acre parcel contiguous with the existing 265-acre Corsicana site for $40 million 1 ✓ No easements required to bring

  11. Slide 11: Corsicana Data Center Campus Will be Developed Over Two Phases

    Corsicana Data Center Campus Will be Developer Over Two Phases Phase 1 504 MW Total Critical IT Load Capacity Six 56 MW Buildings Substation Two 84 MW Buildings PHASE 1 Expansion ▪ Development of Core & Shell for first two buildings initiated ▪ Pace of development will be driven by tenant demands Ph

  12. Slide 12: Riot has Initiated Core & Shell Development at Corsicana

    Riot has Initiated Core & Shell Development at Corsicana Riot’s Core & Shell represents the first stage of data center development, where the exterior is complete, with additional infrastructure ready to support full buildout ▪ As part of Corsicana Phase 1, Riot has initiated Core & Shell developmen

  13. Slide 13: Riot Power Portfolio

    RIOT III POWER PORTFOLIO

  14. Slide 14: Power-First Strategy

    POWER-FIRST STRATEGY APPROACH FOCUS ON TO BTC MINING MAXIMIZING THE VALUE HAS EVOLVED OF OUR MEGAWATTS Provides greater optionality in the Our goal is to fully convert Riot’s megawatts utilization of our current power to Data Center use over time portfolio “Tool” to monetize Riot’s large-scale BTC M

  15. Slide 15: Riot's North American Power Portfolio Ranks Amongst the Largest Within the Data Center Vertical

    Riot’s North American Power Portfolio Ranks Amongst the Largest Within the Data Center Vertical 4,088 MW Acquired on Oct. 15th, 2025, by Public Companies Nvidia, Microsoft, xAI, and Private Companies BlackRock for $40 billion (EV) 2,605 MW 2,550 MW 1,862 MW 1,857 MW 1,535 MW 1,505 MW 1,475 MW 1,084

  16. Slide 16: Riot Currently Trades Among the Lowest EV/MW Multiples in the Sector

    Riot Currently Trades Among the Lowest EV/MW Multiples in the Sector EV / 2027 Available MW 1,2 ($m) $9.2 ▪ Riot currently has 1,862 MWs of fully permitted and readily available power $7.3 $7.2 $6.3 ▪ When compared to a peer group of public Bitcoin Miners, Riot $5.3 Median: $4.9 trades at a discount

  17. Slide 17: Q3 2025 Financial Update

    Q3 2025 IV FINANCIAL UPDATE

  18. Slide 18: Riot Platforms Q3 2025 Snapshot

    RIOT PLATFORMS Q3 2025 SNAPSHOT Financial Metrics BTC Statistics $180 million Total Revenue 1,406 BTC Produced 18% increase quarter-over-quarter Daily production of 15.3 BTC per day $104 million Net Income 19,287 BTC Held Represents a 58% margin Quarter-end value of $2.2 billion 3 $0.26 Earnings per

  19. Slide 19: Bitcoin Mining Driving Strong Cashflows Supporting the Data Center Platform

    Bitcoin Mining Driving Strong Cashflows Supporting the Data Center Platform 1 Improvements in operational uptime and economies of scale continue to be realized Period Q4 2024 Q1 2025 Q2 2025 Q3 2025 LTM Global Network Hash Rate (Avg.) 728 EH/s 801 EH/s 876 EH/s 948 EH/s 838 EH/s Riot Operating Hash

  20. Slide 20: Riot Engineering is a Leader in Service and Equipment Manufacturing for Data Center Infrastructure

    Riot Engineering is a Leader in Service and Equipment Manufacturing for Data Center Infrastructure “In terms of the biggest components that are in short supply … The biggest would be the low and medium voltage switchgear …” UBS Global Research Report (May 2025) ▪ Riot Engineering provides significan

  21. Slide 21: Economies of Scale Driving Ongoing SG&A Cost Reduction

    Economies of Scale Driving Ongoing SG&A Cost Reduction Increasingly Disciplined Approach to Key Accomplishments Cost Control Showing Results 1 SG&A $66.9 $81.1 $71.4 $75.9 $69.8 Rhodium Settlement and Asset Acquisition: ($m) Eliminates future losses on the legacy hosting contract ($14.6M in Revenue

  22. Slide 22: Riot Closing Remarks

    RIOT V CLOSING REMARKS

  23. Slide 23: Unique, Synergistic Portfolio of Power, BTC Mining, and Treasury Assets

    Unique, Synergistic Portfolio of Power, BTC Mining, and Treasury Assets Driving Growth of Large-Scale Data Center Business Infrastructure • Maximizing the value of every watt in our Data Centers Engineering power portfolio • Transitioning Bitcoin Mining to Data Center Powered Land Shareholder operat

  24. Slide 24: Appendix: Q3 Operational Data

    APPENDIX Q3 OPERATIONAL DATA

  25. Slide 25: Bitcoin Mining – Increasing Efficiency and Scale of Operations

    Bitcoin Mining – Increasing Efficiency and Scale of Operations Riot Revenue Breakdown – Q3 2025 3 Q3 2024 Q4 2024 Q1 2025 Q2 2025 Q3 2025 Avg. Hash Price $45 $54 $54 $51 $56 $/PH/s/Day) 11% Avg. Network 625 EH/s 728 EH/s 801 EH/s 876 EH/s 948 EH/s Bitcoin Mining Hash Rate1 Engineering Cost to Mine2

  26. Slide 26: Profitability per Bitcoin Mined Remained In-Line with Prior Quarter

    Profitability per Bitcoin Mined Remained In-Line with Prior Quarter Q2 2025 vs. Q3 2025 Cost to Mine per BTC Q2 2025 1 Q3 2025 2 ▪ Average global network hash rate up 8% in Q3 1,426 BTC Mined 1,406 BTC Mined 2025 vs Q2 2025 Avg. BTC Price of $98,800 Avg. BTC Price of $114,361 - Global network hash r

  27. Slide 27: Engineering – A Key Component of Riot's Vertical Integration Strategy

    Engineering – A Key Component of Riot’s Vertical Integration Strategy Riot Riot Revenue Revenue Breakdown Breakdown –– Q3 202311 Q4 2025 $23.0 11% Cumulative Capex $12.4 $10.4 Bitcoin Mining Savings to $7.5 Engineering Riot $0.3 89% 2021 2022 2023 2024 Q3 2025 $159.6 $114.9 $118.7 Growing $67.8 ▪ Si

  28. Slide 28: Key Capital Expenditures

    Key Capital Expenditures Q4 2025 YTD 2025 Use of Funds Forecasted Description Spend Capex ▪ Includes Core & Shell capex for first 2 buildings at the Corsicana Data Corsicana Data Center Campus - Center campus $0.2 million $3.4 million Core & Shell Development ▪ Represents 112 MW of critical IT with

  29. Slide 29: Maintaining Bitcoin Mining Market Share Through Measured Growth in Installed Hash Rate

    Maintaining Bitcoin Mining Market Share Through Measured Growth in Installed Hash Rate Historical 43.5 EH/s 38.5 EH/s 36.5 EH/s 35.4 EH/s 33.7 EH/s 31.5 EH/s 28.2 EH/s 22.0 EH/s 12.4 EH/s 12.4 EH/s 9.7 EH/s 3.1 EH/s 2021A 2022A 2023A Q1 2024A Q2 2024A Q3 2024A Q4 2024A Q1 2025A Q2 2025A Q3 2025E Q4

  30. Slide 30: Appendix: Q3 Financial Data

    APPENDIX - Q3 FINANCIAL DATA

  31. Slide 31: Definitions, Terms, and Reconciliations (Unaudited)

    Definitions, Terms, and Reconciliations (Unaudited) Cost of Power: The Company defines Cost of Power as the cost of power directly used in the process of mining bitcoin, less power curtailment credits divided by the kilowatt (“kWh”) hours used. Power is overwhelmingly the largest marginal input cost

  32. Slide 32: Definitions, Terms, and Reconciliations (Unaudited)

    Definitions, Terms, and Reconciliations (Unaudited) Fully Costed Gross Margin: The Company defines Fully Costed Gross Margin as Fully Costed Gross Profit (as defined below) divided by Revenue as calculated below. Three Months Ended Three Months Ended Nine Months Ended December 31, March 31, June 30,

  33. Slide 33: Definitions, Terms, and Reconciliations (Unaudited)

    Definitions, Terms, and Reconciliations (Unaudited) Cash SG&A: The Company defines Cash SG&A as Selling, General, and Administrative expenses less Stock-Based Compensation expense. Cash SG&A is used by the Company as we believe it better reflects the operational requirements of the Company by exclud

  34. Slide 34: Definitions, Terms, and Reconciliations (Unaudited)

    Definitions, Terms, and Reconciliations (Unaudited) Gross Profit: The Company defines Gross Profit as Fully Costed Gross Profit (as defined below) plus Power curtailment Credits plus Deprecia tion & Amortization expense. Three Months Ended Three Months Ended Nine Months Ended December 31, March 31,

  35. Slide 35: Definitions, Terms, and Reconciliations (Unaudited)

    Definitions, Terms, and Reconciliations (Unaudited) Hash Cost: The Company defines Hash Cost as Cost of Revenue for self-mining operations, net of Power Curtailment Credits, excluding Bitcoin miner depreciation divided by the average Petahash per second per day (“PH/s/Day”) produced by operations ov

  36. Slide 36: Q3 2025 Statement of Operations (Unaudited)

    Q3 2025 Statement of Operations (Unaudited) 36

  37. Slide 37: Q3 2025 Balance Sheet (Unaudited)

    Q3 2025 Balance Sheet (Unaudited) 37

  38. Slide 38: Non-GAAP Adjusted EBITDA (Unaudited)

    Non-GAAP Adjusted EBITDA (Unaudited) * Indicates Non-GAAP measure. We use Adjusted EBITDA to eliminate the effects of certain non-cash and/or non-recurring items, that do not reflect our ongoing strategic business operations. Adjusted EBITDA is provided in addition to, and not as a substitute for, o

  39. Slide 39: Appendix: Industry Data

    APPENDIX - INDUSTRY DATA

  40. Slide 40: Current ERCOT Energization Timeline is Prohibitively Lengthy

    Current ERCOT Energization Timeline is Prohibitively Lengthy Total ERCOT energization timeline of ~4+ years dependent on location/utility provider, scope of project, etc. 2026 2027 2028 2029 2030 Includes pre-application, scoping, Planning 6 Months and formal queue entry Includes screening study, sy

  41. Slide 41: Existing Grid Infrastructure is Not Sufficient to Meet Forecasted Demand

    Existing Grid Infrastructure is Not Sufficient to Meet Forecasted Demand US On-Grid Annual Electricity Demand (GW) Significant Lead Times to Procure Power2 600 Market Share Market By Net UPS Power¹ Months² Pittsburgh, PA 0.3% 36 550 2 2024-2030 2.2% CAGR Chicago, IL 7.7% 36 Houston, TX 1.7% 36 1 200

  42. Slide 42: Proximity to Tier 1 Data Centers in the United States

    Proximity to Tier 1 Data Centers in the United States Tier 1 DC Emerging market DC market Tier 2 DC Riot market sites 42

  43. Slide 43: Appendix: Management Team & Board of Directors

    APPENDIX MANAGEMENT TEAM & BOARD OF DIRECTORS

  44. Slide 44: Management Team and Board of Directors

    Management Team and Board of Directors Benjamin Yi Jason Les Executive Chairman of the Board Chief Executive Officer; Director Jonathan Gibbs William Jackman Colin Yee Stephen Howell Jason Chung Chief Data Center Officer Executive Vice President, Executive Vice President, Chief Operating Officer Exe