  2. Slide 2: FY2022 Highlights

    FY2022 Highlights Completed sale of 50% of interests in Amadeus Basin • Recognised $36.6 million book profit on sale • NZOG / Cue are funding Central’s share of over $100 million in development and exploration in the permits Steady underlying production and revenues • New Mereenie production wells b

  3. Slide 3: Headline Results

    Headline Results Sales volume 6.3 PJe • Down 39% (2% down on like-for-like basis) • Reflects 50% reduction in ownership interest from October 2021 Sales revenues $42.2m • Down 30% (up 12.7% on a like-for-like basis) • Stronger commodity prices • 15% of gas sold into east coast spot gas market EBITDA

  4. Slide 4: Solid Operational Performance

    Solid Operational Performance Sales prices $6.73 / GJe $5.83 in FY2021 ✓ Gas prices up 15.4% due to spot markets / contract escalation Operating costs ✓ Higher oil prices $3.39 / GJe $2.81 in FY2021 ➢ Includes transportation costs for new sales contract and spot sales ➢ Increased royalties on higher

  5. Slide 5: Financial Security

    Financial Security Reduction and extension of debt facility Maturing facility New facility Net debt $10.2m (down $4.8m) Expiry 30 September 2022 30 September 2025 Loan Balance $30.8m Principal repayments $2.0m per quarter $1.125m per quarter Early termination fee Lesser of: Nil Facility extended • 2

  6. Slide 6: New Contracts in Strong Gas Markets

    New Contracts in Strong Gas Markets Term gas markets remain strong Existing gas contracts escalate with inflation Very strong market interest in new firm gas contracts from 2023 New firm gas sales agreements + 3.15 PJ* over 4 years from 1 Jan 2022 + 0.9125 PJ* during 2025 New access to east coast sp

  7. Slide 7: Drilling Program Update

    Drilling Program Update PV12 drilling progress • Original target (PV Deep) at 3,560m • Difficult drilling conditions – heavily fractured zones resulted in lost circulation of drilling fluids; hard rock resulted in slow rate of penetration • Revised exploration target in lower Pacoota P2/P3 Sandstone

  8. Slide 8: Sub-salt Exploration Program Update

    Sub-salt Exploration Program Update Key activities underway Santos (operator) has commenced procurement, rig contracting, approvals Three wells commencing in 2023 Dukas, Mt Kitty and Mahler Targeting helium, naturally-occurring hydrogen and hydrocarbons Peak farm-out Peak Helium will fund Central’s

  9. Slide 9: Near-term activity (CTP Share)

    Near-term activity (CTP Share) Zevon seismic (100%) Palm Valley #12 drilling (50%) Mereenie production Subsalt Gas, helium and enhancement (25%) Targeting near-term production hydrogen target Planning underway for: through P1 appraisal currently Seismic planned 2023 underway • up to 6 well recomplet

  10. Slide 10: Appendix: Reserves and Resources Information

    Appendix 1 Reserves and Resources Information

  11. Slide 11: Appendix 1: Reserves and Resources information

    Appendix 1: Reserves and Resources information Reserves and contingent resources Reserves Contingent Resources Proved Proved & Best estimate Central – existing fields Probable (Central share) Units 1P 2P 2C Mereenie oil mmbbl 0.37 0.41 0.05 Mereenie gas PJ 30.5 39.2 45.6 Palm Valley PJ 11.3 12.7 6.8

  12. Slide 12: Appendix 1: Reserves and Resources information

    Appendix 1: Reserves and Resources information Prospective Resources – Amadeus exploration targets (Central Share) Low Estimate Best Estimate High Estimate Mean Resources Estimates Target Permit P90 P50 P10 The volumes of Prospective Lead / Prospect Permit formation Interest Recoverable Recoverable

  13. Slide 13: Notice and Legal Disclaimer

    Notice and Legal Disclaimer To the maximum extent permitted by law: This presentation is not intended for prospective investors and does not purport to provide all of the information an interested party may require in order to investigate the affairs of Central Petroleum Ltd (“Company”). This presen

  14. Slide 14: Contact and Further Information

    Level 7, 369 Ann Street Brisbane QLD 4000 Contact and Australia Further Information +61 (0)7 3181 3800 info@centralpetroleum.com.au This presentation was approved and authorised for www.centralpetroleum.com.au release to ASX by Leon Devaney, Managing Director and Chief Executive Officer 14

Central Petroleum — FY2022 Earnings Presentation on 6ix