Nordic Iron Ore Ab · OMXSTO:NIO
Nordic Iron Ore Ab — Informa 8th EU Iron Ore 2013
38 slides from Nordic Iron Ore Ab's conference presentation, Oct 1, 2013
Slide 1: Nordic Iron Ore – Company Presentation
Nordic Iron Ore – Company Presentation The Rejuvenation of the Ludvika Iron Ore Mines – Europe’s next iron ore producer Informa 8th EU Iron Ore Paris, 1-2nd October 2013 1
Slide 2: Agenda
Agenda Introduction Investment highlights Project time plan Financial information Conclusion 2
Slide 3: What defines a good iron ore project?
What defines a good iron ore project? Access to cost effective logistics solutions, - ie railway direct to deep sea port Low operating costs – Under USD 60 /dmt FOB Low capital intensity – <USD 200/annual tonne production Nearby markets Easily beneficiated ore High quality product >62%Fe
Slide 4: Nordic Iron Ore at a glance
Nordic Iron Ore at a glance Restarting Ludvika Mines – Blötberget – mining concession granted • Phase 1 Feasibility study • Environmental permit expected Q4 2013 – Väsman field – under further exploration • Mine concession application submitted 2014 • Environmental permit application 2015 – Håksbe
Slide 5: Our targets
Our targets Production 4.3 Mtpa Production start coarse fines: Q3 2014 Start new beneficiation plant Q3 2016 Concentrate 67% Fe or better 5
Slide 6: Solid economics
Solid economics IRR 25 per cent Pay back period 4.5 years At least 15 year life of mine 6
Slide 7: Investment highlights
Agenda Introduction Investment highlights Project time plan Financial information Conclusion 7
Slide 8: One of Sweden’s largest iron mineralisations (Swedish)
One of Sweden’s largest iron mineralisations Håksberg: Indikerat 25 mt @ 36% Antagen 12 mt @ 36% Väsmans syd mineralisering: Indikerat 7 mt @ 39% Antagen 86 mt @ 38% Blötberget : Indikerat 30 mt @ 45% Antagen 10 mt @ 43% 8
Slide 9: One of Sweden’s largest iron mineralisations
One of Sweden’s largest iron mineralisations Håksberg: 3 Indicated 25 Mt @ 36% Inferred 12 Mt @ 36% Väsman: South mineralisation: Indicated 7 Mt @ 39% Inferred 86 Mt @ 38% Blötberget: Indicated 30 Mt @ 45% Inferred 10 Mt @ 43% 9
Slide 10: Expansion potential
Expansion potential 75000 MagTot (nt) 65000 55000 Targeting mineral resources in excess of 300Mt N S 10
Slide 11: Beneficiation plant next to existing railway
Beneficiation plant next to existing railway 11
Slide 12: Integrated expansion of project to 4.3Mt/y
Integrated expansion of project to 4.3Mt/y Development in three phases 12
Slide 13: Product price premium
Product price premium High quality products Fines Concentrate 67% Fe Concentrate 13
Slide 14: High quality product
High quality product NIO will produce high quality pellet feed concentrates (possibility to produce sinter fines), expected to Comparison of average % Fe yield premium pricing 80 % 70 % 60 % 50 % 40 % 30 % 20 % 10 % 0% Resources Fortescue Dannemora (fines) Kumba Cleveland Cliffs BHP Northern Iron Va
Slide 15: Competitive cost level
Competitive cost level Competitive cash cost and premium product USD 76/dmt 51 /NIO 15
Slide 16: Competitive cash costs to European market – upside potential
Competative cash costs to European market – upside potential USD 59/dmt CFR Rotterdam / Nordic Iron Ore AB 16
Slide 17: Low development risk
Low development risk Scaleable project Experienced management team Existing mine infrastructure Reduced CAPEX Reduced development time Ground pre-prepared for extraction Incremental development Existing competitive logistics solution to deep-water port
Slide 18: Existing logistics – competitive OPEX
Existing logistics – competitive OPEX Existing railway from mine to deep water port MSEK 900 (MUSD 130) committed by Swedish government for refurbishment of railway All year ice free port Baby Cape/Panamax capacity LoI signed with Oxelösund port 18
Slide 19: Project time plan
Agenda Introduction Investment highlights Project time plan Financial information Conclusion 19
Slide 20: Initial phase (2010-2012)
Initial phase (2010-2012) Organisation, management team & BoD Funding: Two mining concessions granted PEA/Scoping study MSEK 98 Environmental permit application (MUSD 15) 20
Slide 21: Current phase (2013)
Current phase (2013) Resource expansion and infill drilling Funding: Beneficiation tests and process layout SEK 50 million DFS Phase I (MUSD 7.5) Exploratory talks with market for off-take agreements 21
Slide 22: Construction Phase I (2014-2015)
Construction Phase I (2014-2015) Mining concession application Väsman Funding: Environmental permit application Väsman MSEK 2 000 Preparation for construction phase – Dewatering Blötberget (MUSD 300) – New entrance tunnel Production start Phase Ia 22
Slide 23: Construction Phase I (2014-2015) cont.
Construction Phase I (2014-2015) cont. Construction project build up Construction of plant with first production line and rail terminal • Off-take agreements (preferred with finance) • Complete feasibility study - Phase II 23
Slide 24: Construction Phase II (2016-2017)
Construction Phase II (2016-2017) Organizational build up Development of Väsman Funding: MSEK 700 Complete production line 1 - commission (MUSD 100) Production start and ramp-up Construction of production line 2 Commissioning process line 2 24
Slide 25: Construction phase III (2018-2019)
Construction phase III (2018-2019) Mine development of N Väsman & S Håksberg Production ramp-up Construction of production line 3 Commission production line 3 25
Slide 26: Risk mitigation
Risk mitigation Construction and process risk greatly reduced due to: 1 Complete DFS before final investment decision 2 Experienced project management team, supported by strong engineering and mine development functions 3 Detailed planning and close monitoring of schedule 4 Focus on cost control and
Slide 27: Risk mitigation – separate project organisation
Risk mitigation – separate project organisation Project director Exploration Procurement & Controller quality Production Economy & finance Planning HSE CEO Logistics HR Marketing and sales Blötberget Väsman Environment Håksberg Skeppmora 27
Slide 28: Project development schedule
Project development schedule -- Key milestones Investment decision & start of early production Construction, Beneficiation start DFS-Phase I Installation & commissioning & ramp up 2013 2014 2015 2016 2017-2019 Environmental permit B+H Environmental permit V Mining concession V Permits/concessions re
Slide 29: Management and board
Management and board Management Christer Lindqvist Lennart Eliasson Hans Thorshag Louise Sjögren Paul Marsden CEO CFO Technical Director Chief Geologist Sales and Marketing Board of directors Broad mix of skills, knowledge and experience Board is incentivised through stocks and options 29
Slide 30: Financial information
Agenda Introduction Investment highlights Project time plan Financial information Conclusion 30
Slide 31: Attractive economics
Attractive economics Example calculation at full production, USD/t Assumed long term price (62% Fe) 120 Premium (67% Fe) +15 Freight –24 FOB 111 OPEX* -52 OH-cost -1 Financing cost** -10 Margin 48 *During the first 2 years OPEX will be higher ** Financing cost will be lower after ≈ 5 years
Slide 32: CAPEX- three phases overview and schedule
CAPEX- three phases overview and schedule 10% MUSD 671 to full production 4% 5% 38% 200 42% 152 Mining Benefication Transport & Logistics Infrastructure & Buildings 138 Administration 128 100 95 87 Studies = 23 71 Phase III=168 Phase II =182 Phase I = 298 0 2014 2015 2016 2017 2018 2019 32
Slide 33: Capex and production ramp-up
Capex and production ramp-up Staged mine development brings down risk Revenue from Q3 2014 Gradual ramp up of logistics chain Part of Capex financed internally 200 Chart Title 4.00 150 20 3.00 100 4.3 152 3.6 2.00 70 128 118 50 2.5 71 87 0.5 1.9 1.00 25 0.5 0.6 0.2 0 0.00 2014 2015 2016 2017
Slide 34: Funding strategy
Funding strategy Financing steps, MUSD Funds raised = MSEK 98 (approx. MUSD 14) ≈ 300 300 Investments will be financed approx. 50/50 debt/ equity IPO planned in connection with funding of investment 200 Second raise for phase II and III after start of production Phase I IPO ≈ 100 100 1,5 3,2 8,6 7,5
Slide 35: Key figures
Key figures Targeting a 4.3 Mtpa operation OPEX 51.5 USD/t CAPEX to full production USD 671 million Pay back period ≈ 4.5 years NPV (@ 8.0%) USD 1,024 million IRR 25%mine at
Slide 36: Conclusion
Agenda Introduction Investment highlights Project time plan Financial information Conclusion 36
Slide 37: Conclusion
Conclusion 1 Low development risk Opportunity to capitalise 2 on sunk capital Existing Logistics 3 solution 4 High quality product Very competitive OPEX 5 with upside potential Large mineralization with 6 expansion potential 37
Slide 38: Thank you
Thank you www.nordicironore.se