Harmony Gold Mining Co. Ltd. · JSE:HAR

Harmony Gold Mining — Corporate Update (May 2006)

65 slides from Harmony Gold Mining's corporate update, May 26, 2006

  1. Slide 1: Analyst and Media Visit Phakisa/Tshepong

    Analyst and Media Visit Phakisa /Tshepong 26 May 2006

  2. Slide 2: Location

    LOCATION HARMONY” a FREE STATE | 4 N y NN ba (7 HARMONY FREE-GOTO > OPE INS PREG STEY REE GOLD| “At jeer 1 @ Odendaalsrus x °o a HARMONY FREE STATE o * OPERATIONS Boo - L we © S ¥c a | HARMONY WELKOM\ | 9” 9, 97 OPERATIONS \———<7/]_ @ ° | @NYALAX — ey / ij

  3. Slide 3: Phakisa Project

    HARMONY’ PHAKI SA PRO/ECT

  4. Slide 4: Project Team Vision

    PHAKISA PROJECT VISION Project Team Vision Safety: Zero fatal incidents, overall improvement of safety performance of 5 % per year Project: • Completion of the Phakisa project on time within budget to world class standard. •Increase in SAMREC reserve ounces. •To give value to our stake holders.(Empl

  5. Slide 5: Project Team Vision (continued)

    PHAKISA PROJECT VISION Project Team Vision (continued) • Introduce new technology • Implement a culture of people wellness – Best training - (Self Directed Work Teams) – Safety & Health - (HIV awareness, safe behavior) • Implement new mine occupational hygiene conditions – 26°c wet bulb temperatures

  6. Slide 6: Phakisa Area

    PHAKISA AREA Phakisa Shaft Phakisa area 69 to 85 L Phakisa Gift Block Decline 75 to 85 L

  7. Slide 7: Project Goal

    “PHAKISA GOAL” Project Goal: “To hoist 90 000 tons of ore per month producing 648 kg at R425 / ton (2005/6 m/terms) by May 2010”

  8. Slide 8: Comparison of NPVs

    PHAKISA PROJECT COMPARISON OF NPV’S Gold Price (kg) NPV @ 7.5% (MILLIONS) IRR R 92 000 R 1,327m 26% R 100 000 R 1,729m 30% R 105 000 R 1,980m 32% R 110 000 R 2,230m 34% R 120 000 R 2,732m 38% 2005/6 Terms

  9. Slide 9: Financial Indicators: Sensitivity Analysis

    FINANCIAL INDICATORS (R’MILLION) Sensitivity Analysis @ R105,000/kg Revenue (Gold price & Grade) Working Costs Capex 3000 2500 2000 NPV 1500 1000 R 1,980m 500 0 -10% -5% Base +5% +10% % Change in parameters

  10. Slide 10: Name Plate

    PHAKISA PROJECT NAME PLATE Name Plate: - (Sept’05/06) Production Parameters (Ave LOM) R/Kg Au R/Kg 59310 $/Oz @ R6.50:$1 $/Oz 284 R/ton R/ton 425 Monthly Production (Ave @ Full Cap) Kg Kg 648 Oz Oz 20833 Dry Tons Milled t/mth 88916 Recovered Grade g/ton 7.29 1st Gold Production May 2008

  11. Slide 11: Project Objectives

    PROJECT PROJECT OBJECTIVES Project Objectives Project started July 2003 Schedule 52% vs. 53% planned • First revenue May 2008 • Full production May 2010 • Completion of the Project February 2009 Cost 54% vs. 62% planned • Budget cost R397.5m • Final Estimated Cost R 644.1m • Spent to April 2006 R 34

  12. Slide 12: Annual Capital Expenditure Profile

    PHAKISA FINANCIAL STATUS Annual Capital Expenditure Profile Table (R million) 2004 2005 2006 2007 2008 2009 Actual Sunk 117.3 115.9 114.5 Forecast 49.6 143.1 87.2 16.5 Total 117.3 115.9 164.1 143.1 87.2 16.5

  13. Slide 13: Phakisa Project: Surface Work Complete by End 2006

    PHAKISA PROJECT END 2006 Surface Mechanical - 100% Koepe Winder Electrical - 100% 55 Level Rock silo Complete 54 Level NYALA 55 Level 55 to 59 Level Vent pass - 100% Fridge-plant HAULAGE TO NYALA Rail-Veyor to Nyala Primary Support in progress 59 Level 63 Level 66 Level 69 Level OR E RE SE R VE 21 7

  14. Slide 14: Phakisa Project: End of Project

    PHAKISA PROJECT END OF PROJECT Surface Koepe Winder 55 Level Rock silo Complete 54 Level NYALA 55 Level HAULAGE TO NYALA Fridge-plant Rail-Veyor to Nyala 59 Level 63 Level START 66 Level –28/12/06 66 Level START 69 Level 69 Level –28/11/06 OR E RE SE R MAY. 2008 VE 71 Level START 71 Level – 14/11/06

  15. Slide 15: Phakisa Surface Layout

    HARMONY’ PHAKISA SURFACE LAYOUT

  16. Slide 16: Phakisa Project Technical

    PHAKISA PROJECT TECHNICAL EXPLOSIVE BAY ENG. WORKSHOP FAN STORE TIMBER YARD COFFERDAM RECLAMATION IMS EQUIPMENT YARD CORE YARD WINDER EXISTING OFFICES PARKING YARD NEW OFFICES SERVICES CENTRE ESCOM YARD CHANGE HOUSES SHAFT

  17. Slide 17: Harmony Innovation: Bulk Material Handling System

    HARMONY INNOVATION BULK MATERIAL HANDLING SYSTEM 55 LEVEL

  18. Slide 18: A World-First Underground Rail-Veyor System

    PHAKISA PROJECT RAIL-VEYOR THE SOLUTION: A WORLD-FIRST U/G RAIL-VEYOR SYSTEM

  19. Slide 19: Rail-Veyor Layout of Tramming Haulage on 55 L

    RAIL-VEYOR LAYOUT OF TRAMMING HAULAGE ON 55 L The tramway from Phakisa to Nyala is designed to support the production profile of 115 000 tons per month (Design capacity 135 000 tons per month, main constraint, man/material winder) NYALA 3# - VENT SHAFT Conventional bulk handling systems, locomotive

  20. Slide 20: Rail-Veyor Characteristics

    PHAKISA PROJECT RAIL-VEYOR CHARACTERISTICS • Safer – low fire and accident risks • Combines the best features of a conveyor and rail systems. • Conveys material as a conveyor with high flexibility and increased capacity possibility. • Negotiate curves as a rail system. • No extensive access developm

  21. Slide 21: Rail-Veyor Summary of the Three Scenarios

    PHAKISA PROJECT RAIL-VEYOR SUMMARY OF THE THREE SCENARIO’S Rail Conveyor Railveyor system system system Initial Capital R 31.186 m R 30.620 m R 21.116 Installation Period in months 25 18 12 Operating cost R/ton R 5.68 R 3.58 R 2.51 Availability 70% 85% 98% Flexibility (increase capacity) 0% 120% 250

  22. Slide 22: Rail-Veyor

    PHAKISA PROJECT RAIL-VEYOR HARMONY’ /

  23. Slide 23: Rail-Veyor

    PHAKISA PROJECT RAIL-VEYOR External drive station @ 367m spacing Motor Gearbox Drive wheel Drive plate

  24. Slide 24: Rail-Veyor

    PHAKISA PROJECT RAIL-VEYOR Train going up the tipping loop

  25. Slide 25: Rail-Veyor

    PHAKISA PROJECT RAIL-VEYOR Tipping at 3-5 m/s

  26. Slide 26: Rail-Veyor

    PHAKISA PROJECT RAIL-VEYOR Loading at 3 m/s

  27. Slide 27: Rail-Veyor

    PHAKISA PROJECT RAIL-VEYOR Testing the double track

  28. Slide 28: Investigating New Technology

    PHAKISA PROJECT INVESTIGATING NEW TECHNOLOGY Other New Mine Technology includes: • Electric Rockdrills for stoping • New generation universal drill rigs for development • Minimise the use of compressed air throughout the mine • Maximise position efficiency of fridge plants • Employ Vapour Mist or Fo

  29. Slide 29: Investigating New Technology

    PHAKISA PROJECT INVESTIGATING NEW TECHNOLOGY In Stope Roof Bolter

  30. Slide 30: Investigating New Technology

    PHAKISA PROJECT INVESTIGATING NEW TECHNOLOGY Roof Support Drill Rig Development End Drill Rig

  31. Slide 31: Investigating New Technology

    PHAKISA PROJECT INVESTIGATING NEW TECHNOLOGY Power Pack

  32. Slide 32: Investigating New Technology

    PHAKISA PROJECT INVESTIGATING NEW TECHNOLOGY Tip cover with Fogger System for dust allaying

  33. Slide 33: Investigating New Technology

    PHAKISA PROJECT INVESTIGATING NEW TECHNOLOGY New cordless LED cap lamp

  34. Slide 34: Investigating New Technology

    PHAKISA PROJECT INVESTIGATING NEW TECHNOLOGY Loco complying to RBE Code of Practice

  35. Slide 35: Investigating New Technology

    PHAKISA PROJECT INVESTIGATING NEW TECHNOLOGY High Speed Settler

  36. Slide 36: Phakisa Labour Build-Up Plan

    PHAKISA PROJECT LABOUR BUILDUP PHAKISA LABOUR BUILD - UP PLAN 1400 1200 1170 1000 EMPLOYEES 783 800 600 400 200 0 Nov-06 Nov-07 Jun-06 Jul-06 Jan-07 Jun-07 Jul-07 Apr-06 Mar-07 Apr-07 May-06 Aug-06 Sep-06 Oct-06 Dec-06 Feb-07 May-07 Aug-07 Sep-07 Oct-07 Dec-07 Phakisa Labour Plan Phakisa Access & De

  37. Slide 37: Tshepong Sub 66 Project

    HARMONY’ TSHEPONG SUB 66 PRO/ ECT

  38. Slide 38: Project Goal

    “SUB 66 GOAL” Project Goal: “To hoist 48 560 tons of ore per month producing 350kg at R433 / ton (2005/6 m/terms) by July 2008”

  39. Slide 39: Tshepong Sub 66 Area

    TSHEPONG SUB 66 AREA Tshepong Existing Shaft Tshepong Workings Sub 66 Area Decline 66 to 71 L

  40. Slide 40: Name Plate

    NAME PLATE Name Plate: - (Sept’05/06) Production Parameters (Ave LOM) R/Kg Au R/Kg 60076 $/Oz @ R6.50:$1 $/Oz 287 R/ton R/ton 433 Monthly Production (Ave @ Full Cap) Kg Kg 350 Oz Oz 11253 Tons t/mth 48560 Recovered Grade g/ton 7.21 1st Gold Productions August 2006

  41. Slide 41: Project Objectives

    PROJECT OBJECTIVES Project Objectives Project started April 2003 Schedule 59% vs. 64% planned • First revenue August 2006 • Full production July 2008 • Completion of the Project February 2008 • Completion of the Sinking the Decline December 2006 Cost 61% vs. 65% planned • Budget cost R280.4m • Final

  42. Slide 42: Technical Description

    TECHNICAL DETAIL Technical Description • The twin decline system extends from 65 level to 72 level. • Total length of 1164m • Open mining levels 69 and 71. • The Material decline - Belt conveyor and monorail system. • The Chair-lift decline - Transportation of men.

  43. Slide 43: Configuration Material Decline

    CONFIGURATION MATERIAL DECLINE MONO CONVEYOR RAIL SERVICES MATERIAL DECLINE 6 X 4 Contains the conveyor for rock handling and Mono-Train for material handling.

  44. Slide 44: From the Mono-Train Cab

    FROM THE MONO-TRAIN CAB HARMONY”

  45. Slide 45: Macro Schedule

    MACRO SCHEDULE Macro schedule Mining Development 55% Decline Access development 82 % completed 69 L Access Development 66% completed X/C 98 & 93 in progress, X/C 95 & 96 completed 71 L Access development 19% Completed 71 station and tipping x/c completed. Raise development 16% 69 raise 95 73%, 69 ra

  46. Slide 46: Sub 66 2nd Access Haulage

    Sub 66 2nd Access Haulage of 1.5 km Equipped with rail line

  47. Slide 47: Milestones for Next Year

    MILESTONES Milestones for next year Mining Development Complete sinking the decline Raise bore 69- 71 ore passes Complete 69 L& 71 L Access Development Completed 3 raise lines Raise development Completed 4 raise lines Engineering Complete Conveyor Complete chairlift Complete Water distribution 71 le

  48. Slide 48: Project Status

    PROJECT STATUS Schedule to Full CHAIR LIFT Production DECLINE 12 DEG Holing of Raises Decline completed MATERIAL DECLINE 12 DEG MARCH 06 PROJECT BOUNDARY MARCH 06 Oct 2007 FEB 2008 DEC 05 Dec 2006 May 2006 Aug 2006 MARCH 06 Dec 2007 X/C 95 X/C 96 X/C 98 MARCH 06 MAR 06 PROJECT BOUNDARY X/C 90 X/C 92

  49. Slide 49: Annual Capital Expenditure Profile

    FINANCIAL STATUS Annual Capital Expenditure Profile Table (R million) 2003 2004 2005 2006 2007 2008 Actual Sunk 32.8 66.6 40.6 38.0 Forecast 17.4 55.0 29.9 Total 32.8 66.6 40.6 55.4 55.0 29.9 No budget overrun is foreseen for the project, only a cash flow shift from 2006 to 2007

  50. Slide 50: Gold Recovered Sub Projects

    GOLD RECOVERED SUB 66 PROJECTS Gold Production LOM Au/.Year Progress 4,500 50000 Full Production 4,000 45000 40000 3,500 35000 Au Kg Progressive 3,000 Au Kg/year 30000 2,500 25000 2,000 20000 1,500 15000 1,000 10000 500 5000 - 0 2010/11 2012/13 2014/15 2016/17 2018/19 2004/5 2002/3 2006/7 2008/9 200

  51. Slide 51: Comparison of NPVs

    COMPARISON OF NPV’S Gold Price (kg) NPV @ 7.5% (MILLIONS) IRR R 92 000 R 738.27 32.4% R 100 000 R 914.04 36.2% R 105 000 R 1 023.89 38.4% R 110 000 R 1 133.53 40.7% R 120 000 R 1 353.24 44.3% 2005/6 Terms

  52. Slide 52: Financial Indicators

    FINANCIAL INDICATORS NPV @7.5% REVENUE AU= R105 000/KG OPEX CAPEX 1800 1600 1400 1200 RAND MILLION 1000 800 600 R 1,023m 400 200 0 -25% -20% -15% -10% -5% 0 5% 10% 15% 20% 25% % VARIATION

  53. Slide 53: Synergy Phakisa & Tshepong

    HARMONY’ SYNERGY PHAKI SA & TSHEPONG

  54. Slide 54: Tshepong/Phakisa Mine

    TSHEPONG/PHAKISA MINE • Create a world class gold mine • From a proven track record • Known mining conditions • Modern infrastructure • Compared to other projects – low risk • Production built-up – low risk and bankable

  55. Slide 55: Tshepong & Phakisa Area Combined

    TSHEPONG & PHAKISA AREA COMBINED TSHEPONG EXISTING WORKINGS SUB 66 AREA PHAKISA AREA GIFT BLOCK

  56. Slide 56: Tshepong & Phakisa Total Resource & Reserve

    TSHEPONG & PHAKISA TOTAL RESOURCE & RESERVE Resources • 166.5m metric tons at 9.11g/t for 1516 tons gold • 183.5m short tons at 0.266oz/t for 48.7m oz gold Reserves • 43.2m metric tons at 7.20g/t for 311 tons gold • 47.6m short tons at 0.210oz/t for 10.0m oz gold (Current @ R92 000/kg)

  57. Slide 57: Tshepong & Phakisa Total Production

    TSHEPONG & PHAKISA TOTAL PRODUCTION Monthly Production Tons Milled 245 000 Rec. Grade 7.07 Gold Produced (kg) 1 733 (55 717oz) R/kg 62 800 $/Oz @ R6.50:$1 301 R/t 445 Annual Ounces 668 600

  58. Slide 58: Tshepong & Phakisa Connected

    TSHEPONG & PHAKISA CONNECTED HOLED ON 55 L HOLED ON 66 L TO BE HOLED ON 69 L TO BE HOLED ON 71 L

  59. Slide 59: Immediate Opportunities

    TSHEPONG & PHAKISA AREA COMBINED Immediate opportunities . • Dumping of water via 55 level to Nyala shaft • Ventilating Tshepong east block from Phakisa • Power back-up supply from Tshepong to Phakisa • Sharing of infra structure i.e. Control room, equipment, management, skilled people, etc. (ecomom

  60. Slide 60: Possible Future Expansions

    TSHEPONG & PHAKISA POSSIBLE FUTURE EXPANSIONS Phakisa Tshepong -1677 BC 55 lvl Linked to Nyala 57 lvl 59 lvl Linked to Eland Sub Shaft 60 lvl 63 lvl 63 lvl 66 lvl 66 lvl 69 lvl 69 lvl 71 lvl 71 lvl DECLINE 73 lvl POSSIBLE FUTURE 75 lvl EXTENSION 77 lvl 77 lvl 79 lvl 81 lvl 83 lvl 85 lvl

  61. Slide 61: Tshepong & Phakisa Connected

    TSHEPONG & PHAKISA CONNECTED Holed on 55 L Holed on 66 L To be Holed on 69 L To be Holed on 71 L Opportunity to Hole on 73 L in future Opportunity to Hole on 75 L in future

  62. Slide 62: Future Opportunities

    TSHEPONG & PHAKISA AREA COMBINED Future Opportunities • Improved Ventilation at lower levels. • Possible rock transfer from Phakisa to Tshepong shaft, this will eliminate the 5 km tramming to Nyala. • Production synergies. • Exchange ground to improve the overall NPV.

  63. Slide 63: Exchange Ground for Early Gold

    TSHEPONG & PHAKISA EXCHANGE GROUND FOR EARLY GOLD Current investigation in progress to exchange blocks of ground which will access high grade gold earlier, this will have a positive effect on the NPV. Tshepong existing workings Short distance Longer distance Short distance SUB 66 Area Longer distanc

  64. Slide 64: Private Securities Litigation Reform Act Safe Harbor Statement

    PRIVATE SECURITIES LITIGATION REFORM ACT SAFE HARBOR STATEMENT This presentation contains "forward-looking statements" within the meaning of Section 27A of the Securities Act of 1933, as amended, and 21E of the Securities Exchange Act of 1934, as amended, that are intended to be covered by the safe

  65. Slide 65: Questions

    Phakisa & Tshepong QUESTIONS www.harmony.co.za

Harmony Gold Mining — Corporate Update (May 2006) on 6ix