  1. Slide 1: Canada Water Development Construction Liaison Forum

    Canada Water Development Construction Liaison Forum Plots Al & A2 (and surrounding area) 25 May 2022

  2. Slide 2: Introductions and meeting code of conduct

    Introductions and meeting code of conduct Canada Water development Construction management Updates from contractors - Construction of Plot A2 (Mace) Overview of - Construction of Plot Al (Wates) to n i g ht ’ Ss - Canada Dock (Galldris/British Land) + Q&A presentation

  3. Slide 3: Our presenters

    Our presenters SARAH WARD Construction Neighbour Liaison Manager MICHAEL DELFS British Land lead for Canada Dock DARREN MADIGAN CAT HOLLAND DANIEL BOULTON EMMALEEN MAYELL DAVID WAKE Contractor, Wates Contractor, Wates Contractor, Mace Contractor, Mace Contractor, Galldris Construction of Plot Al Con

  4. Slide 4: Wider Canada Water development works

    Wider Canada Water development works ee pn we Pictured: Plan showing details of work site locations

  5. Slide 5: Key

    Key Canada Water Development boundary @ First phase of the development Former Dock Offices (retained) New public square in the Dock Offices courtyard New pedestrian route from Lower Road to Canada Water Dock First section of New High Street CANADA WATER CANADA DOCK

  6. Slide 6: Site layout and vehicle access

    Site layout and vehicle access * The haul road, by the former Rotherhithe Police Station, is shared between Plots Al and A2 and controlled by Alandale Group. * The entrance to the haul road is on Lower Road. Traffic marshals are located on Lower Road to ensure there is no traffic build up and to ens

  7. Slide 7: Common working practices

    Common working practices Noise, dust and vibration monitoring and reporting Standard construction working hours: * Monday - Friday: 8am - 6pm * Saturday: 8am - 2pm (no noisy works before 9am) * When work outside of standard hours is needed, this will be agreed with Southwark Council and communicated

  8. Slide 8: Plot A2

    Plot A2 eS CP wm

  9. Slide 9: Plot A2 - Current site activity

    Plot A2 - Current site activity + Piling works and first phase of bulk excavation for swimming pool area completed. + Works have begun to form swimming pool base and basement which includes waterproofing and reinforcement for the pool base as well as drainage to basement area. * The second phase of

  10. Slide 10: Plot A2 — Indicative timeline

    Plot A2 — Indicative timeline Spring 2022 Piling complete Autumn 2022 Steel frame commences Winter 2022 Basement box completes and temporary propping removed Spring 2023 Facade installation commences Summer 2023 Superstructure frame complete Winter 2023 Final tower crane dismantled and removed Sprin

  11. Slide 11: Plot A1

    Plot Al se li “ | ili, ane

  12. Slide 12: Plot A1 - Current site activity

    Plot Al - Current site activity * Piling works now completed. * Current phase of works includes capping beam formation and bulk excavation which involves removing large amounts of soil, rock and other materials from the site in preparation for starting to construct the building. + First of three tow

  13. Slide 13: Plot A1 — Indicative timeline

    Plot Al — Indicative timeline Summer 2022 b Polat ne Spring 2024 Autumn 2024 2022 Winter 2022 Winter 2023 ‘Summer 2024 Basement Residential towe Cladding installat

  14. Slide 14: Canada Dock

  15. Slide 15: Canada Dock - Site activity

    Canada Dock - Site activity * Ground condition surveys and water level monitoring within the dock are ongoing and are due to complete by mid-June. * An additional rig was delivered to site and lifted into place via crane on 24 May. Cranes will return to site to remove rigs and floating pontoon once

  16. Slide 16: Ecological mitigation

    Ecological mitigation * We are working within ecological constraints and as advised by our Ecological Clerk of Works. * \Wecontinue to upgrade existing and install new temporary bird nesting areas to compensate for the loss of existing habitat. We have harvested existing reeds for reuse within these

  17. Slide 17: Canada Dock - Key dates

    Canada Dock - Key dates Completion of ground condition surveys and water level monitoring: June 2022 Main construction works: November 2022 - April 2024 Completion of construction works: April 2024

  18. Slide 18: Contact us

    CANADAANATER Contact us Tel: 0800 470 4593 (freephone) Email: team@canadawater.co.uk Website: www.canadawater.co.uk