Nordic Mining Asa · OSL:NOM

Nordic Mining Asa — Q1 2019 Earnings Presentation

25 slides from Nordic Mining Asa's earnings presentation, May 10, 2019

  1. Slide 1: Minerals for a sustainable future – Q1 2019 presentation

    Minerals for a sustainable future OAX: NOM Q1 2019 presentation Oslo, 10 May 2019

  2. Slide 2: Disclaimer

    Disclaimer This document has been used by Nordic Mining during an oral presentation. Therefore, this document is incomplete without the oral explanations, comments and supporting instruments that were submitted during the referred presentation. To the extent permitted by law, no representation or wa

  3. Slide 3: Agenda

    1. Introduction 2. Financial update 3. Engebø Rutile and Garnet 4. Keliber Oy Lithium 5. Q & A

  4. Slide 4: Highlights

    Highlights • Record group profit due to value increase in NM’s Keliber asset • All major test works completed for Engebø • Engebø DFS progressing into the final phase • Engebø garnet performs in line with premium products • Positive market outlooks

  5. Slide 5: Close to construction of two strategic assets

    Close to construction of two strategic assets Engebø Rutile and Garnet (100%) • Large resource base • Long term industrial partners • First European producer of garnet • Post tax NPV of USD 305m Keliber – Lithium hydroxide (18.5%) • First European producer • Large resource potential • Scalable produ

  6. Slide 6: Engebø Rutile and Garnet

    Engebø Rutile and Garnet Large outcropping deposit, next to tidal waters Unique mineral properties, solid market fundamentals Minimum ore haulage, effective mining concept Robust project economics, short payback period Environmental permit granted International offtake partners 6

  7. Slide 7: Agenda

    1. Introduction 2. Financial update 3. Engebø Rutile and Garnet 4. Keliber Oy Lithium 5. Q & A

  8. Slide 8: Consolidated income statement

    Consolidated income statement Q1-2019 Q1-2018 (Amounts in NOK million) Unaudited Unaudited Sales - - • Operating loss reflects the cost of Payroll and related costs (4,3) (1,9) ongoing DFS activities Depreciation and amortisation - - • Gain on investment of NOK 98m Other operating expenses (10,9) (1

  9. Slide 9: Consolidated statement of financial position

    Consolidated statement of financial position 31.03.2019 31.12.2018 (Amounts in NOK million) Unaudited Audited ASSETS Evaluation and exploration assets 25,7 25,6 • Shareholding in Keliber reclassified Property, plant & equipment 0,4 0,2 from associate to financial asset Financial assets 113,1 - Inves

  10. Slide 10: Financing plan

    Financing plan • Capital requirement to complete Engebø DFS; approx. NOK 40m • Completion of DFS represents a key milestone for de-risking of the Engebø project and will form the basis for further financing • Key options under assessment: o Divestment o Strategic investor/offtake partners o Private

  11. Slide 11: Agenda

    1. Introduction 2. Financial update 3. Engebø Rutile and Garnet 4. Keliber Oy Lithium 5. Q & A

  12. Slide 12: Project development – DFS in final phase

    Project development – DFS in final phase All major process test work completed Engineering progressing on all working areas Requests for Quotation (RFQ) ongoing Regulation plans for minesite and water supply released for public hearing Engebø garnet performance tests completed Offtake discussions pr

  13. Slide 13: Major test work completed; Product performance tests

    Major test work completed • Test work programs completed: - Bulk program - Validation program - Variability program • Flow sheet optimized with regard to rutile and garnet Product performance tests • Product tests of garnet carried out with full scale water jet cutting equipment • Engebø garnet prod

  14. Slide 14: Engineering is progressing in all working areas

    Engineering is progressing in all working areas • Process flow diagrams and P&IDs generated • 3D modelling of underground crushing chamber, service area and haul roads completed • 3D modelling of process modules commenced • Detailed specifications of equipment packages in final stage • Initial const

  15. Slide 15: Regulation plans on public hearing; Process plant site layout optimized

    Regulation plans on public hearing • The zoning plan for fresh water pipeline has been sent on hearing in two municipalities, Askvoll and Naustdal • Detailed regulation plan for the mine site has been issued for hearing in the Naustdal municipality Process plant site layout optimized • Logistics for

  16. Slide 16: Local stakeholder communication

    Local stakeholder communication • Meetings with local municipalities, political parties and politicians • Project briefings with potential local vendors • Participation at relevant regional conferences and business fora • Site visits and presentations for students • Engaging the local community in e

  17. Slide 17: DFS Progress overview

    DFS Progress overview Activities 2019 Q1 Q2 Q3 Q4 Mining studies Mining optimization schedule Process testwork Engineering Procurement/RFQs Construction execution plan Capex estimate Opex estimate Risk management / QRA Final economic analysis DFS report Today Cost Economic Test work Engineering RFQs

  18. Slide 18: Offtake discussions progressing

    Offtake discussions progressing Rutile • Heads of Agreement for rutile offtake and financing Heads of • Comprising offtake for the majority of the rutile production agreement with • Intention to participate with a substantial portion of the Japanese trading construction financing house • Engebø ruti

  19. Slide 19: Rutile prices forecasted to increase with growing demand

    Rutile prices forecasted to increase with growing demand Global rutile demand has outpaced supply….. …..driving rutile prices up US$ 1,118/tonne FOB (Real 2018$) 19

  20. Slide 20: Nearing construction and production

    Nearing construction and production 20

  21. Slide 21: Agenda

    1. Introduction 2. Financial update 3. Engebø Rutile and Garnet 4. Keliber Oy Lithium 5. Q & A

  22. Slide 22: First producer of battery-grade lithium hydroxide in Europe

    First producer of battery-grade lithium hydroxide in Europe Lithium-ion gigafactories in Europe Yearly demand from European gigafactories 8GWh in 2020 By 2023 2 GWh 32 GWh in 2023 4 GWh Gigafactories are 1 Gwh Planned to triple capacity demands expected to 0.8 kt of demand 73 kt LCE lithium per year

  23. Slide 23: Solid project economics in updated DFS

    Solid project economics in updated DFS Increased NPV by switching output to hydroxide Keliber ownership as of April 2019 • Aiming to be the first European company to produce high-purity lithium hydroxide from its own ore • Six deposits in one of the most significant lithium bearing areas in Europe •

  24. Slide 24: Agenda

    1. Introduction 2. Financial update 3. Engebø Rutile and Garnet 4. Keliber Oy Lithium 5. Q & A

  25. Slide 25: Safety – Environment - Innovation

    Safety – Environment - Innovation www.nordicmining.com 2 5