Slide 1: Ningaloo Vision Cessation of Production and Floating Asset Removal Environment Plan
Information for relevant persons Ningaloo Vision Cessation of Production and Floating Asset Removal Environment Plan Activity overview Consultation and feedback Santos is planning for the All petroleum activities in Santos meets this requirement progressive decommissioning Commonwealth waters by und
Slide 2: Activity description
Activity description Activity details Timing Activities associated with the removal of the floating assets will commence following the end of field life, which could occur at any time during the five-year period of the accepted EP. The floating asset removal activity is planned to take between 45 an
Slide 3: Description of the natural environment and operational area
Description of the • The Ningaloo Australian Marine Park (AMP) is located approximately natural environment 27 km southwest of the operational area. • The operational area does not contain any shoreline habitat. Due to water depths, there are no primary producer habitats (including coral and seagras
Slide 4: Activity purpose and approvals
Activity purpose and approvals The Ningaloo Vision Cessation – description of how Santos performance to ensure impacts of Production and Floating will maintain all property on and risks during planned and Asset Removal (CoPFAR) EP the title, as required by s572 unplanned events are reduced is being
Slide 5: Defining the environment area for proposed activities
Defining the environment area for proposed activities Santos has undertaken an this activity is the combined to a different set of wind and initial assessment to identify EMBA for the modelled potential weather conditions derived the environmental, social, worst-case scenarios (discharge from histor
Slide 6: Environmental, social, economic and cultural features
Environmental, social, economic and cultural features Santos has undertaken a review of publicly available information to identify environmental, social, economic and cultural features and/or values that may be affected by activity impacts and risks. The outcomes of this review are summarised in Tab
Slide 7: Environmental, social, economic and cultural features continued
Table 2. Environmental, social, economic and cultural features ... continued Feature Description Within Within Public information review Operational EMBA Area Cultural heritage Registered cultural sites under the: No Yes There are no known sites of shipwrecks, sunken aircraft • Underwater Cultural H
Slide 8: Environmental, social, economic and cultural features continued
Table 2. Environmental, social, economic and cultural features ... continued Feature Description Within Within Public information review Operational EMBA Area Key ecological Key Ecological Features (KEFs) are Yes Yes The operational area is located within the Continental features elements of the Com
Slide 9: Activity impacts and risk management
Activity impacts and risk management We have summarised in Table 3 the potential environmental impacts and risks and associated management measures for the proposed activity. These aspects will be risk-assessed within the Environment Plan on a case-by-case basis. Table 3. Activity impacts and risk m
Slide 10: Activity impacts and risk management continued
Table 3. Activity impacts and risk management ... continued Physical presence and interaction with other marine users Description of potential impacts Compliance with the following key management measures Potential interactions with other marine users may occur as a result of: • Maritime notices. •
Slide 11: Activity impacts and risk management continued
Table 3. Activity impacts and risk management ... continued Operational discharges Description of potential impacts Compliance with the following key management measures Planned discharges from vessels to the marine environment include: • Waste (garbage) management plan. • Sewage and grey water. • D
Slide 12: Potential risks - unplanned activities
Table 3. Activity impacts and risk management ... continued Potential risks - unplanned activities Unplanned oil spill resulting from a vessel collision Description of potential risks Compliance with the following key management measures The maximum credible spill scenario as a result of a vessel co
Slide 13: Activity impacts and risk management continued
Table 3. Activity impacts and risk management ... continued Minor hydrocarbon release Description of potential impacts Compliance with the following key management measures Sources of risk from minor hydrocarbon releases may occur as a result of: • General chemical management procedure. • ROV equipm
Slide 14: Activity impacts and risk management continued
Table 3. Activity impacts and risk management ... continued Unplanned Introduction of invasive marine species (IMS) Description of potential risks Compliance with the following key management measures Introduction of invasive marine species (IMS) may occur due to: • Implementation of the management
Slide 15: Consultation and providing feedback