Boral Ltd.

Boral — Corporate Update (December 2022)

26 slides from Boral's corporate update, Dec 1, 2022

  1. Slide 1: Berrima Cement Works Community Liaison Group Meeting

    Berrima Cement Works Community Liaison Group Meeting 1 December 2022

  2. Slide 2: Agenda

    Agenda 1. Welcome and apologies 2. Operations summary 3. Environmental works update 4. Planning and projects 5. Communications update 6. General business and contacts 7. Next meeting 2

  3. Slide 3: Welcome and Apologies

    Welcome and Apologies

  4. Slide 4: Attendees

    Attendees CLG representatives Clive West, Berrima resident and Berrima Resident Association representative Andrew Wood, New Berrima resident Barry Arthur, Environment Manager, Wingecarribee Shire Council Boral staff Dean Beltrame, Operations Manager Berrima Greg Johnson, Environmental Sustainability

  5. Slide 5: Review of Minutes and actions arising from last meeting

    Review of Minutes and actions arising from last meeting Previous meeting Minutes – 29 July 2022 Matters arising from last meeting • Develop an email distribution list for alerts regarding unusual noise or maintenance that will include contact details for community enquiries. • Invite the Boral Prope

  6. Slide 6: Operations summary

    Operations summary

  7. Slide 7: Safety, Customer and People

    Safety • Zero harm achieved (no serious incidents). • Wet weather continues to present hazardous conditions on site in particular with material handling. • January major shutdown risk assessment and safety management plan review currently in progress. Customer and People • No supply or product quali

  8. Slide 8: Production/Performance

    Production/Performance • Clinker and cement volumes similar to last year (~ 1.35Mt & ~ 1Mt respectively). • Energy costs continue to be a significant head wind (coal & electricity). Value Improvement Projects identified and progressing to assist mitigate these costs (SWDF, GBFS, Cement milling effic

  9. Slide 9: Environmental works update

    Environmental works | update

  10. Slide 10: Environmental overview

    Environmental overview • Independent Annual Non-Standard Fuels Audit scheduled for November​. • High Rate WW/RDF Proof of Performance Trials submitted to DPE to support our SWDF usage from 40 to 50%​. • Tyre Chip trial approved by EPA and DPIE completed. EPA accepted trial completed as required in c

  11. Slide 11: Management plan update

    Management plan update There have been no recent updates. Future updates to the OEMP and other management plans will be undertaken as required when consent modifications are made with a full review due next April 2023. 11

  12. Slide 12: Environmental monitoring – air quality management

    Environmental monitoring – air quality management • Our last stack test was undertaken on over 30/6 and 1/7 2022​. • All stack tests YTD have been compliant along with our Continuous Emission Monitoring (CEMs). 12

  13. Slide 13: Environmental monitoring – dust deposition trends

    Environmental monitoring – dust deposition trends 13

  14. Slide 14: Environmental monitoring – high volume air sampler data

    Environmental monitoring – high volume air sampler data 14

  15. Slide 15: Property planning and approvals update

    Property planning and approvals update

  16. Slide 16: Modification 14 – solid waste derived fuels (SWDF)

    Modification 14 – solid waste derived fuels (SWDF) Project Objective • Increase the volume of SWDF from 100,000tpa to 250,000tpa; • Expansion of existing SWDF storage and handling facilities; • Construct an alternate access to the site; • Additional 13 truck movements per day; and • Permit 24 hour d

  17. Slide 17: Modification 15 – tyre chip storage and feed infrastructure

    Modification 15 – tyre chip storage and feed infrastructure Project Objective • Permit new permanent outdoor storage and feed system to support use of tyre chips; • Modification of relevant conditions of consent; and • Tyre chip use already permitted under Kiln 6 development consent, no change in vo

  18. Slide 18: Carbon Capture Pilot Plant

    Carbon Capture Pilot Plant Project Objective • 1 - 3 year trial to research carbon emissions reduction associated with the production/manufacture of clinker; • Importation of up to 2,000 tonnes of recycled concrete aggregates processed from construction and demolition waste; • Installation of pre-fa

  19. Slide 19: Planned applications

    Planned applications Consent to be modified Description Timing Ball Mill Consent (DA85-4-2005) Modification to align noise management conditions of Currently on hold the ball mill consent with approved site wide noise management plan 19

  20. Slide 20: Communications update

    Communications update

  21. Slide 21: Communications update: CLG vacancy and community drop-in session

    Advertisement for the EOI for the vacant CLG position has been put on the notice board at the post office and will be shared with the Berrima Residents Association. A community drop-in session was held in Berrima on 26 November to answer questions regarding the proposed pit top treatment and pipelin

  22. Slide 22: General business and contacts

    General business and contacts

  23. Slide 23: General business

    General business Items of general business: • Habitat corridors along the riparian zones on Boral land – (Cameron McArthur) • What is an electrostatic precipitator (esp) trip ? (Gabriel Paicu) 23

  24. Slide 24: Contacts

    Contacts Boral Berrima Cement contacts: Reception 02 4860 2222 Kate Woodbridge Stakeholder Relations Manager 0401 893 815/ kate.woodbridge@boral.com.au www.boral.com.au/berrimacement feedback@boral.com.au Like us on Facebook: @ Boral Australia 24

  25. Slide 25: Next meeting

    Next meeting • Move to six monthly meetings?

  26. Slide 26: BORAL

    BORAL Building something great