  1. Slide 1: Boral Deer Park Operations

    Build something great™ ® Boral Deer Park Operations Deer Park Quarry Environmental Review Committee 10 December 2015

  2. Slide 2: Agenda

    Build something great™ ® Agenda Deer Park Quarry Environmental Review Committee- 10 December 2015  Welcome, introductions and apologies (5.00pm- 10 mins)  Previous minutes and actions (10 mins)  Business reports (30 mins) • Concrete • Asphalt • Quarry  Environment (20 mins) • New dust monitors (

  3. Slide 3: Boral personnel

    Build something great™ ® Boral personnel Deer Park Quarry Environmental Review Committee- 10 December 2015  Paul Hodges Quarry Manager- Deer Park  Michael Suddes Operations Manager- Concrete West  Amy Wells Manufacturing Operations Manager- Asphalt  Luke Brown Project Sponsor- Deer Park Quarry R

  4. Slide 4: Previous meeting minutes and actions

    Build something great™ ® Previous meeting minutes and actions Erin Furmanczyk, Stakeholder Relations Advisor (Southern Region) No. Action Responsibility Due date 1 Provide information about the proposed asphalt plant upgrade when DK TBA more information becomes available 2 Undertake a quarry blast a

  5. Slide 5: Boral Operations Reports - Concrete

    Build something great™ ® Boral Deer Park Operations Boral Operations Reports - Concrete Michael Suddes, Operations Manager, Concrete West

  6. Slide 6: Boral Operations Reports - Asphalt

    Build something great™ ® Boral Deer Park Operations Boral Operations Reports - Asphalt Amy Wells, Manufacturing Operations Manager- Asphalt

  7. Slide 7: Boral Operations Reports - Quarries

    Build something great™ ® Boral Deer Park Operations Boral Operations Reports - Quarries Paul Hodges, Quarry Manager, Boral Deer Park Quarry

  8. Slide 8: Quarry – Monitoring Locations

    Build something great™ ® Quarry – Monitoring Locations Deer Park Quarry Environmental Review Committee- 10 December 2015 Dust Monitors Blast Monitors A B

  9. Slide 9: Quarry – Ambient Air - Ash

    Build something great™ ® Quarry – Ambient Air- Ash Deer Park Quarry Environmental Review Committee- 10 December 2015 Deer Park Quarry - Ambient Air - Ash 50.0 Lab technicians reported evidence 45.0 of bird droppings in the vicinity 40.0 35.0 Ash (g/m2/month) 30.0 Train station construction, Boral ea

  10. Slide 10: Quarry – Blast Reports - Air Vibrations

    Build something great™ ® Quarry – Blast Reports- Air Vibrations Deer Park Quarry Environmental Review Committee- 10 December 2015

  11. Slide 11: Quarry – Blast Reports - Ground Vibrations

    Build something great™ ® Quarry – Blast Reports- Ground Vibrations Deer Park Quarry Environmental Review Committee- 10 December 2015

  12. Slide 12: Deer Park Quarry – Fuel Tank Upgrade

    ® Deer Park Quarry– Fuel Tank Upgrade For more details contact: Tate Cromie – 0466 655 612 Tate.Cromie@boral.com.au

  13. Slide 13: House Keeping - Deer Park Quarry

    ® House Keeping - Deer Park Quarry For more details contact: Joe Bellofiore joe.bellofiore@boral.com.au

  14. Slide 14: Environment

    Build something great™ ® Boral Deer Park Operations Environment Dr Richard Strauch, Group Environmental Advisor Cassi Sartori, Environmental Coordinator

  15. Slide 15: Dust Monitoring - Orisis monitors

    Build something great™ ® Dust Monitoring- Orisis monitors Dr Richard Strauch, Group Environmental Advisor, Boral Corporate

  16. Slide 16: Dust monitoring - A Typical Day

    Build something great™ ® Dust monitoring- Orisis monitors Deer Park Quarry Environmental Review Committee- 10 December 2015 A Typical Day This is actually what the Orisis monitors reported for Thursday December 3 Alarms and event investigations can be based on this.

  17. Slide 17: Dust monitoring - LabTech Adjusting Equipment

    ® Build something great™ Dust monitoring- Orisis monitors Deer Park Quarry Environmental Review Committee- 10 December 2015 LabTech Adjusting Equipment But this is how best to interpret and report overall, given the health standard is a 24hr average figure Basically the ‘background’

  18. Slide 18: Weed management

    Build something great™ ® Weed management Cassi Sartori, Environmental Coordinator, Boral OHS Functional Group

  19. Slide 19: Weed Management Plan within the Northern Grassland

    Build something great™ ® Weed Management Plan within the Northern Grassland Deer Park Quarry Environmental Review Committee- 10 December 2015 • Brett Lane and Associates management plan produced in 2013- 5 year plan • 3 stages

  20. Slide 20: Serrated Tussock in the Northern Grassland May 2013

    Build something great™ ® Serrated Tussock in the Northern Grassland May 2013 Deer Park Quarry Environmental Review Committee- 10 December 2015 BL&A described serrated tussock as the most widely spread species within the study area.

  21. Slide 21: Serrated Tussock in the Northern Grassland July 2015

    Build something great™ ® Serrated Tussock in the Northern Grassland July 2015 Deer Park Quarry Environmental Review Committee- 10 December 2015

  22. Slide 22: Artichoke Thistle in the Northern Grassland May 2013

    Build something great™ ® Artichoke Thistle in the Northern Grassland May 2013 Deer Park Quarry Environmental Review Committee- 10 December 2015

  23. Slide 23: Artichoke Thistle in the Northern Grassland July 2015

    Build something great™ ® Artichoke Thistle in the Northern Grassland July 2015 Deer Park Quarry Environmental Review Committee- 10 December 2015

  24. Slide 24: Serrated Tussock in the Northern Grassland July 2015

    Build something great™ ® Serrated Tussock in the Northern Grassland July 2015 Deer Park Quarry Environmental Review Committee- 10 December 2015 EC = Species 2013 (EC) 2013 Area Ha 2015 (EC) 2015 Area Ha Estimated Coverage <20% 33.5 <20% 30.4 Serrated Tussock 20 - 50% 38.5 20-50% 34 >50% 25.3 >70% 9

  25. Slide 25: Aus Eco – Weed Management for FY16

    Build something great™ ® Aus Eco – Weed Management for FY16 Deer Park Quarry Environmental Review Committee- 10 December 2015 Spring 2015  Boom spray serrated tussock, chilean and cane needle grass.  Hand weed rice flower pens Summer 2015-2016  reduce fox and rabbit populations  Spot spray serra

  26. Slide 26: Aus Eco – Native Revegetation Status July 2015

    Aus Eco – Native Revegetation Status July 2015 ® Deer Park Quarry Environmental Review Committee- 10 December 2015

  27. Slide 27: Deer Park Quarry Replacement Project Update

    Build something great™ ® Deer Park Quarry Replacement Project Update Luke Brown , Project Sponsor- Deer Park Quarry Replacement Project

  28. Slide 28: Deer Park Quarry Replacement Project

    Build something great™ ® Deer Park Quarry Replacement Project Luke Brown , Project Sponsor- Deer Park Quarry Replacement Project  Replacement Plant Project Next Steps:  Received Planning Approval 18th November from MCC  Site establishment underway, target completion end 2015  Concrete foundation

  29. Slide 29: General business and community news

    Build something great™ ® Boral Deer Park Operations General business and community news Erin Furmanczyk, Stakeholder Relations Advisor (Southern Region)

  30. Slide 30: Proposed meeting schedule 2016

    Build something great™ ® Proposed meeting schedule 2016 1. Thursday 17 March, 5.00pm 2. Thursday 14 July, 5.00pm 3. Thursday 17 November, 5.00pm Dates are indicative only and are subject to change

  31. Slide 31: Thank you for your attendance

    ® THANK YOU FOR YOUR ATTENDANCE  Boral Deer Park contacts  deerparkenquiries@boral.com.au  Quarry – 9363 7850  Asphalt – 9360 4255  Concrete – 9361 2196  Erin Furmanczyk– Stakeholder Relations Advisor 03 9981 2925 or erin.furmanczyk@boral.com.au  Paul Jackson – Stakeholder Relations Manager 0