    Key Petroleum Ltd 13 December 2012 The Manager Australian Securities Exchange Company Announcements Office Level 4/20 Bridge Street SYDNEY NSW 2000 Dear Sir RE: INVESTOR UPDATE PRESENTION We attach herewith an Investor Update Presentation regarding Key Petroleum Limited’s current activities. Regards

  2. Slide 2: Investor Update 2012 Broker Brief

    INVESTOR UPDATE 2012 Broker Brief 13 December 2012

  3. Slide 3: Disclaimer

    Disclaimer The information in this presentation is an overview and does not contain all information necessary for investment decisions. In making investment decisions, investors should rely on their own examination of Key Petroleum Ltd and consult with their own legal, tax, business and/or financial

  4. Slide 4: Board of Directors

    Board of Directors • Mr Kane Marshall – Petroleum Engineer BSc (Geology), BCom (Corp. Finance) & MPetEng Appointed Managing Director in April 2012 with over 10 years experience in exploration, production and development internationally and in Australia • Mr Ian Paton – Geophysicist BSc (Geophysics),

  5. Slide 5: Strategic Direction

    Strategic Direction • Primary re-focus to Australian exploration and development opportunities • The Company has now exited from all minority small impact international interests • New board in place with track record of success as at July 2012 to execute new strategic direction • Company continues

  6. Slide 6: Exploration Interests

    Exploration Interests • Canning Basin - Conventional and Unconventional:  EP 448 - 70.00%  EP 438 - 76.00%  EP 104 - 16.44%  R1 - 16.44%  Production License L15 (West Kora Oil Field) - 49.00% • North Perth Basin Conventional Oil:  EP 437 - 50.00%  After completion of farm out wholly owned su

  7. Slide 7: Canning Basin Interests

    Canning Basin Interes T 126°00°E Test Lower Anderson Stokes Bay -1 ¢ 4 | Westen Ce RS il MB, T 122°00"E [1800's "ial Deepen Lawford-1 ® Evaluate } 100 kilometres shale Fotartial ‘Areas to be Evaluated for Shale Gas by LE key Permits Conoco Phillips Tar Loos [__] Buru Permits __<_————— | k [1 tien st

  8. Slide 8: Canning Basin Interests (cont'd)

    Canning Basin Interests (cont’d) • Interests in four million gross acres encompassing conventional and unconventional targets • Liquids focused exploration • Key operates one block (EP 448) and currently operates Cyrene-1 on behalf of the EP 438 Joint Venture • Cyrene-1:  Post farmin Key interest g

  9. Slide 9: Key Petroleum Limited Exploration Programme

    Key Petroleum Limited Exploration Programme Cyrene-1 commitment well targeting both conventional and unconventional plays over a 4 way dip anticlinal structure

  10. Slide 10: Key Petroleum Limited Exploration Programme (cont'd)

    Key Petroleum Limited Exploration Programme (cont’d) CYRENE -1, ONSHORE CANNING BASIN, WA • Cyrene-1 farmed out to Buru Energy to earn 75% (Mitsubishi and Buru) in EP 438 by spending $3 million including a well • Key Petroleum (70%) and Indigo Oil Pty Ltd (20%) are carried through the $3 million spe

  11. Slide 11: Cyrene-1 Geographic Location

    Cyrene-1 Geographic Location LOCATION • 100km South of Broome, 1.5km from Great Northern Highway • The Cyrene structure consists of a four way dip closed anticline with estimated potential recoverable oil 5MBO • Is adjacent to the Hedonia-1 well drilled by Gulf in the early 1980s, which had strong o

  12. Slide 12: Cyrene-1 Location

    Cyrene-1 Location LOCATION • Located on a working cattle station  Gates to be kept closed at all times (cattle)  Speed limit in place on access track  Rig location marked from the main highway

  13. Slide 13: Cyrene-1 Wellsite Layout

    Cyrene-1 Wellsite Layout Store Tools Fuel Tank Tank 1 Tank 2 Tank 3 F Sump l a 20m x 15m r e L i n e DCA Rig 7 Layout

  14. Slide 14: Cyrene-1 Wellsite Update

    Cyrene-1 Wellsite Update WELLSITE ACTIVITIES • All site works completed and drilling to commence with all DCA Equipment on site • Pre-drilling start up meeting conducted on 11 December 2012 • Surface hole section to be drilled before Christmas then operations suspended over Christmas break. Will re-

  15. Slide 15: Cyrene-1 Wellsite Update (cont'd)

    Cyrene-1 Wellsite Update (cont’d) OPERATION ACTIVITIES UPDATE • Planned surface hole to a depth of 175m will be drilled followed by the running and cementing of the 9 5/8” surface casing • The BOP Stack will be nippled up and operations suspended prior to drilling to the primary target in January. •

  16. Slide 16: Cyrene-1 Wellsite Activities

    Cyrene-1 Wellsite Activities Earthworks and necessary civil works for the rig and camp were completed in October 2012

  17. Slide 17: Cyrene-1 Wellsite Activities (cont'd)

    Cyrene-1 Wellsite Activities (cont’d) Wellhead and rig equipment has been offloaded on location as well as surface casing and drill pipe

  18. Slide 18: Cyrene-1 Wellsite Activities (cont'd)

    Cyrene-1 Wellsite Activities (cont’d) The drilling camp has been delivered to site and has been setup to house up to 30 personnel.

  19. Slide 19: Cyrene-1 Wellsite Activities (cont'd)

    Cyrene-1 Wellsite Activities (cont’d) A pre-drill start up meeting was conducted on 11 December 2012 with DCA Manager Trevor Iley and Key Petroleum Managing Director Kane Marshall amongst other important personnel.

  20. Slide 20: Canning Basin Conventional & Unconventional Upside Potential

    Canning Basin Conventional & Unconventional Upside Potential • Athos 2D seismic survey has identified other conventional and unconventional structures in the EP 438 permit • Core of Goldwyer shale will assist in understanding of unconventional potential of Key’s EP 448 permit (Key 70%) where Key is

  21. Slide 21: Canning Basin Conventional & Unconventional Upside Potential (cont'd)

    Canning Basin Conventional & Unconventional Upside Potential (cont’d) • Currently seeking farmin partner for Calam ia-1 Juno-1 Munda-1 Vela-1 Darriwell-1 EP448 to drill a well in 2014 Canning Munro-1 Basin dry season and commencing Kem p Field-1 heritage and environmental approvals EP-448 for geoche

  22. Slide 22: North Perth Basin Conventional & Unconventional Potential

    North Perth Basin Conventional & Unconventional Potential • Key Petroleum has a 50% interest in EP 437 • The Key technical team has identified two distinct play types:  Unconventional carbonaceous shale gas potential of the Cattamarra Coal Formation  Conventional Triassic oil potential contained w

  23. Slide 23: North Perth Basin Conventional & Unconventional Potential (cont'd)

    North Perth Basin Conventional & Unconventional Potential (cont’d) • Looking to farm out EP437 or equity swap into other basin acreage that team is currently evaluating • EP 437 Commitment Waugh-1 is planned primarily to conventional oil play:  Open hole drill stem test planned if good oil shows ar

  24. Slide 24: North Perth Basin Conventional & Unconventional Potential (cont'd)

    North Perth Basin Conventional & Unconventional Potential (cont’d)

  25. Slide 25: Corporate Position

    Corporate Position • Key Petroleum listed in 2007 • Market Capitalisation as at 13 December 1 Year Daily Share Price Movement 2012 is ~ $13.5 million • Cash ~ $4.4 million • No contingent liabilities Appointment of new • Capital Structure 450,509,417 shares Board • Top 20 controlling ~ 33.4% • New b

  26. Slide 26: Key Petroleum Limited

    hey Petroleum Limited