  1. Slide 1: Woburn to Wakefield Line Project

    Woburn to Wakefield Line Project Construction Information for Residents, Businesses and Stakeholders April 2020

  2. Slide 2: Purpose and Need

    Woburn to Wakefield Line Project Purpose and Need A strong electrical transmission grid is vital to the safety, security and economic prosperity of the region. The transmission system serves a critical role to ensure that electricity flows with a high degree of reliability from wherever the power is

  3. Slide 3: Project Overview

    Woburn to Wakefield Line Project Project Overview • To improve system reliability and address increasing demand for electricity, Eversource is constructing the Woburn to Woburn Line Project. • The Project involves the construction of a new 345-kilovolt (kV) underground transmission line that will co

  4. Slide 4: Benefits for Stoneham & Woburn

    Woburn to Wakefield Line Project Benefits for Stoneham & Woburn • Provides the most cost-effective solution to meet customer needs while improving power system reliability and quality. • Delivers substantially greater levels of power-import capability, which will enable access to lower-cost and clea

  5. Slide 5: Project Route and Manhole Locations through Stoneham

    Woburn to Wakefield Line Project Project Route and Manhole Locations through Stoneham The Woburn to Wakefield Line Project includes 16 manhole locations on Eversource’s portion of the project route. Six manholes will be located in the Town of Stoneham and are scheduled to be installed during the 202

  6. Slide 6: Project Route and Manhole Locations through Stoneham

    Woburn to Wakefield Line Project Project Route and Manhole Locations through Stoneham Streets Total Length Montvale Avenue 3500 feet Main Street 1700 feet Elm Street 4500 feet Stoneham Manhole Locations Total project route 9700 feet Manhole 11 Montvale Avenue miles through (1.9 miles) (between Wobur

  7. Slide 7: Stoneham Construction Hours

    Woburn to Wakefield Line Project Stoneham Construction Hours • The safety of residents, pedestrians, motorist, police details and our crews is our top priority. • This project requires our crews to work in the street for each phase of the project including vault installation, trench digging/cable pu

  8. Slide 8: Project Route and Manhole Locations through Woburn

    Woburn to Wakefield Line Project Project Route and Manhole Locations through Woburn The Woburn to Wakefield Line Project includes 16 manhole locations on Eversource’s portion of the project route. Four manholes will be located in the City of Woburn and are scheduled to be installed during the 2020 c

  9. Slide 9: Construction Locations and Work Hours

    Woburn to Wakefield Line Project Woburn Construction Locations and Work Hours Streets Total Woburn Construction Hours Length The hours for construction in Woburn are 7 a.m. to 5 p.m., Lake Avenue 1400 feet Monday through Friday, on Lake Avenue, Pickering Street, Border Street and Washington Street.

  10. Slide 10: Work Zone Construction Sequence - "The Train"

    Woburn to Wakefield Line Project Work Zone Construction Sequence - “The Train” Our work crews will be working in local streets for each phase of the project: vault installation, trench digging, cable installation, cable pulling/cable splicing, and restoration. Typical Construction Sequence 1. Saw cu

  11. Slide 11: Typical Underground Construction

    Woburn to Wakefield Line Project Typical Underground Construction

  12. Slide 12: Stoneham & Woburn Community Outreach

    Woburn to Wakefield Line Project Stoneham & Woburn Community Outreach Eversource has developed a comprehensive community outreach plan for Stoneham & Woburn. Below is a list of typical tools that will be used to communicate with stakeholders to keep them informed of project construction activities.

  13. Slide 13: Contact Information

    Contact Information Project Manager Mike Hager Email: michael.hager@eversource.com Siting & Construction Services Nicole Bowden Email: nicole.bowden@eversource.com Sean Shortell Email: sean.shortell@eversource.com For the Public: Project Hotline: 1-800-793-2202 Project Website: https://www.eversourc