Inter Pipeline — Investor Presentation (November 2019)
46 slides from Inter Pipeline's investor presentation, November 2019
Slide 1: Investor Presentation November 2019
INVESTOR { PRESENTATION — a TSX | IPL NOVEMBER 2019 ® inter pipeline
Slide 2: Forward-Looking Information
FORWARD-LOOKING INFORMATION Certain information contained herein may constitute forward-looking statements that involve known and unknown risks, assumptions, uncertainties and other factors. Forward-looking statements in this presentation include, but are not limited to: (i) Inter Pipeline’s busines
Slide 3: Inter Pipeline Investment Highlights
INTER PIPELINE INVESTMENT HIGHLIGHTS ▪ Top tier energy infrastructure business that has significant growth potential ▪ Progressing $3.7 billion in active projects today ▪ Demonstrated track record of delivering large-scale projects on time and on budget ▪ Reliable operations, with stable cash flow a
Slide 4: World-Scale Energy Infrastructure
WORLD-SCALE ENERGY INFRASTRUCTURE Oil Sands NGL Conventional Bulk Liquid Transportation Processing Oil Pipelines Storage 2019 September YTD EBITDA 55% 21% 14% 10% 2.3 million b/d Over 240,000 b/d 3,900 km pipeline 37 million barrels of contracted of production network in of storage capacity capacity
Slide 5: Value Creation
VALUE CREATION ▪ Exploring sale of European Bulk Liquid Storage business ▪ Announced $100 million Phase 2 expansion of the Central Alberta pipeline system ▪ Completed $110 million oil sands connection to Canadian Natural’s Kirby North project ▪ Successfully closed $750 million subordinated hybrid no
Slide 6: Business Strategy
BUSINESS STRATEGY OWN AND OPERATE HIGH-QUALITY ENERGY INFRASTRUCTURE ASSETS EBITDA from ▪ Well-contracted to provide cash flow stability ▪ Industry-leading project execution, with exceptional 83% cost-of-service and fee-based contracts* EH&S performance Payout ratio MAINTAIN STRONG FINANCIAL POSITIO
Slide 7: EBITDA by Contract Type
EBITDA BY CONTRACT TYPE Oil Sands Transportation NGL Processing Cost-of-Service 67% ($430 million) ($169 million) 100% 8% 26% Fee-Based 16% 66% Commodity-Based 14% Conventional Oil Pipelines Bulk Liquid Storage ($112 million) ($77 million) Product Margin 3% 21% 22% 29% Total EBITDA: $788 million 57%
Slide 8: Growth Profile
GROWTH PROFILE Target Est. Capital Cost Active Projects Segment In-Service Date ($ Million) Heartland Petrochemical Complex NGL Late-2021 $3,500 CAPL Expansion Phase 1 (Stettler) Conventional Mid-2020* $82 CAPL Expansion Phase 2 (Viking Connector) Conventional Q2-2020 $100 Total ~$3,700 Announcement
Slide 9: Cash Flow Growth
CASH FLOW GROWTH FFO per share 11.8% CAGR2013-2018 $2.80 $2.65 $2.38 $2.19 $1.71 $1.57 $1.60 $1.52 $1.26 $1.27 $1.29 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 8.3% CAGR 2008-2018 FFO per share attributable to shareholders 8
Slide 10: Dividend Growth
DIVIDEND GROWTH Dividends per share 5.3% CAGR2014-2019F $1.69 $1.71 $1.63 $1.57 $1.49 $1.32 $1.18 $1.06 $0.97 $0.91 $0.85 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019F 7.3% CAGR 2009-2019F 2019F based on actual dividends to date and $0.1425 per share per month thereafter 9
Slide 11: Dividend Stability
DIVIDEND STABILITY $ Million $1,200 $1,000 $800 $600 $400 $200 $0 2013 2013 2014 2014 2015 2015 2016 2016 2017 2017 2018 2018 FFO Dividend FFO Dividend FFO Dividend FFO Dividend FFO Dividend FFO Dividend Cost-of-Service Fee-Based Commodity-Based Product Margin Dividends supported by cost-of-service
Slide 12: Heartland Petrochemical Complex
\ : HEARTLAND. PETROCHEMICAL COMPLEX TSX | IPL
Slide 13: Heartland Petrochemical Complex (HPC)
HEARTLAND PETROCHEMICAL COMPLEX (HPC) ▪ Transformational growth opportunity ✓ Capacity to consume ~22,000 b/d of propane to produce ~525 kilotonnes per annum (KTA) of polypropylene (PP) ✓ Expected to add approximately $450 to $500 million of average annual EBITDA ✓ Target 70% to 85% of processing ca
Slide 14: Polypropylene Market Fundamentals
POLYPROPYLENE MARKET FUNDAMENTALS 000 KTA ▪ Single largest polymer in the world North American Polypropylene Total demand expected to grow ✓ Used in many common goods, such as ~22% over the next five years consumer packaging, automobile parts, 12 medical equipment, currency and textiles ✓ Expected t
Slide 15: Canadian Propane Supply Advantage
CANADIAN PROPANE SUPPLY ADVANTAGE 000’s b/d ▪ Canadian propane market to remain 300 oversupplied over the long-term ✓ More than 100,000 b/d of expected 250 oversupply that will have to be exported ✓ Forecast petrochemical demand and 200 potential international LPG exports will not balance the Canadi
Slide 16: Canadian Propane Discount
CANADIAN PROPANE DISCOUNT USD per USG $0.60 Mont Belvieu to Edmonton Propane Price Differential Cochin pipeline reversal* $0.40 $0.29 $0.20 $0.14 $0.00 2008 2010 2012 2014 2016 2018 Monthly Differential Cochin In-Service Differential Cochin Reversed Differential Canadian propane discount relative to
Slide 17: North American Cost Competitiveness
NORTH AMERICAN COST COMPETITIVENESS USD per metric ton $1,750 2018 PP Price $1,500 Delivered Cash Cost* $1,250 Indicative Margin $1,000 $750 $500 $250 $0 Heartland Complex US-Based PP Facilities Alberta-produced polypropylene expected to have one of the lowest delivered cash costs to the US Midwest
Slide 18: Propane Producer Value Proposition
PROPANE PRODUCER VALUE PROPOSITION ▪ Benefits for propane producers: ✓ Offers a higher realized propane price relative to selling in the local, oversupplied market ✓ Creates ratable demand for propane ✓ Adds diversification to propane sales portfolio ▪ Commercial framework: ✓ Producer delivers propa
Slide 19: Indicative Propane Producer Uplift
INDICATIVE PROPANE PRODUCER UPLIFT Propane Value Increase Edmonton Propane Price 500% $1.25 415% 400% $1.00 300% $0.75 200% 166% $0.50 133% 100% 65% $0.25 29% 0% $0.00 2014* 2015 2016 2017 2018 Heartland Polypropylene Edmonton Propane (USD per USG) Propane producers would have realized a 110%* uplif
Slide 20: PP Buyer Value Proposition
PP BUYER VALUE PROPOSITION ▪ Benefits for PP buyers: ✓ Offers lower realized PP feedstock price relative to buying on the spot market ✓ Provides supply diversification ✓ Allows vertical integration without capital outlay ▪ Commercial framework: ✓ Counterparty pays a fixed capital fee as well as a pr
Slide 21: Indicative PP Buyer Savings
INDICATIVE PP BUYER SAVINGS Polypropylene Savings Edmonton Propane Price 30% $1.25 27% 26% 24% 22% $1.00 18% 18% $0.75 12% 10% $0.50 6% $0.25 0% $0.00 2014* 2015 2016 2017 2018 Heartland Polypropylene Edmonton Propane (USD per USG) PP buyers would have saved 20%* through the Heartland Complex Polypr
Slide 22: Project Status
PROJECT STATUS ▪ Approximately 60% of the $3.5 billion project cost de-risked ✓ Based on lump-sum contracts, firm purchase orders, and substantially completed time and materials works ▪ Well-advanced PDH project ✓ Propane-propylene splitter installed on site ✓ Over $500 million lump-sum/unit rate co
Slide 23: Operational Expertise & Readiness
OPERATIONAL EXPERTISE & READINESS ▪ Extensive NGL operating experience ✓ Full operational responsibility for the Cochrane straddle plant, as well as the Pioneer 1 & 2 offgas plants ✓ Management oversight of the Redwater Olefinic Fractionator, as well as the Empress II & V straddle plants ▪ De-riskin
Slide 24: Capital Profile & Financing Strategy
CAPITAL PROFILE & FINANCING STRATEGY $ Million Heartland Complex financing sources Total project cost of ~$3.5 billion ▪ Potential proceeds from the sale of Inter Terminals ~$1,900 ▪ Capacity available under existing $1.5 billion committed credit facility ~$900 ✓ Over $1.2 billion available as at Q3
Slide 25: Oil Sands Transportation: 55% of 2019 September YTD EBITDA
2019 SEPTEMBER YTD 55% EBITDA 24
Slide 26: Oil Sands Transportation
OIL SANDS TRANSPORTATION ▪ Three major oil sands pipeline systems AOSP IMPERIAL KEARL HUSKY SUNRISE ✓ Cold Lake, Corridor and Polaris AOC JACOS / NEXEN HANGINGSTONE HANGINGSTONE ✓ Provide bitumen blend and Polaris Pipeline CVE NARROWS LAKE diluent transportation service CVE CHRISTINA LAKE Cold Lake
Slide 27: EBITDA Stability
EBITDA STABILITY Contracted Ultimate ▪ EBITDA underpinned by long-term (000’s b/d) Product Capacity Capacity cost-of-service contracts Bitumen Cold Lake 1,255 1,900 ✓ Contracted capacity of ~2.3 million b/d Blend Bitumen ✓ 2018 EBITDA of ~$600 million, Corridor 465 1,400 Blend independent of through
Slide 28: Overbuild Strategy
OVERBUILD STRATEGY ▪ Over 2.3 million b/d of available capacity, providing SUNRISE PHASE 2 & DEBOTTLENECK long-term growth platform HORIZON ✓ Well-positioned to accommodate ASPEN PHASE 1 & 2 high return bolt-on projects MACKAY RIVER ALGAR LAKE ✓ Ability to accommodate both small Polaris Pipeline Col
Slide 29: NGL Processing: 21% of 2019 September YTD EBITDA
2019 SEPTEMBER YTD 21% EBITDA 28
Slide 30: NGL Processing
NGL PROCESSING ▪ Large-scale NGL infrastructure Pioneer I & II ✓ Three straddle plants strategically located on the TransCanada Alberta System ✓ Two offgas plants with dedicated Boreal Pipeline Redwater supply agreements Offgas Extraction ~40,000 b/d Capacity Facility ✓ Boreal pipeline with low cost
Slide 31: NGL Processing EBITDA
NGL PROCESSING EBITDA $ Million ▪ Significant EBITDA generation at $450 Cochrane and Redwater $375 ✓ Robust frac-spreads and strong volumes drove record results in 2018 $300 ✓ Commodity-based EBITDA used to fund growth and strengthen balance sheet $225 ▪ Stable cost-of-service and fee-based $150 EBI
Slide 32: Conventional Oil Pipelines: 14% of 2019 September YTD EBITDA
2019 SEPTEMBER YTD 14% EBITDA 31
Slide 33: Conventional Oil Pipelines
CONVENTIONAL OIL PIPELINES ▪ Three conventional pipeline systems ✓ Bow River, Central Alberta and Mid-Saskatchewan Bow River Pipeline ✓ 3,900 km of pipeline and over 1.3 Central Alberta Pipeline million barrels of storage capacity Mid-Saskatchewan Pipeline Viking Formation East Duvernay ✓ Service ov
Slide 34: Central Alberta Pipeline System Expansion
CENTRAL ALBERTA PIPELINE SYSTEM EXPANSION EDMONTON Phase 1: ▪ Phase 1: Stettler Station expansion Stettler Station Mid-2020 ✓ Product batching and 10,000 b/d of additional Phase 4: ($82MM) Mainline truck unloading capacity completed; two Expansion 130,000 barrel tanks under construction HARDISTY ✓ F
Slide 35: Conventional EBITDA
CONVENTIONAL EBITDA $ Million $250 5.6% CAGR 2008-2018 $200 $150 $100 $50 $0 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Cost-of-Service Fee-Based Product Margin 34
Slide 36: Bulk Liquid Storage: 10% of 2019 September YTD EBITDA
2019 SEPTEMBER YTD 10% EBITDA 35
Slide 37: Bulk Liquid Storage
BULK LIQUID STORAGE Terminal Location ▪ 23 petroleum and petrochemical storage terminals across Europe ✓ Approximately 37 million barrels of SWEDEN total storage capacity ✓ Cost-of-service and fee-based business DENMARK ✓ Average utilization rate of 84%* IRELAND ▪ Closed NuStar Europe acquisition EN
Slide 38: Financial Summary
> FINANCIAL SUMMARY Ne TSX | IPL ——_— .
Slide 39: Financial Objectives
FINANCIAL OBJECTIVES YTD Q3 Post-HPC 2019 Target Dividends Dividends underpinned cost-of-service Greater than Greater than and fee-based cash flow 100% 100% Less than Payout ratio, after sustaining capital 86% 80% Greater than FFO to recourse debt* 19% 23% Leverage Less than Recourse debt to EBITDA*
Slide 40: Credit Strength
CREDIT STRENGTH Oil Sands NGL Conventional Bulk Liquid Transportation Processing Oil Pipelines Storage ($805 million) ($888 million) ($697 million) ($203 million) 97% 84% 74% 41% 12 customers ~20 customers 100+ producers ~130 customers Remaining contract Remaining contract Typical exposure of Remain
Slide 41: Capital Structure
CAPITAL STRUCTURE $ Billion ▪ Target capital structure of 50% to 55% $8 sr. recourse debt to total capitalization ✓ Credit facility covenant of 65% $6 ▪ $1.4 billion of consolidated debt is non- recourse to IPL $4 ✓ Corridor pipeline system has its own capital structure and credit ratings ✓ Flow thr
Slide 42: EBITDA by Business Segment
EBITDA BY BUSINESS SEGMENT $ Million $1,250 $1,000 $750 $500 $250 $0 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Oil Sands Transportation NGL Processing Conventional Oil Pipelines Bulk Liquid Storage Over $500 million of incremental EBITDA expected in 2022 41
Slide 43: Corporate Sustainability
CORPORATE SUSTAINABILITY ▪ Commitment to safety ✓ Zero lost time incidents ✓ Completed 33 in-line inspections covering over 1,300 km of pipeline ✓ 99% pipeline availability rate ▪ Commitment to the environment ✓ Carbon Disclosure Project filing completed for 2018 ✓ Full compliance with environmental
Slide 44: Environmental Highlights
ENVIRONMENTAL HIGHLIGHTS ▪ Offgas facilities process waste gas from oil sands upgraders ✓ Extract a valuable liquids stream and remove ~336,000 tonnes of GHG per year ▪ PP produced at HPC is expected to have a low GHG emissions profile ✓ GHG footprint ~65% lower than the global average and ~35% lowe
Slide 45: Looking Forward
LOOKING FORWARD ▪ Over $4.2 billion of identified future potential growth opportunities ▪ Management track record of increasing shareholder value ▪ Committed to maintaining a strong balance sheet and investment grade credit rating ▪ Well-positioned to sustain dividends, with upside growth potential
Slide 46: Contact Information
CONTACT INFORMATION INTER PIPELINE LTD. SUITE 3200, 215 – 2ND STREET SW CALGARY, AB T2P 1M4 PHONE: 1 (866) 716 7473 PHONE: 1 (403) 290 6000 WEB: INTERPIPELINE.COM INVESTORRELATIONS@INTERPIPELINE.COM 45 45