Antipa Minerals Limited · ASX:AZY
Antipa Minerals — Investor Presentation (December 2022)
37 slides from Antipa Minerals's investor presentation, December 2022
Slide 1: Investor Update Presentation
INVESTOR UPDATE PRESENTATION Stand-alone gold development opportunity at 100% owned Minyari Dome Gold Project and commanding Paterson Province gold-copper exploration portfolio December 2022 | ASX : AZY
Slide 2: Disclaimer
DISCLAIMER Refer to Antipa Minerals ASX release 31 August 2022, for full Minyari Dome Project Scoping Study details. Antipa Minerals confirms that it is not aware of any new information or data that materially affects the information included in that release. All material assumptions and technical p
Slide 3: The Antipa Minerals Portfolio
THE ANTIPA MINERALS PORTFOLIO Rapid advancement of our flagship Minyari Dome Project 2.7 ATTRIBUTABLE MINERAL Moz GOLD ONLY SCOPING STUDY CONFIRMS STAND-ALONE PROJECT POTENTIAL Minyari Dome B RESOURCE A 100% Antipa 5,100 km2 COMPLEMENTARY MAJOR D OF HIGHLY PROSPECTIVE GROWTH PROJECTS A GOLD AND COPP
Slide 4: Corporate Snapshot
CORPORATE SNAPSHOT High quality register, strong strategic cornerstone investment CAPITAL STRUCTURE | ASX : AZY SHARE REGISTER4 Share price1 A$ 0.022 9.9% Shares on issue1 3,593.0 M 4.1% 3.6% Market capitalisation1 A$ 79.0 M 9.6% Cash2 A$ 12.0 M 72.8% Debt Nil EV A$ 67.0 M Newcrest IGO Board and man
Slide 5: Board and Management
BOARD AND MANAGEMENT Proven value creators Stephen Power Roger Mason Mark Rodda Peter Buck Gary Johnson Luke Watson Non-executive Chairman Managing Director Executive Director – Non-Executive Director Non-Executive Director CFO and Company Commercial and Legal Secretary Corporate lawyer with Geo
Slide 6: Minyari Dome Project
MINYARI DOME A PROJECT 100% ANTIPA Scoping Study confirms sizeable Technically and commercially robust Stand-alone gold mining and processing operation stand-alone project potential with clear and substantial upside Strategically significant location 35km from the Telfer mine and processing faci
Slide 7: Scoping Study Highlights
SCOPING STUDY HIGHLIGHTS Stand-alone gold mining and processing facility at Minyari Dome MINE SCHEDULE MINING PHYSICALS STANDARD CIL PLANT 21.4 Mt at 1.6 g/t gold 3 Mtpa throughput 90% gold recovery Initial open pit and underground mine For 7+ years initial processing life Simple non-refractory meta
Slide 8: Scoping Study Highlights: Detailed study outcomes
SCOPING STUDY HIGHLIGHTS Detailed study outcomes KEY MINYARI DOME PARAMETERS (± 35%) Ore tonnage Mt 21.4 Grade gold g/t 1.6 Contained ounces gold koz 1,090 Plant throughput Mtpa 3.0 Processing life (excluding pre-production) Years 7+ Strip ratio open pit waste:ore 5:1 LOM1 Gold production Annual Gol
Slide 9: Potential Upside Drivers
POTENTIAL UPSIDE DRIVERS Three key project value levers 1 2 3 Cu Co MINERAL MINE ADDITIONAL RESOURCE SCHEDULING PROJECT EXPANSION REVISION OPTIMISATION Extensional Mineral Resource Future exploration success to Potential copper and cobalt targets including satellites optimise processing by-product o
Slide 10: Potential Upside Drivers: Mineral Resource Extension Opportunities
POTENTIAL UPSIDE DRIVERS 1. Mineral Resource Extension Opportunities DRILL TESTING koz PHASE 1 - 13,000M OF RC AND DIAMOND CORE DRILLING COMPLETED PHASE 2 – 10,400M OF DIAMOND CORE AND AIR CORE DRILLING IN PROGRESS Minyari Down Plunge Mineralisation open down plunge Minyari Keel Zone Minyari fol
Slide 11: Minyari and Minyari North Plunge Targets
POTENTIAL UPSIDE DRIVERS 1. Mineral Resource Extension Opportunities –Minyari and Minyari North Plunge Targets Thick pipe like Minyari breccia mineralisation starting at surface and remaining open below 670 metres depth – delivers 3,300oz per vertical metre The intensity of this style of intrusi
Slide 12: Maiden Mineral Resource Opportunities
POTENTIAL UPSIDE DRIVERS 1. Maiden Mineral Resource Opportunities Minyari North 300m long coincident geophysical anomaly 500m north of Minyari with encouraging Minyari-style alteration and sulphide mineralisation including koz 28m at 0.5 g/t gold and 0.20% copper which plunges northwest the same a
Slide 13: Mine Scheduling Revision
POTENTIAL UPSIDE DRIVERS 2. Mine Scheduling Revision ktpa 3,500 5.0 4.5 3,000 4.0 2,500 3.5 g/t 3.0 2,000 2.5 IMMEDIATE 1,500 2.0 POTENTIAL TO 1,000 1.5 PUSH-BACK THE 1.0 PROCESSING OF 500 0.5 LOWER GRADE 0 - STOCKPILES Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Plant throughput Gold feed grade Silver feed grade INVES
Slide 14: Additional Project Optimisation
POTENTIAL UPSIDE DRIVERS 3. Additional Project Optimisation POTENTIAL TO UNDERTAKE MORE Cu Co DETAILED EVALUATION OF POLYMETALLIC DEVELOPMENT OPPORTUNITIES PRE-FEASIBILITY STUDY METALLURGICAL TEST-WORK Minyari Dome May 2022 Mineral Resource Estimate also contains OBJECTIVE TO IMPROVE 64,300 tonnes
Slide 15: Development Timeline
DEVELOPMENT TIMELINE Prioritising the rapid advancement of our flagship Minyari Dome Project 2022 CY23 MINYARI Q3 Q4 Q1 Q2 Q3 Q4 DOME Scoping Study RAPID ADVANCEMENT New target finalisation FOCUS 2022 Exploration Programme: Phase 1 2022 Exploration Programme: Phase 2 STUDIES + Targeted updated Miner
Slide 16: Complementary Major Growth Projects
COMPLEMENTARY MAJOR GROWTH PROJECTS B CITADEL JV (35% Antipa and 65% Rio Tinto) C WILKI FARM-IN (100% Antipa - Newcrest Mining Ltd farming in) D PATERSON FARM-IN (100% Antipa - IGO Ltd farming in)
Slide 17: Citadel JV Project (35%)
B CITADEL JV PROJECT (35%) Significant gold-copper-silver resource STRATEGIC 1,200km2 JOINT VENTURE OF PROJECT AREA WITH RIO 8,500M DRILL PROGRAMME TINTO2 FOR 20221 B 108 MT MINERAL RESOURCE WITHIN 45 OF km Au 2.4 Moz (0.85 Moz attrib.) at 0.72 g/t Cu 162 kt (56.7 kt attrib.) at 0.15% RIO’S WINU COP
Slide 18: Wilki Farm-In Project
C WILKI FARM-IN PROJECT A compelling greenfield opportunity MASSIVE ATTRACTIVE FARM-IN AGREEMENT WITH A$60M 2,200km NEWCREST 2 SPEND FOR 75% JV LAND MINING1 INTEREST HOLDING +A$6M WITHIN SPENT BY NEWCREST TO 3 km DATE OF THE 2.4 MT MINERAL RESOURCE TELFER GOLD-COPPER- SILVER MINE AND 22Mtpa Au 103.5
Slide 19: Paterson Farm-In Project
D PATERSON FARM-IN PROJECT Limited historic drilling, massive potential LARGE ATTRACTIVE FARM-IN AGREEMENT WITH A$30M 1,550km IGO 2 1 SPEND FOR 70% JV INTEREST LAND HOLDING ANTIPA FREE CARRIED TO COMPLETION OF FEASABILITY STUDY WITHIN +A$4M 22 km SPENT BY IGO TO DATE OF THE GOLD-COPPER-SILVER TELFER
Slide 20: Planned Discovery Activity Schedule
PLANNED DISCOVERY ACTIVITY SCHEDULE CY2022 H1 CY2023 Q2 Q3 Q4 Q1 Q2 Minyari Dome (AZY 100%): Drilling (diamond and reverse circulation), geophysical surveys Paterson IGO Farm-in1: Soil sampling, geophysical surveys, drilling (air core and diamond) Wilki Newcrest Farm-in1: Target identification and r
Slide 21: Emerging Tier 1 Gold and Copper Business
EMERGING TIER 1 GOLD AND COPPER BUSINESS OUTSTANDING Paterson region has been historically underexplored Prospective frontier for the discovery of multi-cycle, tier-one gold-copper LOCATION deposits PROXIMAL TO THE TELFER MINE AND HAVIERON AND In the last 6 years >16Moz of gold and >3Mt of cop
Slide 22: Contact
CONTACT Managing Director Mr Roger Mason E: roger.mason@antipaminerals.com.au Executive Director Mr Mark Rodda E: mark.rodda@antipaminerals.com.au Media Relations Mr Michael Vaughan Fivemark Partners E: michael.vaughan@fivemark.com.au T : +61 422 602 720 Corporate Office Level 2, 16 Ord Street West
Slide 23: Appendix
APPENDIX Scoping Study, Mineral Resource detail and other additional information INVESTOR PRESENTATION | 23
Slide 24: Production Projection
PRODUCTION PROJECTION At throughput rate 3 Mtpa ore Minyari Dome Project gold and silver recovered output schedule koz AVERAGE 168 koz pa 250 GOLD Peak production Overthefirstfiveyearsof mining 205 koz of gold in 200 Year 3 AVERAGE 44 koz pa 150 SILVER 100 Over the life of mine 50 MINYARI DEPOSIT 96
Slide 25: Project NPV Sensitivity Analysis
PROJECT NPV SENSITIVITY ANALYSIS Tremendous upside to bull market gold pricing IRR NPV7% 34% A$392M (pre-tax) (pre-tax) OPEX ± 10% 213 557 UNLEVERED PAYBACK 2.5 Gold price ± 10% 228 557 years (pre-tax) Recovery ± 2% (Abs) 356 429 NET CASH FLOW Discount rate ± 15% 363 424 A$672M CAPEX ± 10% 365 419 u
Slide 26: Mining Methods
MINING METHODS Contractor mining at three open pits and Minyari deposit underground Minyari deposit accounts for 96% of total gold mining Minyari Dome Project conceptual configuration production Standard truck and shovel mining at three open pits Underground mining will use Modified Sub-Level
Slide 27: Mining Schedule
MINING SCHEDULE Ore tonnage by Mineral Resource category and mining source 21.4 Mt of open pit and underground ore Minyari Dome Project Mined Ore Projection by mining method (kt) Average LOM grade of 1.6 g/t for 1.1 Moz gold 8,000 6,000 13.5 Mt ore from open pits (at a strip ratio of 5:1) and
Slide 28: Process Flowsheet and Production Rate
PROCESS FLOWSHEET AND PRODUCTION RATE 3 Mtpa Carbon-In-Leach facility currently considered optimal Gravity and Carbon-In-Leach facility (CIL) for a gold-silver Block flow diagram of CIL flowsheet case producing doré gold Processing facility was evaluated at throughput rates of 1 Mtpa, 2 Mtpa and
Slide 29: Capital Cost Estimate Summary
CAPITAL COST ESTIMATE SUMMARY Upfront capital requirement of A$275M CAPITAL COST ESTIMATE (A$M ± 35%) MAXIMISES Processing Plant (3 Mtpa CIL) 77.1 GOLD OUNCES Contingency 7.7 duringthefirstfour yearsofproduction Infrastructure - Process 33.0 EPCM 13.5 PREFERENTIAL Reagents 2.3 PROCESSING Tailings St
Slide 30: Operating Cost Estimate Summary
OPERATING COST ESTIMATE SUMMARY Contractor mining at 3 Mtpa throughput Operating costs estimated for mining, processing OPERATING COST ESTIMATE (A$/T ORE ± 35%) and administration Mining – open pit (13.5 Mt of ore) 25.3 Consultants Snowden Optiro independently Mining – underground (7.9 Mt of ore
Slide 31: JV and Farm-In Project Summary
JV AND FARM-IN PROJECT SUMMARY Citadel Joint Venture – Antipa 35% : Rio Tinto 65% (Rio earnt 65% by sole funding A$25M) ~1,200km2 Citadel JV Project just 4km from Rio Tinto’s Winu copper-gold-silver development project Existing Mineral Resource 2.4Moz gold at 0.72 g/t, 162kt copper at 0.15% and
Slide 32: Shallow Depth of Younger Cover
SHALLOW DEPTH OF YOUNGER COVER –FIRST MOVER EXPLORATION AND DEVELOPMENT ADVANTAGE ~50% OF ANTIPA TENEMENTS ARE UNDER LESS THAN 20 metres OF COVER ~80% OF ANTIPA TENEMENTS ARE UNDER LESS THAN 80 metres OF COVER INVESTOR PRESENTATION | 32
Slide 33: Citadel JV Project (35% Antipa)
CITADEL JV PROJECT (35% ANTIPA) Geology and scale suggests substantial growth and development potential Calibre deposit (shown right) Inferred Mineral Resource 92Mt at 0.72 g/t gold, 0.11% copper and 0.46 g/t silver for 2.1Moz gold, 104kt copper and 1.3Moz silver 1.7km long, up to 480m thick and
Slide 34: Havieron Gold-Copper Deposit
HAVIERON GOLD - COPPER DEPOSIT 1. The Havieron deposit is the subject of a joint venture agreement between Greatland Gold Plc and Newcrest Mining Ltd. Newcrest holds a 70% interest in Havieron earnt via total expenditure of US$65M. 2. Refer Greatland Gold Plc’s website (www.greatlandgold.com) and Lo
Slide 35: Telfer Gold-Copper-Silver Operation
TELFER GOLD – COPPER - SILVER OPERATION • Gold production gap Newcrest Mining Ltd’s (NCM) group production profile - Focus just on the orange area (i.e. Telfer+Havieron)1 Note NCM’s diminishing production from the Telfer hub (35km from Minyari) from FY241 onwards which has recently been pushed-out u
Slide 36: Mineral Resource: Minyari Dome
MINERAL RESOURCE Minyari Dome Minyari Dome Project (100%)1 Deposit Au cut-off Category Tonnes (Mt) Au grade (g/t) Cu grade (%) Ag grade (g/t) Co (%) Au (oz) Cu (t) Ag (oz) Co (t) Minyari 0.5 Au Indicated 15.00 1.17 0.19 0.54 0.04 567,000 27,800 259,600 5,930 Minyari 0.5 Au Inferred 2.70 1.12 0.12 0.
Slide 37: Mineral Resource: Advanced exploration optionality
MINERAL RESOURCE Advanced exploration optionality Citadel Project (Antipa 35% and Rio Tinto 65% JV) Deposit Au cut-off Category Tonnes (Mt) Au equiv. (g/t) Au grade (g/t) Cu grade (%) Ag grade (g/t) Au equiv. (Moz) Au (Moz) Cu (t) Ag (Moz) Calibre 0.5 Au Inferred 92 0.92 0.72 0.11 0.46 2.7 2.10 104,
Antipa Minerals — Investor Presentation (December 2022) on 6ix