First Quantum Minerals Ltd. · TSX:FM

First Quantum Minerals — Merger or Acquisition (January 2013)

94 slides from First Quantum Minerals's merger presentation, Jan 29, 2013

  1. Slide 1: An Opportunity to Create a New Leader in Global Copper

    An Opportunity to Create a New Leader in Global Copper A Combination of First Quantum and Inmet January 2013 Global Diversified TSX: FM; LSE: FQM

  2. Slide 2: Cautionary Statement

    Cautionary Statement Certain statements and information contained in this presentation, including all statements that are not historical facts, contain forward-looking statements and forward-looking information within the meaning of applicable securities laws. Such forward-looking statements or info

  3. Slide 3: A Significant Premium Today with Considerable Upside in the Future

    A Significant Premium Today with Considerable Upside in the Future  C$72.00 per Inmet share, implying a total equity purchase consideration of approximately C$5.1 billion1  Each Inmet shareholder will have the option to elect to receive consideration per Inmet share of: – C$72.00 in cash, or – 3.2

  4. Slide 4: A Compelling Combination

    A Compelling Combination & c™ INERALS LTD.

  5. Slide 5: A Vision to Create a Global Copper Leader

    A Vision to Create a Global Copper Leader  The combination of First Quantum and Inmet will be the largest pure copper player in the sector, with a portfolio of operating and development assets across four continents  First Quantum and Inmet are complementary and bringing together the best talents

  6. Slide 6: On the Cusp of a Substantial Re-Rating

    On the Cusp of a Substantial Re-Rating Large-Cap Copper Producers P / NAV1 Mid-Cap Copper Producers Southern Copper Antofagasta Pro-forma First Quantum3 PanAust Oz Minerals Freeport4 Lundin Teck First Quantum Hudbay Copper Mountain Inmet2 Taseko Capstone Market Capitalization US$ Bn1 Source: Capital

  7. Slide 7: First Quantum Has Delivered and Continues to Deliver

    First Quantum Has Delivered and Continues to Deliver 7

  8. Slide 8: We Build Projects Efficiently and Well Below Industry Norms

    We Build Projects Efficiently and Well Below Industry Norms Capital Intensity (US$ / t) Cobre Panama (Inmet) Galeno (Minmetals) Las Bambas (Xstrata) Tampakan (Xstrata) Toromocho (Chinalco) Potential for Sierra Gorda (KGHM) significant capital cost savings by adopting Ministro Mina Hales (Codelco) Fi

  9. Slide 9: We Deliver Value to Shareholders

    We Deliver Value to Shareholders Total Annualized Shareholder Return1 Jan-2000 – 23-Nov-2012 First Quantum 35% Southern Copper 31% Antofagasta 29% Inmet 27% BHP 18% Teck 15% Freeport 13% Rio Tinto 10% 2 Xstrata 8% 3 Norilsk 7% Anglo American 6% 4 Kazakhmys 5% Source: S&P Capital IQ (1) Based on loca

  10. Slide 10: And Specifically Deliver On Each Project We Take On

    And Specifically Deliver On Each Project We Take On US$ Bn 99% 4.0 3.8 3.5 3.0 375% 2.5 2.5 150% 2.0 1.9 1.8 1.5 67% 115% 26% 1.0 1.0 0.9 0.7 0.7 0.7 0.6 0.5 0.5 0.3 ‐‐ Kansanshi Guelb Moghrein Kevitsa1 Trident Ravensthorpe Haquira3 2001 2004 2008 (Sentinel / Enterprise)2 2010 2010 2010 Cost plus Ca

  11. Slide 11: And Exceed Expectations

    And Exceed Expectations Delivered Exceeded Project Announced Target Parameter Promised Delivered Target? Expectations? 244,979 tonnes of copper1   Kansanshi February Peak Production 130,000 tonnes of 2004 copper   Peak Production 35,000 ounces of gold 112,286 ounces of gold  Commissioning Late

  12. Slide 12: First Quantum and Inmet Together Can Deliver Cobre Panama

    First Quantum and Inmet Together Can Deliver Cobre Panama 12

  13. Slide 13: First Quantum's Project Philosophy

    First Quantum's Project Philosophy Core First Quantum Criteria Core First Quantum Attributes • Set ambitious targets for • Industry leading performance (e.g. schedule, cost and performance capital cost per tonne of output) • Finished project must perform to • Strong track record expectation • Our pr

  14. Slide 14: Traditional Project

    Traditional Project Owner EPCM Engineer 14

  15. Slide 15: First Quantum Target Project Model

    First Quantum Target Project Model Engineering & Design By FQM 15

  16. Slide 16: Typical First Quantum Project

    Typical First Quantum Project Concrete Piping 8% 7% Earthworks E& I 5% 10% Construction Management 4% Transport & Logistics 8% Pre-commissioning & Commissioning 1% Contracts 2% Engineering & Design 5% Procurement 3% Structure/Mechanical/Plate 47% 16

  17. Slide 17: Our Core Project Development Criteria: Finished Project Must Perform

    Our Core Project Development Criteria  FINISHED PROJECT MUST PERFORM TO EXPECTATION Kevitsa – achieving throughput above design Ravensthorpe – steady state and reliable operation 17

  18. Slide 18: Our Core Project Development Criteria: Adherence to Time Schedule

    Our Core Project Development Criteria  ADHERENCE TO TIME SCHEDULE  Kevitsa First Quantum news release Nov 30, 2009 : “Commercial production target mid 2012” Actual achievement August 2012  Ravensthorpe First Quantum news release February 10, 2010 : “Approx. 18 months construction and ramp up” (i.

  19. Slide 19: Our Core Project Development Criteria: Adherence to Capital Cost Budget

    Our Core Project Development Criteria  ADHERENCE TO CAPITAL COST BUDGET Since 2003 Over $2.3B of projects delivered within 6% of capex budget Different countries, different technologies, different contracting requirements, different conditions 19

  20. Slide 20: Cost overrun is common in infrastructure projects

    Others? “Cost overrun is common in infrastructure, building and technology projects. One of the most comprehensive studies of cost overrun that exists found that 9 out of 10 projects had overrun; overruns of 50 to 100 percent were common; overrun was found in each of 20 nations and five continents c

  21. Slide 21: First Quantum Key Project Staff Have Worked in Latin America and Globally

    First Quantum Key Project Staff Have Worked in Latin America and Globally Latin America Chile Africa Zambia Europe France Argentina Mauritania Spain Peru DRC Finland Zimbabwe United Kingdom Brazil Ghana Germany Mexico Namibia Norway Botswana Italy Australasia Australia Mozambique Bulgaria New Zealan

  22. Slide 22: Country, Logistical and Technical Challenges

    Country, Logistical and Technical Challenges January 24 News Release: “First Quantum has built mines around the world, applying its development expertise to some of the industry’s most challenging projects, in the hottest and coldest, driest and wettest climates, spanning sophisticated first-world l

  23. Slide 23: The Diverse Environment in Which We Operate

    The Diverse Environment in Which We Operate 23

  24. Slide 24: The Diverse Environment in Which We Operate

    The Diverse Environment in Which We Operate 24

  25. Slide 25: The Diverse Environment in Which We Operate

    The Diverse Environment in Which We Operate 25

  26. Slide 26: The Diverse Environment in Which We Operate

    The Diverse Environment in Which We Operate 26

  27. Slide 27: The Diverse Environment in Which We Operate

    The Diverse Environment in Which We Operate 27

  28. Slide 28: The Diverse Environment in Which We Operate

    The Diverse Environment in Which We Operate 28

  29. Slide 29: The Diverse Environment in Which We Operate

    The Diverse Environment in Which We Operate 29

  30. Slide 30: The Diverse Environment in Which We Operate

    The Diverse Environment in Which We Operate 30

  31. Slide 31: The Diverse Environment in Which We Operate

    The Diverse Environment in Which We Operate 31

  32. Slide 32: The Diverse Environment in Which We Operate

    The Diverse Environment in Which We Operate 32

  33. Slide 33: The Diverse Environment in Which We Operate

    The Diverse Environment in Which We Operate 33

  34. Slide 34: Development Expertise – Technical

    Development Expertise – Technical 34

  35. Slide 35: Development Expertise – Technical

    Development Expertise – Technical 35

  36. Slide 36: Development Expertise – Technical

    Development Expertise – Technical 36

  37. Slide 37: Development Expertise – Technical

    Development Expertise – Technical 37

  38. Slide 38: Development Expertise – Technical

    Development Expertise – Technical 38

  39. Slide 39: Development Expertise – Technical

    Development Expertise – Technical 39

  40. Slide 40: Development Expertise – Technical

    Development Expertise – Technical 40

  41. Slide 41: Development Expertise – Technical

    Development Expertise – Technical 41

  42. Slide 42: Development Expertise – Technical

    Development Expertise – Technical 42

  43. Slide 43: A Flexible, Efficient and Transferable Approach to Projects

    A Flexible, Efficient and Transferable Approach to Projects • Define and plan, set contracting strategy early • Identify risks, and identify opportunities • Copy existing designs, duplication, standardization, brainstorm • Maximize commonality of equipment • Maximize in house work and leverage off o

  44. Slide 44: Over the Last ~12 Months

    Over the Last ~12 Months  RAVENSTHORPE Commissioning and commercial production achieved on December 28, 2011  KEVITSA Completion of construction, commissioning and commercial production achieved on August 18, 2012  KANSANSHI Numerous improvement projects 1,000tpd Acid Plant 5 – commissioned and o

  45. Slide 45: Sentinel Project

    Sentinel Project & INERALS LTD.

  46. Slide 46: Sentinel Copper Concentrator Simplified Flowsheet

    Sentinel Copper Concentrator Simplified Flowsheet  Crushing and Conveying  Stockpile and Reclaim  Milling  Flotation  Filtration and Copper Concentrate Product 46

  47. Slide 47: Key Recent Accomplishments

    Key Recent Accomplishments  Total Sentinel project progress to date is 19.2% cumulative  Record construction progress in earthworks and concrete  50% concrete poured (36,600m3)  Over 6,600t of structural steel issued Approved For Construction (>50%), over 2,000t fabricated, over 1,000t erected 

  48. Slide 48: Key Recent Accomplishments

    Key Recent Accomplishments  Merged all execution areas to common project schedule  Completed quarry mining balance of project concrete requirements  Increased to 74% Zambian project content (+6% from December 2012)  First houses ready for occupation 48

  49. Slide 49: Efficient Site Manning

    Efficient Site Manning FQML Expat 1% FQM Roads Expat Infra Expat 1% Operations & 1% Support Expat Infra Filipinos 1% 8% Infra Local FQML Plant 27% Filipinos / Indonesians 14% FQMO Roads Local FQML Plant Local 11% 16% Operations & Support Local 19% Filipinos / Department Local Expat TOTAL Indonesians

  50. Slide 50: Rapid Ramp-up of Site Manpower

    Rapid Ramp-up of Site Manpower Data Date (28 Jan 13) 50

  51. Slide 51: Sentinel On Schedule and On Budget

    Sentinel On Schedule and On Budget Data Date (28 Jan 13) Overall Progress: Actual = 19.18% Plan = 19.07% Commitments Budget Sentinel Capex $950M $1,885M 51

  52. Slide 52: The Planning (2011)

    The Planning (2011) & FIRST QUANTUM (s2) INERALS LTD.

  53. Slide 53: Sentinel Mill Area (June 2012)

    Sentinel Mill Area (June 2012) 53

  54. Slide 54: Sentinel Mill Area (July 2012)

    Sentinel Mill Area (July 2012) 54

  55. Slide 55: Sentinel Mill Area (August 2012)

    Sentinel Mill Area (August 2012) 55

  56. Slide 56: Sentinel Mill Area (September 2012)

    Sentinel Mill Area (September 2012) 56

  57. Slide 57: Sentinel Mill Area (October 2012)

    Sentinel Mill Area (October 2012) 57

  58. Slide 58: Sentinel Mill Area (November 2012)

    Sentinel Mill Area (November 2012) 58

  59. Slide 59: Sentinel Mill Area (December 2012)

    Sentinel Mill Area (December 2012) 59

  60. Slide 60: Sentinel Mill Area (January 2013)

    Sentinel Mill Area (January 2013) 60

  61. Slide 61: Sentinel Mill Area (January 2013)

    Sentinel Mill Area (January 2013) 61

  62. Slide 62: Sentinel Mill Area (January 2013)

    Sentinel Mill Area (January 2013) 62

  63. Slide 63: First Mill Shell Delivery

    (> carriers - &logistics \\ 65511) — | FIRST QUANTUM (63) MINERALS LTD.

  64. Slide 64: First Mill Shell Delivery

    FIRST QUANTUM (64) MINERALS LTD.

  65. Slide 65: 1,000 Man Construction Camp

    1,000 Man Construction Camp 65

  66. Slide 66: River Diversion

    River Diversion FIRST QUANTUM MINERALS LTD.

  67. Slide 67: River Diversion

    & FIRST QUANTUM MINERALS LTD.

  68. Slide 68: Arial Plant Site (November 2012)

    Arial Plant Site (November 2012) 68

  69. Slide 69: Arial Plant Site (November 2012)

    Arial Plant Site (November 2012) 69

  70. Slide 70: Arial Plant Site (November 2012)

    Arial Plant Site (November 2012) 70

  71. Slide 71: Arial Plant Site (November 2012)

    Arial Plant Site (November 2012) 71

  72. Slide 72: Arial Plant Site (November 2012)

    Arial Plant Site (November 2012) 72

  73. Slide 73: Sentinel Tails Thickening (January 2013)

    Sentinel Tails Thickening (January 2013) 73

  74. Slide 74: Sentinel Main Warehouse (January 2013)

    Sentinel Main Warehouse (January 2013) 74

  75. Slide 75: Concrete Bench Plant

    Concrete Bench Plant & FIRST QUANTUM MINERALS LTD.

  76. Slide 76: Quarry for Concrete Aggregates

    Quarry for Concrete Aggregates 76

  77. Slide 77: Block Making Machine for Housing

    Block Making Machine for Housing 77

  78. Slide 78: Block Making Machine for Housing

    Block Making Machine for Housing 78

  79. Slide 79: Truss Making Machine for Housing

    Truss Making Machine for Housing 79

  80. Slide 80: Truss Making Machine for Housing

    Truss Making Machine for Housing 80

  81. Slide 81: Senior Housing and Golf Course

    Senior Housing and Golf Course 81

  82. Slide 82: Accommodation and Messing

    Accommodation and Messing 82

  83. Slide 83: Senior Housing

    . 4 ike ** Se Mi % Wi) me ~ 7 = | aw _! Te ‘ & FIRST QUANTUM MINERALS LTD.

  84. Slide 84: Senior Housing

    & FIRST QUANTUM (#4) MINERALS LTD.

  85. Slide 85: Senior Housing

    Hagley +i aan eats et - Se at ee 7 Rei a ce, SME PF ES 7 FIRST QUANTUM MINERALS LTD.

  86. Slide 86: Senior Housing

    Senior Housing 86

  87. Slide 87: Senior Housing

    Senior Housing 87

  88. Slide 88: Senior Housing

    Senior Housing 88

  89. Slide 89: Senior Housing

    & FIRST QUANTUM MINERALS LTD.

  90. Slide 90: Senior Housing

    Senior Housing 90

  91. Slide 91: Sentinel is Not Cobre Panama – But it is Comparable

    Sentinel is Not Cobre Panama – But it is Comparable A project's size is defined not by how much you spend on it Main Project Elements Sentinel Cobre Panama (excl. Enterprise) Throughput 55 Mtpa 60 Mtpa Output (LOM Average) 270 – 300 ktpa 266 ktpa Year of First Production 2014 2016 Process Plant $713

  92. Slide 92: Sentinel is Not Cobre Panama – But it is Comparable

    Sentinel is Not Cobre Panama – But it is Comparable Sentinel Frontier Cobre Panama Throughput (Mtpa) 55 10 60 Copper Production (ktpa) 270-300 96 266 $m % $m % $m % Total Capex 1,885 100% 226 100% 6,182 100% Process Plant and Mining 1,146 61% 156 69% 1,531 25% Equipment Mine other, Dewatering, Pre-

  93. Slide 93: A Highly Attractive Offer

    A Highly Attractive Offer BO INERALS LTD.

  94. Slide 94: A Vision to Create a Global Copper Leader

    A Vision to Create a Global Copper Leader  Combination of First Quantum and Inmet expected to be the new go-to copper producer  Combination creates significant value  Combination expected to be re-rated upwards  Combination with a long standing commitment to social and environmental excellence 