Slide 1: Berrima Cement Works Community Liaison Group Meeting
Berrima Cement Works Community Liaison Group Meeting 1 December 2022
Slide 2: Agenda
Agenda 1. Welcome and apologies 2. Operations summary 3. Environmental works update 4. Planning and projects 5. Communications update 6. General business and contacts 7. Next meeting 2
Slide 3: Welcome and Apologies
Welcome and Apologies
Slide 4: Attendees
Attendees CLG representatives Clive West, Berrima resident and Berrima Resident Association representative Andrew Wood, New Berrima resident Barry Arthur, Environment Manager, Wingecarribee Shire Council Boral staff Dean Beltrame, Operations Manager Berrima Greg Johnson, Environmental Sustainability
Slide 5: Review of Minutes and actions arising from last meeting
Review of Minutes and actions arising from last meeting Previous meeting Minutes – 29 July 2022 Matters arising from last meeting • Develop an email distribution list for alerts regarding unusual noise or maintenance that will include contact details for community enquiries. • Invite the Boral Prope
Slide 6: Operations summary
Operations summary
Slide 7: Safety, Customer and People
Safety • Zero harm achieved (no serious incidents). • Wet weather continues to present hazardous conditions on site in particular with material handling. • January major shutdown risk assessment and safety management plan review currently in progress. Customer and People • No supply or product quali
Slide 8: Production/Performance
Production/Performance • Clinker and cement volumes similar to last year (~ 1.35Mt & ~ 1Mt respectively). • Energy costs continue to be a significant head wind (coal & electricity). Value Improvement Projects identified and progressing to assist mitigate these costs (SWDF, GBFS, Cement milling effic
Slide 9: Environmental works update
Environmental works | update
Slide 10: Environmental overview
Environmental overview • Independent Annual Non-Standard Fuels Audit scheduled for November. • High Rate WW/RDF Proof of Performance Trials submitted to DPE to support our SWDF usage from 40 to 50%. • Tyre Chip trial approved by EPA and DPIE completed. EPA accepted trial completed as required in c
Slide 11: Management plan update
Management plan update There have been no recent updates. Future updates to the OEMP and other management plans will be undertaken as required when consent modifications are made with a full review due next April 2023. 11
Slide 12: Environmental monitoring – air quality management
Environmental monitoring – air quality management • Our last stack test was undertaken on over 30/6 and 1/7 2022. • All stack tests YTD have been compliant along with our Continuous Emission Monitoring (CEMs). 12
Slide 13: Environmental monitoring – dust deposition trends
Environmental monitoring – dust deposition trends 13
Slide 14: Environmental monitoring – high volume air sampler data
Environmental monitoring – high volume air sampler data 14
Slide 15: Property planning and approvals update
Property planning and approvals update
Slide 16: Modification 14 – solid waste derived fuels (SWDF)
Modification 14 – solid waste derived fuels (SWDF) Project Objective • Increase the volume of SWDF from 100,000tpa to 250,000tpa; • Expansion of existing SWDF storage and handling facilities; • Construct an alternate access to the site; • Additional 13 truck movements per day; and • Permit 24 hour d
Slide 17: Modification 15 – tyre chip storage and feed infrastructure
Modification 15 – tyre chip storage and feed infrastructure Project Objective • Permit new permanent outdoor storage and feed system to support use of tyre chips; • Modification of relevant conditions of consent; and • Tyre chip use already permitted under Kiln 6 development consent, no change in vo
Slide 18: Carbon Capture Pilot Plant
Carbon Capture Pilot Plant Project Objective • 1 - 3 year trial to research carbon emissions reduction associated with the production/manufacture of clinker; • Importation of up to 2,000 tonnes of recycled concrete aggregates processed from construction and demolition waste; • Installation of pre-fa
Slide 19: Planned applications
Planned applications Consent to be modified Description Timing Ball Mill Consent (DA85-4-2005) Modification to align noise management conditions of Currently on hold the ball mill consent with approved site wide noise management plan 19
Slide 20: Communications update
Communications update
Slide 21: Communications update: CLG vacancy and community drop-in session
Advertisement for the EOI for the vacant CLG position has been put on the notice board at the post office and will be shared with the Berrima Residents Association. A community drop-in session was held in Berrima on 26 November to answer questions regarding the proposed pit top treatment and pipelin
Slide 22: General business and contacts
General business and contacts
Slide 23: General business
General business Items of general business: • Habitat corridors along the riparian zones on Boral land – (Cameron McArthur) • What is an electrostatic precipitator (esp) trip ? (Gabriel Paicu) 23
Slide 24: Contacts
Contacts Boral Berrima Cement contacts: Reception 02 4860 2222 Kate Woodbridge Stakeholder Relations Manager 0401 893 815/ kate.woodbridge@boral.com.au www.boral.com.au/berrimacement feedback@boral.com.au Like us on Facebook: @ Boral Australia 24
Slide 25: Next meeting
Next meeting • Move to six monthly meetings?