    Exhibit 99.1 Great Plains Energy Investor Presentation on 2008 Rate Case Filings September 9, 2008

  2. Slide 2: Forward-looking statements

    Slide 2: Forward-looking statements

    Statements made in this presentation that are not based on historical facts are forward-looking, may involve risks and uncertainties, and are intended to be as of the date when made. Forward-looking statements include, but are not limited to, the outcome of regulatory proceedings, cost estimates of

  3. Slide 3: Investor Presentation on 2008 Rate Case Filings - Terry Bassham, CFO

    Slide 3: Investor Presentation on 2008 Rate Case Filings - Terry Bassham, CFO

    Great Plains Energy Investor Presentation on 2008 Rate Case Filings September 9, 2008 Terry Bassham, CFO Executive Vice President Finance & Strategic Development

  4. Slide 4: Missouri and Kansas Rates Below National Average

    Slide 4: Missouri and Kansas Rates Below National Average

    Business Week July 24, 2008 Missouri and Kansas Rates Below National Average

  5. Slide 5: Recent Rate Case Outcomes

    Slide 5: Recent Rate Case Outcomes

    • 2006 rate cases for KCP&L included 100 MW of new wind generation in rate base • KCP&L 2007 cases included La Cygne Unit 1 SCR in rate base • KCP&L reached settlements in Kansas in both 2006 and 2007 > Energy cost adjustment approved in 2007 case > Energy efficiency rider approved in 2007 case • MP

  6. Slide 6: Summary of Rate Cases

    Slide 6: Summary of Rate Cases

    • Requested ROE reasonable based on extensive cost of capital analysis • Capital structure based on Great Plains Energy consolidated capital structure > Excludes short-term debt > Per the Aquila transaction approval, Kansas filing excludes Aquila cap structure impact and synergies Summary of Rate Ca

  7. Slide 7: Requested Capital Structure

    Slide 7: Requested Capital Structure

    Requested Capital Structure - Missouri Requested Capital Structure - Kansas Note *1: Cost of debt varies by case as follows: KCPL MO- 6.32%, GMO MPS- 6.851%, GMO L&P (electric and steam)- 7.634% Requested Capital Structure

  8. Slide 8: Rate Base Growth

    Slide 8: Rate Base Growth

    $1.5 KCP&L GMO $2.8 KCP&L $1.0 $4.3 $2.4 $1.1 $2.3 Rate Cases Filed 8/5/2008 KCP&L Historical Rate Base Aquila (KCP&L GMO) Historical Rate Base Rates Effective 1/1/2007 Rates Effective 1/1/2008 Rates Effective 5/31/2007 Rates Effective 3/1/2006 Projected Combined Rate Base March 31, 2009 (in billion

  9. Slide 9: Comprehensive Energy Plan

    Slide 9: Comprehensive Energy Plan

    Spearville Wind Energy Facility ü 100MW completed on schedule and under budget LaCygne ü Phase 1: Unit 1 SCR - Completed on schedule, under budget, and performing per specification • Phase 2: Unit 1 - bag house and scrubber environmental upgrades: > Project Definition Report completed in Q3 2007 > E

  10. Slide 10: KCP&L (KS) Rate Case

    Slide 10: KCP&L (KS) Rate Case

    70% 30% CEP Breakdown • Rate increase of 17.5% or $71.6 million based on test year base revenues of approximately $409 million (excluding fuel expense recovered through the energy cost adjustment mechanism) • Utilizes calendar 2007 test year with April 30, 2009 true-up of plant; rates effective July

  11. Slide 11: KCP&L (MO) Rate Case

    Slide 11: KCP&L (MO) Rate Case

    66% 34% CEP Breakdown • Rate increase of 17.5% or $101.5 million based on test year base revenues of approximately $580 million • Utilizes calendar 2007 test year, with update based on October 31, 2008 financials and true-up as of April 30, 2009 • Synergies from Aquila transaction begin to flow to c

  12. Slide 12: KCP&L GMO (MPS) Rate Case

    Slide 12: KCP&L GMO (MPS) Rate Case

    • The amount of the GMO (MPS) rate increase is 14.4% or $66.0 million based on test year revenue of approximately $460 million • Continuation of fuel adjustment clause Docket number ER-2009-0090 KCP&L GMO (MPS) Rate Case

  13. Slide 13: KCP&L GMO (L&P Electric) Rate Case

    Slide 13: KCP&L GMO (L&P Electric) Rate Case

    • 13.6% rate increase or $17.1 million based on test year revenues of approximately $125 million • Continuation of fuel adjustment clause Docket number ER-2009-0090 KCP&L GMO (L&P Electric) Rate Case

  14. Slide 14: KCP&L GMO (L&P Steam) Rate Case

    Slide 14: KCP&L GMO (L&P Steam) Rate Case

    • Requested rate increase of 7.7% or $1.3 million based on test year base revenue of approximately $17 million • Requesting to continue the Quarterly Cost Adjustment (QCA) for fuel, but proposing to change the base amounts included in the tariff and to modify the recovery adjustment to reflect 100%

  15. Slide 15: Projected Missouri Regulatory Timeline

    Slide 15: Projected Missouri Regulatory Timeline

    Applications filed with MPSC Sept. 5, 2008 Staff conducts audit of entire operations Now - - March 2009 Update of revenue requirement model based on Oct. 31, 2008. Submitted approx. Jan. 1, 2009 Staff and interveners file March 2009 Rebuttal testimony March 2009 Pre-hearing conference April 2009 Tru

  16. Slide 16: Investor Presentation on 2008 Rate Case Filings

    Slide 16: Investor Presentation on 2008 Rate Case Filings

    Great Plains Energy Investor Presentation on 2008 Rate Case Filings September 9, 2008

Source: SEC EDGAR · 8-K filed Sep 9, 2008

More decks from Great Plains Energy Incorporated