Boral — Corporate Update (December 2015)
31 slides from Boral's corporate update, Dec 10, 2015
Slide 1: Boral Deer Park Operations
Build something great™ ® Boral Deer Park Operations Deer Park Quarry Environmental Review Committee 10 December 2015
Slide 2: Agenda
Build something great™ ® Agenda Deer Park Quarry Environmental Review Committee- 10 December 2015 Welcome, introductions and apologies (5.00pm- 10 mins) Previous minutes and actions (10 mins) Business reports (30 mins) • Concrete • Asphalt • Quarry Environment (20 mins) • New dust monitors (
Slide 3: Boral personnel
Build something great™ ® Boral personnel Deer Park Quarry Environmental Review Committee- 10 December 2015 Paul Hodges Quarry Manager- Deer Park Michael Suddes Operations Manager- Concrete West Amy Wells Manufacturing Operations Manager- Asphalt Luke Brown Project Sponsor- Deer Park Quarry R
Slide 4: Previous meeting minutes and actions
Build something great™ ® Previous meeting minutes and actions Erin Furmanczyk, Stakeholder Relations Advisor (Southern Region) No. Action Responsibility Due date 1 Provide information about the proposed asphalt plant upgrade when DK TBA more information becomes available 2 Undertake a quarry blast a
Slide 5: Boral Operations Reports - Concrete
Build something great™ ® Boral Deer Park Operations Boral Operations Reports - Concrete Michael Suddes, Operations Manager, Concrete West
Slide 6: Boral Operations Reports - Asphalt
Build something great™ ® Boral Deer Park Operations Boral Operations Reports - Asphalt Amy Wells, Manufacturing Operations Manager- Asphalt
Slide 7: Boral Operations Reports - Quarries
Build something great™ ® Boral Deer Park Operations Boral Operations Reports - Quarries Paul Hodges, Quarry Manager, Boral Deer Park Quarry
Slide 8: Quarry – Monitoring Locations
Build something great™ ® Quarry – Monitoring Locations Deer Park Quarry Environmental Review Committee- 10 December 2015 Dust Monitors Blast Monitors A B
Slide 9: Quarry – Ambient Air - Ash
Build something great™ ® Quarry – Ambient Air- Ash Deer Park Quarry Environmental Review Committee- 10 December 2015 Deer Park Quarry - Ambient Air - Ash 50.0 Lab technicians reported evidence 45.0 of bird droppings in the vicinity 40.0 35.0 Ash (g/m2/month) 30.0 Train station construction, Boral ea
Slide 10: Quarry – Blast Reports - Air Vibrations
Build something great™ ® Quarry – Blast Reports- Air Vibrations Deer Park Quarry Environmental Review Committee- 10 December 2015
Slide 11: Quarry – Blast Reports - Ground Vibrations
Build something great™ ® Quarry – Blast Reports- Ground Vibrations Deer Park Quarry Environmental Review Committee- 10 December 2015
Slide 12: Deer Park Quarry – Fuel Tank Upgrade
® Deer Park Quarry– Fuel Tank Upgrade For more details contact: Tate Cromie – 0466 655 612 Tate.Cromie@boral.com.au
Slide 13: House Keeping - Deer Park Quarry
® House Keeping - Deer Park Quarry For more details contact: Joe Bellofiore joe.bellofiore@boral.com.au
Slide 14: Environment
Build something great™ ® Boral Deer Park Operations Environment Dr Richard Strauch, Group Environmental Advisor Cassi Sartori, Environmental Coordinator
Slide 15: Dust Monitoring - Orisis monitors
Build something great™ ® Dust Monitoring- Orisis monitors Dr Richard Strauch, Group Environmental Advisor, Boral Corporate
Slide 16: Dust monitoring - A Typical Day
Build something great™ ® Dust monitoring- Orisis monitors Deer Park Quarry Environmental Review Committee- 10 December 2015 A Typical Day This is actually what the Orisis monitors reported for Thursday December 3 Alarms and event investigations can be based on this.
Slide 17: Dust monitoring - LabTech Adjusting Equipment
® Build something great™ Dust monitoring- Orisis monitors Deer Park Quarry Environmental Review Committee- 10 December 2015 LabTech Adjusting Equipment But this is how best to interpret and report overall, given the health standard is a 24hr average figure Basically the ‘background’
Slide 18: Weed management
Build something great™ ® Weed management Cassi Sartori, Environmental Coordinator, Boral OHS Functional Group
Slide 19: Weed Management Plan within the Northern Grassland
Build something great™ ® Weed Management Plan within the Northern Grassland Deer Park Quarry Environmental Review Committee- 10 December 2015 • Brett Lane and Associates management plan produced in 2013- 5 year plan • 3 stages
Slide 20: Serrated Tussock in the Northern Grassland May 2013
Build something great™ ® Serrated Tussock in the Northern Grassland May 2013 Deer Park Quarry Environmental Review Committee- 10 December 2015 BL&A described serrated tussock as the most widely spread species within the study area.
Slide 21: Serrated Tussock in the Northern Grassland July 2015
Build something great™ ® Serrated Tussock in the Northern Grassland July 2015 Deer Park Quarry Environmental Review Committee- 10 December 2015
Slide 22: Artichoke Thistle in the Northern Grassland May 2013
Build something great™ ® Artichoke Thistle in the Northern Grassland May 2013 Deer Park Quarry Environmental Review Committee- 10 December 2015
Slide 23: Artichoke Thistle in the Northern Grassland July 2015
Build something great™ ® Artichoke Thistle in the Northern Grassland July 2015 Deer Park Quarry Environmental Review Committee- 10 December 2015
Slide 24: Serrated Tussock in the Northern Grassland July 2015
Build something great™ ® Serrated Tussock in the Northern Grassland July 2015 Deer Park Quarry Environmental Review Committee- 10 December 2015 EC = Species 2013 (EC) 2013 Area Ha 2015 (EC) 2015 Area Ha Estimated Coverage <20% 33.5 <20% 30.4 Serrated Tussock 20 - 50% 38.5 20-50% 34 >50% 25.3 >70% 9
Slide 25: Aus Eco – Weed Management for FY16
Build something great™ ® Aus Eco – Weed Management for FY16 Deer Park Quarry Environmental Review Committee- 10 December 2015 Spring 2015 Boom spray serrated tussock, chilean and cane needle grass. Hand weed rice flower pens Summer 2015-2016 reduce fox and rabbit populations Spot spray serra
Slide 26: Aus Eco – Native Revegetation Status July 2015
Aus Eco – Native Revegetation Status July 2015 ® Deer Park Quarry Environmental Review Committee- 10 December 2015
Slide 27: Deer Park Quarry Replacement Project Update
Build something great™ ® Deer Park Quarry Replacement Project Update Luke Brown , Project Sponsor- Deer Park Quarry Replacement Project
Slide 28: Deer Park Quarry Replacement Project
Build something great™ ® Deer Park Quarry Replacement Project Luke Brown , Project Sponsor- Deer Park Quarry Replacement Project Replacement Plant Project Next Steps: Received Planning Approval 18th November from MCC Site establishment underway, target completion end 2015 Concrete foundation
Slide 29: General business and community news
Build something great™ ® Boral Deer Park Operations General business and community news Erin Furmanczyk, Stakeholder Relations Advisor (Southern Region)
Slide 30: Proposed meeting schedule 2016
Build something great™ ® Proposed meeting schedule 2016 1. Thursday 17 March, 5.00pm 2. Thursday 14 July, 5.00pm 3. Thursday 17 November, 5.00pm Dates are indicative only and are subject to change
Slide 31: Thank you for your attendance
® THANK YOU FOR YOUR ATTENDANCE Boral Deer Park contacts deerparkenquiries@boral.com.au Quarry – 9363 7850 Asphalt – 9360 4255 Concrete – 9361 2196 Erin Furmanczyk– Stakeholder Relations Advisor 03 9981 2925 or erin.furmanczyk@boral.com.au Paul Jackson – Stakeholder Relations Manager 0