  1. Slide 1: Boral Hall Quarry Community Meeting

    Build something great™ ® Boral Hall Quarry Community Meeting 9 May 2013

  2. Slide 2: Agenda

    Build something great™ ® Agenda Community meeting – Boral Hall Quarry 9 May 2013 Welcome and introductions Previous meeting notes, matters arising and apologies General update Environmental update Drill and Blast management Section 96 application update General business 2

  3. Slide 3: Welcome and introductions

    ® Build something great™ Welcome and introductions Community meeting – Boral Hall Quarry 9 May 2013 Boral personnel present at today’s meeting: Mark McCluskey Quarry Manager, Boral Hall Quarry Dave Hall Quarry Supervisor, Boral Hall Quarry Robert Morris Boral Hall Quarry Paul Jackson Stakeholder Rel

  4. Slide 4: Previous meeting notes & matters arising

    ® Build something great™ Previous meeting notes & matters arising Community meeting – Boral Hall Quarry 9 May 2013 Previous meeting notes Community meeting of 6 December 2012 (please refer to hard copies). REMINDER: All meeting notes and presentations can be viewed on the Boral Hall Quarry website –

  5. Slide 5: Boral Hall Quarry Operations

    Build something great™ ® Boral Hall Quarry Operations Mark McCluskey, Boral Hall Quarry Manager

  6. Slide 6: General Update

    ® Build something great™ General Update Community meeting – Boral Hall Quarry 9 May 2013 Since the last meeting… Went to Yass Valley Council on 9 Dec and were successful in our Section 96 modification application Final detailed road design is currently with RMS awaiting final approval. Production is

  7. Slide 7: Environmental Management & Performance

    Build something great™ ® Boral Hall Quarry Environmental Management & Performance Mark McCluskey, Boral Hall Quarry Manager

  8. Slide 8: Environmental Update

    ® Build something great™ Update Community meeting – Boral Hall Quarry 9 May 2013 Environmental Update Tree planting to begin on bench no 1 in the quarry – this will be final restoration on final face. Hydro–seeding tip area has also begun. Dust results at our five stations have been good, however fu

  9. Slide 9: Environmental Blast Monitoring

    Build something great™ ® Boral Hall Quarry Environmental Blast Monitoring Mark McCluskey, Boral Hall Quarry Manager

  10. Slide 10: Drill and Blast management

    ® Build something great™ Drill and Blast management Community meeting – Boral Hall Quarry 9 May 2013 Basic factors in blast design Generally we look to blast anywhere between 30000 – 60000t per blast. Select a blast hole pattern, survey the blast area & calculate the explosive usage. Geology and for

  11. Slide 11: Drill and Blast Management

    ® Build something great™ Drill and Blast Management Community meeting – Boral Hall Quarry 9 May 2013 Blast Design A shot may have anywhere between 70 -120 holes drilled into the rock. Each shot hole contains a detonator and explosive – a detonator initiates the explosive. The shot is designed so tha

  12. Slide 12: Video of Hall Quarry Blast – March 2013

    ® Build something great™ Title Community meeting – Boral Hall Quarry 9 May 2013 VIDEO OF HALL QUARRY BLAST – MARCH 2013 12

  13. Slide 13: Section Update

    Build something great™ ® Boral Hall Quarry Section 96 Update Mark McCluskey, Boral Hall Quarry Manager Paul Jackson, Stakeholder Relations Manager

  14. Slide 14: Section 96 application update

    ® Build something great™ Section 96 application update Community meeting – Boral Hall Quarry 9 May 2013 Since our last meeting: - Section 96 modification application was presented to Yass Valley Councillors at the meeting of 19 December. - The application was approved. In the months since: - Boral h

  15. Slide 15: New intersection concept

    ® Build something great™ New intersection concept Community meeting – Boral Hall Quarry 9 May 2013 15

  16. Slide 16: General business

    Build something great™ ® Boral Hall Quarry General business

  17. Slide 17: General business

    ® Build something great™ General business Community meeting – Boral Hall Quarry 9 May 2013 Items of general business. Next meeting October/November 2013 Boral Hall Quarry contacts Mark McCluskey – Quarry Manager 0401 893 436 or mark.mccluskey@boral.com.au Hall Quarry Weighbridge 6230 2755 Paul Jacks

  18. Slide 18: Thank you for your attendance

    ® THANK YOU FOR YOUR ATTENDANCE Build something great™ Boral Hall Quarry Community Meeting 9 May 2013 ®