TransAlta Renewables Inc

TransAlta Renewables — Shareholder Meeting (April 2016)

32 slides from TransAlta Renewables's shareholder meeting presentation, Apr 28, 2016

  1. Slide 1: TransAlta Renewables Annual Meeting of Shareholders

    TransAlta Renewables Annual Meeting of Shareholders Thursday, April 28, 2016 1

  2. Slide 2: Welcome Remarks

    TransAlta Renewables Annual Meeting of Shareholders Welcome Remarks Allen R. Hagerman Chair of the Board 2

  3. Slide 3: Meeting agenda

    TransAlta Renewables Annual Meeting of Shareholders Financial Statements and Auditor’s Report Election of Directors Appointment of the Auditors Termination of formal business of the meeting Update from President, Brett Gellner Question period 3

  4. Slide 4: Call to Order

    TransAlta Renewables Annual Meeting of Shareholders Call to Order 4

  5. Slide 5: Annual Audited Financial Statements and Auditors' Report

    TransAlta Renewables Annual Meeting of Shareholders Annual Audited Financial Statements and Auditors’ Report Copies Available at the Back 5

  6. Slide 6: Election of Directors

    TransAlta Renewables Annual Meeting of Shareholders Election of Directors Board of Directors 6

  7. Slide 7: David W. Drinkwater

    Board of Directors David W. Drinkwater Toronto, Ontario Independent Director since 2013 7

  8. Slide 8: Brett M. Gellner

    Board of Directors Brett M. Gellner Calgary, Alberta Director since 2013 President and Designated Chief Executive Officer 8

  9. Slide 9: Cynthia Johnston

    Board of Directors Cynthia Johnston Calgary, Alberta Director since 2013 9

  10. Slide 10: Kathryn B. McQuade

    Board of Directors Kathryn B. McQuade Mesquite, Nevada Independent Director since 2013 10

  11. Slide 11: Paul H. E. Taylor

    Board of Directors Paul H. E. Taylor Victoria, British Columbia Director since 2013 11

  12. Slide 12: Allen R. Hagerman

    Board of Directors Allen R. Hagerman Calgary, Alberta Independent Director since 2013 Chair of the Board 12

  13. Slide 13: Board of Directors

    Board of Directors TransAlta renewables 13

  14. Slide 14: Appointment of Auditors

    TransAlta Renewables Annual Meeting of Shareholders Appointment of Auditors 14

  15. Slide 15: Company Update

    TransAlta Renewables Annual Meeting of Shareholders Company Update Brett Gellner President 15

  16. Slide 16: Forward Looking Statements

    Forward Looking Statements This presentation may include forward-looking statements or information (collectively referred to herein as “forward-looking statements”) within the meaning of applicable securities legislation. All forward-looking statements are based on TransAlta Renewables’ (“the Compan

  17. Slide 17: Leading Power Energy Infrastructure Company

    Leading Power Energy Infrastructure Company • Diversified asset base with 40 facilities spanning multiple regions • Highly contracted portfolio – weighted average contract life of 15 years 1 • Prudent payout ratio of 80% to 85% of Comparable CAFD • Proven track record for growth • Solid balance shee

  18. Slide 18: Snapshot

    Snapshot Enterprise Value1 $4.0 billion Market Cap.2 $3.2 billion 2015 Comparable EBITDA $261 million 2015 Comparable CAFD $178 million Dividend Yield 7.0% Expected Near-Term Dividend Growth 6% - 7% (once South Hedland is commissioned in 2017) TransAlta Corporation’s Ownership 64% ¹ Does not include

  19. Slide 19: Our Platform

    Our Platform • Highly diversified portfolio including over 2,600 MW of generating capacity North American Gas and Renewables Australian Gas Gas Fired Wind Hydro Gas Fired Gas Pipeline 506 MW 1,248 MW 112 MW 575 MW 270 KM 1 facility 18 facilities 13 facilities 7 facilities 43% interest Note: Segmente

  20. Slide 20: Diversified Asset Platform and Customer Base

    Diversified Asset Platform and Customer Base Significant Diversification by Geography, Technology and Counterparty Significant Diversification1 High Quality Counterparties Highly diversified cash flows from 40 operating sites in Canada, the US and Australia Wind Pipeline Canada U.S. Australia Hydro

  21. Slide 21: Strong Performance Since IPO

    Strong Performance Since IPO • Delivered solid financial and operational performance • Commissioned 68 MW New Richmond wind farm and acquired 144 MW Wyoming wind farm • Completed ~$2.3 billion in drop-down transactions with TransAlta • Increased public float • Increased dividend by 17%; targeting ad

  22. Slide 22: Attractive Total Shareholder Return

    Attractive Total Shareholder Return • TransAlta Renewables has delivered an attractive Total Shareholder Return to investors since the IPO in August 2013 Total Shareholder Return (CAGR%) as at March 31, 2016 17.0% 13.0% 16.6% 9.0% 12.4% 5.0% 8.6% 5.91% 1.0% -0.05% -3.0% -6.6% -7.0% 1 year 2 year Sin

  23. Slide 23: Proven Track Record For Growth

    Proven Track Record For Growth ~130% Increase in Power Generation Capacity Generation Capacity 2,500 2,000 Gas 1,500 Hydro 1,000 Wind 500 - Aug-13 2013 2014 2015 2016 2017 23

  24. Slide 24: Immediate and Future Dividend Growth

    Immediate and Future Dividend Growth Accretive Acquisitions Have Driven Significant Dividend Growth Estimated Dividend per Share Growth $1.00 $0.94 $0.88 $0.84 $0.77 $0.80 $0.75 ~6%-7% South ~5% Hedland $0.60 ~9% Three 2.7% Australian Canadian Assets Projects $0.40 Wyoming Wind $0.20 $0.00 At IPO 20

  25. Slide 25: 2016 First Quarter Performance Highlights

    2016 First Quarter Performance Highlights Significant increase in Q1 2016 performance Comparable CAFD ($M) Comparable EBITDA ($M) $90 $120 $114 $82 $80 $100 $70 $60 $80 $50 $60 $56 $55 $40 $32 $30 $40 $20 $17 $20 $10 $0 $0 Q1 2014 Q1 2015 Q1 2016 Q1 2014 Q1 2015 Q1 2016 25

  26. Slide 26: Strong Outlook for 2016

    Strong Outlook for 2016 Comparable CAFD1 ($M) Comparable EBITDA ($M) $250 $400 $200 $300 $150 $200 $100 $100 $50 $0 $0 2014 2015 2016E 2014 2015 2016E 1 Comparable Cash Available for Distribution (Comparable CAFD) refers to the amount of cash generated from operations after deducting sustaining capi

  27. Slide 27: South Hedland Power Station

    South Hedland Power Station 150 MW Combined Cycle Gas Power Station in Western Australia • Fully contracted with commissioning expected on time and on budget in mid-2017 • Expected to generate ~$80 million of EBITDA on an annualized basis 27

  28. Slide 28: Current Research Analysts' Target Prices

    Current Research Analysts’ Target Prices Research Analysts’ Share Price Targets FirstEnergy Outperform TD Buy Raymond James Outperform NBF Outperform RBC Outperform CIBC Sector Outperform Desjardins Hold $9 $10 $11 $12 $13 $14 $15 $16 Share Price (as of March 31, 2016): $12.65 28

  29. Slide 29: Medium Term Priorities

    Medium Term Priorities • Issue long-term project debt to finance South Hedland and upcoming maturities • Commission South Hedland on time, on budget • Pursue additional growth through third party acquisitions/additional drop-downs from TransAlta Corporation • Continue to deliver solid operational re

  30. Slide 30: Significant Drop-Down Inventory

    Significant Drop-Down Inventory ~1,300 MWs of Potential Drop-Down Candidates from TransAlta Corporation • ~400 MW in Alberta & Ontario including: Gas Fired • 230 MW Poplar Creek facility in AB Generation • ~150 MW from 4 facilities through TA Cogen Alberta • ~800 MW from 13 units in Alberta, Hydro r

  31. Slide 31: Investment Highlights

    Investment Highlights • Scale and diversification • High quality assets and proven technology • Long-term contracted portfolio • Attractive yield and strong balance sheet • Long term alignment with TransAlta as a sponsor and majority shareholder • Well positioned to grow 31

  32. Slide 32: Question and Answer

    Question and Answer 32

TransAlta Renewables — Shareholder Meeting (April 2016) on 6ix