Guanajuato Silver Company Ltd. · TSXV:GSVR

Guanajuato Silver — Investor Presentation (April 2025)

26 slides from Guanajuato Silver's investor presentation, Apr 2, 2025

  1. Slide 1: Mexico's Fastest-Growing Silver Producer

    Mexico´s Fastest-Growing Silver Producer : GSVR : GSVRF April 2025

  2. Slide 2: 2024 Silver Demand

    2024 Silver Demand Solar park construction will continue to drive demand growth. Each new gigawatt of installed solar requires ~ 500,000 silver ounces. 19% Solar Industrial 58.3% Bullion 17.4% Jewelry 17.3% Silverware 4.8% Photography 2.1% Source: World Silver Survey 2024 – The Silver Institute 2

  3. Slide 3: Silver Supply vs. Demand

    Silver Supply vs. Demand Global demand will exceed supply in 2024 for a fourth consecutive year.* * World Silver Survey 2024 – The Silver Institute. 3

  4. Slide 4: Most silver is produced as by-product

    Most silver is produced as by-product Therefore: Higher silver prices may not lead to increased supply. Primary Gold 16% Silver Only 26% Silver Production by Source Copper 25% Metal Lead & Zinc Other 32% 1% * World Silver Survey 2024 – The Silver Institute. 4

  5. Slide 5: Mexico - the world's top silver producer

    Mexico - the world’s top silver producer The country continues to expand its dominant share of the silver market. 24% 14% Mexico 12% Peru China 119Moz 200Moz 107Moz 5% 5% Chile Poland 42Moz 42Moz Source: Statista.com / Kitco.com 2023 Bullion 5

  6. Slide 6: Mexico's Fastest-Growing Silver Company

    Mexico’s Fastest-Growing Silver Company Currently Six Mining Production Areas. Purchased Acquired three Restarted the Added production Added production Cubo Mine. additional mines. Cata mill. from Horcon. from Pinguico. 6

  7. Slide 7: Optimizing Mine Production

    Optimizing Mine Production Successfully advancing the ramp-up across all assets. Silver equivalents are calculated using 81.05:1 (Ag/Au), 0.03:1 (Ag/Pb) and 0.05:1 (Ag/Zn) ratio for Q2 2024; an 88.72:1 (Ag/Au), 0.04:1 (Ag/Pb) and 0.05:1 (Ag/Zn) ratio for Q1 2024; an 85.10:1 (Ag/Au), 0.04:1 (Ag/Pb);

  8. Slide 8: Guanajuato

    Guanajuato Mexico’s premier mining community. 8

  9. Slide 9: Consolidating the Guanajuato Mining Area

    Consolidating the Guanajuato Mining Area Employing 100% Mexican mining expertise. 9

  10. Slide 10: The El Cubo Mines Complex

    The El Cubo Mines Complex The centerpiece of our hub & spoke mining strategy. 45,000 tonnes/month capacity 10

  11. Slide 11: El Cubo's Villalpando Vein

    El Cubo’s Villalpando Vein Longitudinal Section of the Villalpando Vein Showing AgEq g/t. Isopach presentation Mineral Resources Estimate (effective date August 1, 2024) Tonnes Ag(g/t) Ag(oz) Au(g/t) Au(oz) AgEq(g/t) AgEq(oz) Total Indicated 429Kt 144.1 2.0M 1.79 25K 283.9 3.9M Total Inferred 3,711K

  12. Slide 12: El Cubo Mill

    El Cubo Mill Clean. Dry. Organized. 12

  13. Slide 13: Valenciana Mines Complex

    Valenciana Mines Complex Cata Mill – 36,000 tonnes/month capacity. 13

  14. Slide 14: Valenciana Mines Complex

    Valenciana Mines Complex One of the most productive silver mines in Mexico’s 450-year mining history. Mineral Resources Tonnes Ag(g/t) Ag(oz) Au(g/t) Au(oz) AgEq (g/t) AgEq(oz) AuEq (g/t) AuEq(oz) Total Measured 166,262 255 1,362,426 1.81 9,681 409 2,185,272 4.8 25,709 Total Indicated 85,404 240 658

  15. Slide 15: San Ignacio

    San Ignacio Mineralized material for processing at the Cata mill. Primary Access Portal 15

  16. Slide 16: San Ignacio – Melladito Vein

    San Ignacio – Melladito Vein Longitudinal Section of the Melladito Vein Showing Ag g/t. Isopach presentation Mineral Resources Tonnes Ag(g/t) Au(g/t) AgEq (g/t) AgEq(oz) Total Measured 171,000 105 2.16 287 1.57M Total Indicated 619,000 128 2.08 Primary 304 Access Portal 6.05M Total M&I 790,000 123 2

  17. Slide 17: Topia Processing Plant

    Topia Processing Plant 7,500 tonnes/month capacity flotation facility. 17

  18. Slide 18: Topia – Topographical View

    Topia – Topographical View Historical Resource Block Model. Mineral Resources Tonnes Ag(g/t) Au(g/t) Pb (%) Zn (%) Total Measured 176,000 630 1.92 4.63 4.80 Total Indicated 155,800 587 1.75 4.15 4.16 Total M&I 331,800 609 1.84 4.40 4.50 Total Inferred 274,600 592 1.44 3.35 3.63 Source: Apex Geoscien

  19. Slide 19: Shares Issued & Outstanding

    Shares Issued & Outstanding One-Year Share Performance. Common Shares (Pro forma) 472 M Major Shareholders Warrants 157 M Options & RSUs 26 M Fully Diluted 655 M Market Cap C$80 M Myrmikan Capital 19

  20. Slide 20: The GSilver Leadership Team

    The GSilver Leadership Team Directors James Anderson, Chairman & CEO Richard Silas, Director & VP Corporate Dev. 20+ years of capital market experience as a retail 20+ years of experience in corporate governance, broker and investment banker and manager in the regulatory compliance, and the administ

  21. Slide 21: Extensive social outreach programs

    Extensive social outreach programs Social license to operate built on commitment to improving local communities. Guanajuato Silver proudly provides: • Clean water services provided to several local communities • Established a medical clinic and permanent comprehensive health campaigns. • Committed t

  22. Slide 22: Total Resources

    Total Resources* El Cubo Mines Complex & Pinguico Total Measured & Indicated: 3.9M AgEq ounces (429kt grading 283.9g/t AgEq) Total Inferred: 35.6M ounces (3,711kt grading 298.5g/t AgEq) Valenciana Mines Complex(i)(ii) Total Measured & Indicated: 3.2M AgEq ounces (251,666 tonnes grading 400g/t AgEq)

  23. Slide 23: El Cubo resource source notes

    EL Cubo Source: For additional details refer to the technical report dated January 15, 2025 (effective date August 1, 2024) titled “NI 43-101 Technical Report On The El Cubo And El Pinguico Silver Gold Complex, Guanajuato, Mexico” available on SEDAR+ Economic assumptions used include US$25/oz Ag, US

  24. Slide 24: DISCLAIMER 1/2

    DISCLAIMER 1/2 Forward-looking information This document contains certain forward-looking statements and information, which relate to future events or future performance including, but not limited to, statements regarding the industrial case for silver and future demand for silver; that the Company

  25. Slide 25: DISCLAIMER 2/2

    DISCLAIMER 2/2 Valenciana Disclosure The disclosure on this slide is from the technical report dated March 7, 2024 (effective date December 31, 2023) titled “Technical Report on the Valenciana Mine Complex, Guanajuato, Mexico” available on SEDAR+ (the “VMC Report”). On February 28, 2022, Great Panth

  26. Slide 26: Contact

    Contact JJ Jennex Director of Communications (604) 723 1433 jjj@gsilver.com Suite 578 – 999 Canada Place, Vancouver, British Columbia, V6C 3E1 : GSVR : GSVR