British Land Company PLC · LSE:BLND

British Land — Investor Presentation (September 2014)

34 slides from British Land's investor presentation, Sep 23, 2014

  1. Slide 1: Paddington Central Property Tour

    WWW.BRITISHLAND.COM PADDINGTON CENTRAL Property Tour 23 SEPTEMBER 2014

  2. Slide 2: Introduction

    INTRODUCTION Tim Roberts Head of Offices and Residential 2

  3. Slide 3: Key Office and Residential Highlights

    KEY OFFICE AND RESIDENTIAL HIGHLIGHTS • Strengthening leasing performance – Successful letting particularly across our recently completed West End developments • Successful completion of all our 2010 West End developments – Plus 605,000 sq ft at The Leadenhall Building • Well timed acquisitions of P

  4. Slide 4: Leasing Activity Across Our Office Portfolio

    LEASING ACTIVITY ACROSS OUR OFFICE PORTFOLIO • Strengthening letting interest in recent months • Over 200,000 sq ft leasing activity completed/under offer in Q1 including at Leadenhall and 10 Portman Square • Further leasing successes since Q1 announcement, including at 10 Portman Square, Marble Arc

  5. Slide 5: Paddington Central Overview

    PADDINGTON CENTRAL OVERVIEW • 11 acre mixed-use estate in London’s West End acquired in July 2013 • 1.2m sq ft, comprising 7 modern buildings, and a retail and leisure cluster • 610,000 sq ft income generating properties – Occupied by high quality tenants including AstraZeneca, Nokia, Statoil and Ac

  6. Slide 6: Paddington Central Campus

    PADDINGTON CENTRAL CAMPUS Key: BL ownership Non BL ownership Multi-let offices Multi-let offices 268,000 sq ft 143,000 sq ft Development sites 200 residential units (355,000 sq ft) + sold on long leases; Crossrail box below retail at ground floor (80,000 sq ft) FOUR KINGDOM STREET FIVE KINGDOM STREE

  7. Slide 7: Asset Management Initiatives

    ASSET MANAGEMENT INITIATIVES David Lockyer Head of West End Asset Management 7

  8. Slide 8: Progress to Date – 1 Year On

    PROGRESS TO DATE – 1 YEAR ON • Detailed master-plan developed to form long term vision for the campus and its immediate environment. – Improved existing planning consent for 4 KS and redesigning 5 KS – Significant upgrade works to public realm with next phase due to start early 2015 – Improved conne

  9. Slide 9: Public Realm Improvements – Quick Wins

    PUBLIC REALM IMPROVEMENTS – “QUICK WINS” Short-term of objective was to inject life into the campus through summer of sport, film festivals, gigs, food markets, promotions etc to de-sterilise and de-corporatise Before After 9

  10. Slide 10: Masterplan and Vision

    MASTERPLAN AND VISION The masterplan focuses on improving connectivity and permeability to the campus so that it better relates to it’s surroundings and feels part of Central London 10

  11. Slide 11: Masterplan and Vision

    MASTERPLAN AND VISION Improvements to public realm focused around 7 key areas, as well as the development of 4 and 5 Kingdom Street, are a key factor in delivering the physical elements of the masterplan and Vision 11

  12. Slide 12: Next 12 Months – Progressing Masterplan

    NEXT 12 MONTHS – PROGRESSING MASTERPLAN • Start on site with 4 Kingdom Street • Submit planning application for next phase of public realm works which will be focused on the canal-side, the two pedestrian approaches from H&C line exit and Little Venice and the amphitheatre • The rebrand of Paddingto

  13. Slide 13: Paddington Central – Crossrail

    PADDINGTON CENTRAL – CROSSRAIL • Paddington will be one of only three Crossrail stations in London’s West End with direct access to City and Docklands • New access point to Crossrail will be opposite the entrance to Paddington Central, off Bishop’s Bridge Road • As part of these works, reconstructio

  14. Slide 14: Improvements to Sheldon Square

    IMPROVEMENTS TO SHELDON SQUARE • Replace existing harsh ‘stadium lighting’ • Improve shop fronts • Upgrade public realm • Improve circulation areas and use of amphitheatre 14

  15. Slide 15: Improving the Canal Side Entrances

    IMPROVING THE CANAL SIDE ENTRANCES • Upgrade lighting • Introduce art installations • Introduce signage • Widen approaches • Improve finishes • Underpin attractions of canal 15

  16. Slide 16: Improving the Canal Side Entrances

    IMPROVING THE CANAL SIDE ENTRANCES • Upgrade lighting • Introduce art installations • Introduce signage • Improve sightlines and visibility • Improve finishes • Incorporate underutilised areas to create activity 16

  17. Slide 17: Improvements to Kingdom Street

    IMPROVEMENTS TO KINGDOM STREET • Re-balance the priorities between pedestrians and vehicles • Reduce scale to ‘humanise’ the space • Improve the landscaping to soften the feel

  18. Slide 18: Also Upgrading the Buildings

    ALSO UPGRADING THE BUILDINGS • Improving the reception of 2 Kingdom Street to meet occupier needs and their ways of working

  19. Slide 19: Developments

    DEVELOPMENTS Nigel Webb Head of Developments 19

  20. Slide 20: Strong Track Record in Successfully Delivering Developments

    WE HAVE A STRONG TRACK RECORD IN SUCCESSFULLY DELIVERING DEVELOPMENTS • Largest Central London office developer: over 4.5m sq ft completed since 2004 • High quality buildings with strong environmental record YORK HOUSE WILLIS BUILDING 201 BISHOPSGATE & ROPEMAKER PLACE 10 & 20 TRITON 199 BISHIOPSGATE

  21. Slide 21: Progressing Our New London Developments

    PROGRESSING OUR NEW LONDON DEVELOPMENTS • Added 1.1m sq ft of new potential development • Estimated profit of c£375m; of which c£290m to come • Expect to commit to 4 Kingdom Street later this year • Progressing 5 Kingdom Street and Shoreditch plans; retain optionality CLARGES THE ALDGATE YALDING 4 K

  22. Slide 22: Paddington Central – Development Sites

    PADDINGTON CENTRAL – DEVELOPMENT SITES • Secured revised planning consent for • Situated below existing Crossrail deck • 210,000 sq ft of offices (as consented) improved 145,200 sq ft building at ground level (80,000 sq ft) • 14 floors • 9 floors • 8 metre clear slab • Plan to redesign scheme and ad

  23. Slide 23: 4 Kingdom Street Critique + Design Changes

    4 KINGDOM STREET CRITIQUE + DESIGN CHANGES Opportunities for improvement Proposed solutions and mitigations Poor sub-divisibility + floorplate Redesigned and relocated core to create better variation sub-divisibility Lack of ground floor animation Moved corner reception to central position to create

  24. Slide 24: 4 Kingdom Street – Design Improvements

    4 KINGDOM STREET – DESIGN IMPROVEMENTS GROUND FLOOR RECEPTION Rationalised core and central reception increase sub-divisibility TYPICAL UPPER FLOOR Increased lifting capacity and created terraces & tenant amenity space

  25. Slide 25: 4 Kingdom Street – Design Improvements: Facades and Terraces

    4 KINGDOM STREET - DESIGN IMPROVEMENTS FACADES AND TERRACES Consented Proposed - Terraces introduced on each level

  26. Slide 26: 4 Kingdom Street – Design Improvements: Proposed Roof Terrace

    4 KINGDOM STREET - DESIGN IMPROVEMENTS PROPOSED ROOF TERRACE

  27. Slide 27: Appendices

    APPENDICES 27

  28. Slide 28: Paddington Location

    PADDINGTON LOCATION 1 3 2 1. Paddington Central 2. Paddington Station 3. Paddington Basin

  29. Slide 29: The Paddington Area

    THE PADDINGTON AREA 1 2 3 4 5 Paddington 55-65 North Paddington North Westminster ‘Triangle site’ Central Wharf Road Basin Community School 11 4 5 6 3 11 Stone Wharf / towards 1 Little Venice 2 12 Future Crossrail entrance 7 9 8 12 10 6 7 8 9 10 Paddington Eastbourne St. Mary’s Post Office Merchant

  30. Slide 30: Paddington Central – Key Occupiers

    PADDINGTON CENTRAL – KEY OCCUPIERS • Top 8 tenants represent c.75% of the income Area Contracted Unexpired Occupier Building sq ft rent pa £m lease term Astra Zeneca 2 Kingdom Street 75,000 3.4 11 yrs Nokia 2 Kingdom Street 58,000 3.3 8 yrs Rio Tinto 2 Kingdom Street 26,000 1.5 12 yrs Statoil 2 King

  31. Slide 31: 2010 Development Programme

    2010 DEVELOPMENT PROGRAMME As at 31 March 2014 Sector BL Share Sq ft PC Current Cost to ERV Pre-let Resi End Calendar Value Complete Value % '000 Year £m £m1,6 £m2 £m £m3 10 - 30 Brock Street, Regent’s Place4 Mixed Use 100 505 Completed 402 3 20.5 19.1 118 10 Portman Square Offices 100 134 Completed

  32. Slide 32: Recently Committed Development Programme

    RECENTLY COMMITTED DEVELOPMENT PROGRAMME As at 31 March 2014 Sector BL Share Sq ft PC Current Cost to ERV Pre-let Resi End Calendar Value Complete Value % '000 Year £m £m1,4 £m2 £m £m3 Milton Keynes, Kingston Centre Retail 50 21 Completed 5 - 0.3 0.3 - 6 Old Market, Hereford Retail 100 305 Completed

  33. Slide 33: Near-Term and Prospective Developments

    NEAR-TERM AND PROSPECTIVE DEVELOPMENTS As at 31 March 2014 BL Share Sq ft Total Cost Status % '000 £m1 Near-term Pipeline Blossom Street, Shoreditch Mixed Use 100 322 164 Pre-submission 2 5 Kingdom Street Offices 100 240 162 Consented 4 Kingdom Street Offices 100 147 99 Consented Glasgow Fort (Resta

  34. Slide 34: Disclaimer

    DISCLAIMER The information contained in this presentation has been extracted largely from the Full Year Results Announcement for the year ended 31 March 2014. This presentation may contain certain “forward-looking” statements. By their nature, forward-looking statements involve risk and uncertainty