  1. Slide 1: GAIL (India) Limited welcomes to Pata Petrochemical Complex

    GAIL(India)LIMITED Welcomes TO PATA PETROCHEMICAL COMPLEX

  2. Slide 2: GAIL, Pata - Location

    GAIL, PATA -LOCATION  In the district of Auraiya of Eastern UP.  110 Kms from Kanpur and ~400 Kms from N. Delhi.  ~23 Kms from NH-2  Delhi-Howrah railway line runs parallel.  Nearest natural resource: Sengar River.  Water Supply: Upper Ganga Canal Latitude:26o 38’ N Longitude: 79o 39’ E Elevat

  3. Slide 3: Portfolio

    PORTFOLIO GAIL(India) LIMITED ,PATA GAS LNG PETRO- LHC LPG CHEMICALS TRANSMISSION E&P TRANSMISSION & MARKETING BUSINESS PRODUCTION MARKET SHARE: ~ 20 %  LPG PRODUCTION: 2,71,050 TPA CAPACITY : 810 KTA POLYMER  PROPANE PRODUCTION: 106,000 TPA  C5+ LIQUID: 48,680 TPA GAIL, PATA IS THE FIRST AND ONL

  4. Slide 4: Project Implementation

    4 PROJECT IMPLEMENTATION -A peek into the past

  5. Slide 5: GAIL, Pata - Yesterday

    GAIL, PATA -YESTERDAY LAND ACQUISITION FOUNDATION  Plant area: 590 Ha.  Township area: 150 Ha. No of affected villages :  Plant area: 05 nos.  Township area: 03 nos.  No of displaced persons: ~1170 nos. Foundation stone by hon. Former PM(India) Late Sh Rajiv Gandhi On 16 September 1989 5

  6. Slide 6: Construction Phase

    CONSTRUCTION PHASE 6

  7. Slide 7: Construction Phase

    CONSTRUCTION PHASE Today’s glory is past’s reflection 7

  8. Slide 8: Project Implementation: Dedication of GAIL Pata

    PROJECT IMPLEMENTATION 8 DEDICATION OF GAIL PATA TO THE NATION BY HON’BLE PRIME MINISTER, SHRI A B VAJPAYEE ON 10 JUNE 1999.

  9. Slide 9: Project Implementation: Dedication of LPG Plant

    PROJECT IMPLEMENTATION DEDICATION OF LPG PLANT TO THE NATION BY FORMER CM(UP), SHRI RAJNATH SINGH ON 20 JUNE 2001. 9

  10. Slide 10: GAIL-Pata: Journey

    GAIL-PATA: JOURNEY Installed capacity: 260 KTA Investment: 2540 Crores LLDPE Debottlenecking 54 Cr 310 KTA capacity LPG recovery unit GCU Vth furnace&HDPE-2 355 Cr 362 Cr 410KTA After Capacity expansion: 810 KTA PC-II total investment: 8140 Cr. (Pata+Vijaipur) GCU VIth furnace 2015 GCU Debottlecking

  11. Slide 11: Unit Capacity Licensor

    11 Unit Capacity Licensor C2-C3 (GPU) MT 562800 EIL Technip (Stone & Ethylene (GCU) MT 446000 Webster) HDPE-1 MT 100000 MITSUI, JAPAN HDPE-2 MT 100000 MITSUI, JAPAN LLDPE MT 210000 NOVA CHEM Butene-1 MT 10000 AXENS

  12. Slide 12: Unit Capacity Licensor (after expansion)

    12 Unit Capacity Licensor C2-C3 (GPU) MT 1312590 EIL Ethylene (GCU-1) MT 446000 Technip (Stone & Webster) Ethylene (GCU-2) MT 450000 Technip (Stone & Webster) HDPE-1 MT 100000 MITSUI, JAPAN HDPE-2 MT 100000 MITSUI, JAPAN LLDPE-1 MT 210000 NOVA CHEM LLDPE-2 MT 400000 UNIVATION Butene-1 MT 10000 AXENS

  13. Slide 13: Plant Performance - Polymer Production

    PLANT PERFORMANCE-POLYMER PRODUCTION 700000 Polymer Production in MT Actual 600000 573873 500000 446000 441051 440155 451625 420021 420291 420344 400000 385321 353921 344168 291829 303903 311469 300000 267525 250288 200000 100000 0

  14. Slide 14: Polymer Production Plan

    Polymer Production Plan FY Target (MT) 2016-17 610000 2017-18 730000 2018-19 810000 14

  15. Slide 15: GAIL, Pata - Today

    15 GAIL, PATA-TODAY an icon for petrochemicals

  16. Slide 16: Fractions Taken Out at Pata

    FRACTIONS TAKEN OUT AT PATA COMPONENT Lean Gas to C1 HVJ Pipeline C2 C2/C3 to GCU C3 Propane C4 LPG C5 Pentane C6+ Naphtha CO2 Removed in GSU N2

  17. Slide 17: Process Configuration

    PROCESS CONFIGURATION HVJ-32.5 21 GSU/GPU CO2 LPG-I LPG MMSCMD PROPANE 11.5 PENTANE M/L LPG-II NAPHTHA COMP 13.5 C2/C3 INJECTION 2MMSCMD UPSTREAM DOWNSTREAM 12.66 MMSCMD GAS SWEETENING HDPE-1 13.5 MMSCMD UNIT (SNEA P) UNIT (MITSUI) 100,000 TPA GAS Rich Gas from FROMGAIL Vijaipur VIJAIPUR 12.9 MMSCMD

  18. Slide 18: Midstream Unit

    MIDSTREAM UNIT IOP&S STORAGE VESSELS LOADING GANTRIES(16)  RAW WATER TREATMENT  HORTON SPHERES  LPG-8 PLANT  ATMOSPHERIC TANKS  PROPANE-2  DM WATER PLANT  DOUBLE WALL ETHYLENE  PENTANE-1  CW TREATMENT PLANT  C4 MIX-2  POWER PLANT TANKS  NITROGEN & CAP  BUTENE-1  MOUNDED BULLETS  WASTE

  19. Slide 19: Inspection

    GAIL(India)LIMITED ISO 9001:2008, ISO 14001:2004, OHSAS 18001:2007 Certified INSPECTION 19

  20. Slide 20: Our Polyethylene Brands

    OUR POLYETHYLENE BRANDS 20

  21. Slide 21: Marketing Network

    MARKETING NETWORK DELHI LUCKNOW CHANDIGARH JAIPUR KOLKATA BHOPAL AHEMEDABAD HYDERABAD 11 ZONAL OFFICES MUMBAI 35 CONSIGNMENTSTOCKISTS BENGALURU CHENNAI 44 WAREHOUSES

  22. Slide 22: Awards and Accolades

    AWARDS AND ACCOLADES An award reflects our endless efforts

  23. Slide 23: Awards & Accolades

    AWARDS & ACCOLADES GAIL PATA DECLARED WINNER OF OIL INDUSTRY SAFETY AWARD IN CATEGORY " OTHER GAS PROCESSING PLANTS" FOR THE YEAR 2014- 15. CMD TROPHY RECEIVED FOR FY 15-16 FOR QC PROJECT “SYNERGY-008” BY QUALITY CONTROL LAB. TWO TEAMS RECEIVED EXCELLENT AWARD IN NATIONAL CONVENTION HELD AT RAIPUR O

  24. Slide 24: Awards & Accolades

    AWARDS & ACCOLADES THREE TEAMS WON GOLD MEDAL & THREE TEAMS WON SILVER MEDAL IN DIFFERENT CHAPTER CONVENTIONS ON QUALITY CIRCLES CONVENTIONS, CHAPTER CONVENTION FOR QUALITY CIRCLE (CCQC) -2016. GAIL PATA HDPE- I UNIT WON CMD TROPHY FOR BEST HSE PERFORMANCE FOR THE YEAR 2015-16 24

  25. Slide 25: Gailgaon

    25 GAILGAON A haven of heaven

  26. Slide 26: Township Facilities

    TOWNSHIP FACILITIES ATM SPORTS FACILITIES CHILDREN PARK LIBRARY MINI GOLF COURSE SWIMMING POOL AUDITORIUM &

  27. Slide 27: Medical Services

    MEDICAL SERVICES Full Fledged Hospital in the Township. First Aid Centre in the Plant. Compulsory Occupational Health Checkup for all employees including contract personnel every year. Mobile Health Van facility for the benefit of local population. 27

  28. Slide 28: Medical Programs

    MEDICAL PROGRAMS Occupational Health Check Up Audiometry Tests Industrial Hygiene Surveys Ergonomic Survey Canteen Hygiene Survey First Aid training Modules 28 Counseling & scientific sessions

  29. Slide 29: Safety

    SAFETY 29

  30. Slide 30: Plant Design Aspect

    PLANT DESIGN ASPECT  PLANT IS DESIGNED CONSIDERING PASSIVE & ACTIVE PROTECTION METHOD  PASSIVE SAFETY DESIGN IS INHERENT & EXISTS WHETHER RELEASE OF HC/FIRE IS THERE OR NOT  ACTIVE SAFETY DESIGN COVERS SAFETY FEATURES WHEN HC RELEASE/FIRE OCCURS

  31. Slide 31: Plant Safety Features

    PLANT SAFETY FEATURES PRIMARY AND SECONDARY EQUIPMENT & PLANT AREA ISOLATION SYSTEM SPACING & LAYOUT AS PER STANDARDS EQUIPMENT DEPRRESSURING SYSTEM ELECTRICALAREA CLASSIFICATION EQUIPMENT LIQUID PULLDOWN SYSTEM SUITABLE IMPOUNDING,COLLECTION & DRAINAGE FIRE PROTECTION SYSTEMS SUFFICIENT FIREPROOFIN

  32. Slide 32: Corporate Social Responsibility

    32 CORPORATE SOCIAL RESPONSIBILITY Saving Smiles

  33. Slide 33: Our Focus Areas for Community Initiatives

    OUR FOCUS AREAS FOR COMMUNITY INITIATIVES  Community Education & Skill Development Literacy Infrastructure Health care Environment/ Dev.&Empowe Enhancement Sanitation & rment Drinking Water 10% 15% 20% 30% 10% 15%

  34. Slide 34: CSR Related Activities (2016-17)

    CSR RELATED ACTIVITIES (2016-17) GAIL AROGYA-HEALTH CARE SERVICES THROUGH MOBILE MEDICAL VANS (5 NOS.) CATERING BASIC HEALTH SERVICES TO ABOUT 100 VILLAGES AROUND PATA PLANT, AURAIYA (UP), IA WOCKHARDT FOUNDATION. GAIL UJJWAL-PADHO AURAIYA- IMPROVING QUALITY OF BASIC EDUCATION AMONG CHILDREN BY CAPA

  35. Slide 35: CSR Related Activities (2016-17)

    CSR RELATED ACTIVITIES (2016-17) GAIL KAUSHAL-SKILL & ENTREPRENEURSHIP DEVELOPMENT ACTIVITIES FOR GENERATING SELF- EMPLOYMENT NEARBY PAP VILLAGES UNDER PROGRESS, IA IEDUP LUCKNOW. GAIL AROGYA -HIV CARE & PREVENTION THROUGH MASS AWARENESS THRU HIV TESTING/ STI TREATMENT CENTRE (KHUSHI CLINIC) FOR THE

  36. Slide 36: CSR Related Activities (2016-17)

    CSR RELATED ACTIVITIES (2016-17) GAIL HARIT -INSTALLATION OF 1265 UNIT OF SOLAR HOME LIGHT IN NEARBY VILLAGES TO IMPROVE THEIR STANDARD OF LIVING ,IA UPSICL ALLAHABAD. GAIL HARIT-CONSTRUCTION OF 62 BIO GAS UNITS FOR PROMOTING CLEAN ENERGY DRIVE IN RURAL AREA, IA UPSICL ALLAHABAD. GAIL SAKSHAM -2500

  37. Slide 37: Environment

    37 ENVIRONMENT We care since nature nurtures

  38. Slide 38: Green Belt & Water Bodies

    GREEN BELT & WATER BODIES More than 34% of total area is Green cover making it an ideal ecological habitat and promoting Biodiversity (more than 100 species of birds and other life).

  39. Slide 39: Environment Monitoring

    ENVIRONMENT MONITORING • WASTE WATER ANALYSIS • STORM WATER ANALYSIS • STACK MONITORING • AMBIENT AIR MONITORING • SENGAR RIVER U/S AND D/S MONITORING • SOLID WASTE ANALYSIS • NOISE ANALYSIS • METEREOLOGICAL PARAMETER ANALYSIS

  40. Slide 40: Green Initiatives

    GREEN INITIATIVES  Clean & Green Fuel - Natural Gas  On-line Ambient Air Monitoring System  MBR Sewage treatment plant(1 MLD)-SD project  Rain Water Harvesting in Major Buildings  Solar panels installation (5.67 MW)  Water Foot printing in FY 2013-14.  Leak Detection and Repair (LDAR) program

  41. Slide 41: Waste Water Treatment

    WASTE WATER TREATMENT  Wastewater Treatment Facilities  Treated effluent conform to prescribed standards. 41

  42. Slide 42: This Nature has an unbiased relation with everyone since it belongs to me, to

    This Nature has an unbiased relation with everyone since it belongs to me, to you and to all…

  43. Slide 43: Thank You

    THANK YOU

GAIL (India) — Corporate Update (July 2018) on 6ix