Slide 1: Developing Container Capacity: Progress, Issues and the Way Forward
Developing Container Capacity: Progress, Issues and the Way Forward CRISIL Infrastructure Advisory

Slide 2: Overview of the Presentation
Overview of the Presentation • Container ports in India- Present capacity • Container projects proposed/under development • Status of upcoming projects • How much additional capacity is expected? • Container traffic under alternate scenarios. • Issues influencing project development. • Way forward.

Slide 3: Hinterland classification and key container ports in the region
Hinterland classification and key container ports in the region Ports handling containers Western Eastern Southern Ports Ports Ports Chennai, Kolkata, Tuticoin, JNPT, Haldia, Cochin, New Major Ports Mumbai, Paradip, Mangalore, Kandla Vizag Goa Mundra, North/West Private Ports Pipavav East Proposed H

Slide 4: Present container handling capacity-2009
Present container handling capacity-2009 Total 000’ TEUs – 10350 Upper West Coast 3500 Kandla, Mundhra, Upper East Coast Pipavav 350 Paradip, Haldia, Kolkata Central West Coast 4200 300 Mumbai, JNPT Central East Coast Vizag 1400 Lower West Coast 600 Lower East Coast New Mangalore, Cochin, Chennai, T

Slide 5: Container handling projects envisaged upto 2020
Container handling projects envisaged upto 2020 • Upper West Coast- New container terminals at Hazira and Jamnagar. • Central West Coast-Offshore terminal at Mumbai port, fourth container terminal at JNPT, and new developments at Rewas and Dighi. • Lower West Coast-Container terminals at Vallarpadam

Slide 6: Projected container handling capacity-2020
Projected container handling capacity-2020 Total 000’ TEUs – 33150 Upper West Coast Kandla, Mundhra, 6050 Upper East Coast Pipavav, Hazira and Jamnagar 2950 Paradip, Haldia, Kolkata, Dhamra, Kulpi Central West Coast 12300 1250 Mumbai, JNPT, Rewas and Dighi Central East Coast Vizag, Gangavaram, and K

Slide 7: Status of various projects
Status of various projects • Mundhra 2nd container terminal: Operational since August 2008. This terminal is capable of handling about one and a quarter million twenty-feet container per annum and will mainly cater to the needs of the northern hinterland of India. Some of the salient features of the

Slide 8: Status of various projects (Contd)
Status of various projects ( Contd) • Vallarpadam Container Terminal: The first phase of the new Terminal will have a capacity of 1 million TEUs which consists of 600 metres of quay, six Super Post Panamax Quay Cranes and an on-dock railhead serviced by rail- mounted gantry cranes. Construction of a

Slide 9: Traffic handled at major ports
Traffic handled at major ports Traffic handled at major ports • Traffic handled at major ports has increased at a CAGR of 7.32% between 600000 500000 1994-95 to 2008-09. 400000 300000 Traffic in 000 tons 200000 • Traffic handled by major ports in FY 2008- 100000 09 has grown at 2.12% over FY 2007-08

Slide 10: Impact on container cargo
Impact on container cargo Total containerized traffic ( mn teus) 8 7 6 5 4 3 2 1 0 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 Containerized traffic at major ports has increased at a CAGR of 11.92% between 2003-04 and 2008-09, with an increase of 2.02% in 2008-09 over 2007-08 10.

Slide 11: Container traffic under different scenarios
Container traffic under different scenarios

Slide 12: Approach adopted for the assessment
Approach adopted for the assessment General approach • The total container traffic for each port would consist of: – Its share in the container traffic to/ from the primary hinterland – Its share in the container traffic to/ from the secondary hinterland – Non-containerized export-import general car

Slide 13: Assumptions underlying scenario of container traffic- Scenario A
Assumptions underlying scenario of container traffic- Scenario A • Horizon for projection: 2007-2039 • GDP Growth: 8.00% p.a from 2008-2020, 7.5% p.a from 2021-25 and declining by 0.5% every four years thereafter upto 2039. • Container penetration level: increasing to 75% by 2014 and assumed at thos

Slide 14: Container traffic- Scenario A
Container traffic- Scenario A Projected general cargo and containerized tonnage 1600000 1400000 1200000 1000000 Indian General cargo ('000 tonnes) 800000 Containerised Tonnage ('000 600000 tonnes) 400000 200000 0 06 09 12 15 18 FY 1 24 27 30 33 36 39 2 FY FY FY FY FY FY FY FY FY FY FY Total India's

Slide 15: Container Traffic-Revised scenario B
Container Traffic-Revised scenario B • Horizon for projection: 2007-2039 • GDP Growth: 5.7% in 2009-10 , 7% and 7.8% in 2010-11 and 2011-12 resp ( CCER), 6.4% p.a until 2021-22 (post 1991 average) and 5.5% p.a thereafter upto 2038-39 (post 1975 average). • Container penetration level: increasing to

Slide 16: Container Traffic-Revised scenario B
Container Traffic-Revised scenario B Projected general and containerized cargo 1200000.00 1000000.00 800000.00 Indian General cargo ('000 tonnes) 600000.00 Containerised Tonnage ('000 400000.00 tonnes) 200000.00 0.00 FY 6 FY 9 FY 2 FY 5 18 FY 1 FY 4 FY 7 FY 0 FY 3 FY 6 39 0 0 1 1 2 2 2 3 3 3 FY FY P

Slide 17: Projected container capacity -2020
Projected container capacity -2020 Port Group FY 09 FY 10 FY 11 FY 12 FY 13 FY 14 FY 15 FY 16 FY 17 FY 18 FY 19 FY 20 Upper West Coast 3500 3600 3950 4950 5700 5700 6050 6050 6050 6050 6050 6050 Central West Coast 4200 4200 4200 5500 6600 7350 8100 10200 10350 11050 11800 12300 Lower West Coast 600

Slide 18: Scenarios of container traffic versus capacity addition proposed
Scenarios of container traffic versus capacity addition proposed. Base case scenario FY 2012 FY 2015 FY 2020 • Base case scenario: Assuming that only Container capacity ( mn projects under implementation or at the teus) 13.95 19.65 23.9 bidding stage come up. Moderate scenario FY 2012 FY 2015 FY 202

Slide 19: Container projects- happenings
Container projects- happenings • PSA which was to have set up the container terminal at Hazira has walked out of the deal citing commercial terms that render the project unviable. As per the terms, the waterfront royalty payable to Gujarat on a per container basis by the terminal operator was to inc

Slide 20: Vizhinjam- Happenings
Vizhinjam- Happenings • The tendering process began in 2003 for the project on a build-own-operate-and- transfer basis for 30 years and was once terminated owing to non-receipt of bids. • In 2005 the tender was awarded to a consortium in which Zoom Developers was a member subject to the Government o

Slide 21: Project Development Process
Project Development Process Inception Feasibility Project Preparation Period Procurement Development Delivery Project Term Exit 21.

Slide 22: Bottlenecks at Project Inception Stage
Bottlenecks at Project Inception Stage Inception ÂQuite often many projects lack sound economic rationales. Projects are often based on political statements thus Feasibility impacting scale and scope ÂMany departments have a tendency to list projects for PPP, Procurement when departmental funds are

Slide 23: Bottlenecks at Project Feasibility Stage
Bottlenecks at Project Feasibility Stage Inception ÂThe feasibility studies are not conducted properly (leading to lower user demand as compared to projected demand, Feasibility bankability, etc) ÂMany projects suffer from improper planning and lack of Procurement linkages (like lack of road and rai

Slide 24: Inadequate Feasibility Studies
Inadequate Feasibility Studies Lack of Budgets Inadequate feasibility studies Number of projects/state Budget constraints at state level for 200-400 Infrastructure projects Average Project Cost Reduction in scope of work for feasibility Rs 200-400 crores studies Expenses for feasibility & procuremen

Slide 25: Examples of Bottlenecks at Project Feasibility Stage
Examples of Bottlenecks at Project Feasibility Stage Project Stage Issue Critical Issues constraining Project Implementation Project Delay in Coal Berth at Tuticorin Port: Expected date of Feasibility preparation of commencement of work June 2006, but feasibility report feasibility report received b

Slide 26: Bottlenecks at Project Procurement Stage
Bottlenecks at Project Procurement Stage ÂThere is lack of marketing leading to low awareness of the Inception projects initiated by Government Feasibility ÂIn many cases improper prequalification process leads to mixed bag of strong and weak qualifiers which lead to Procurement speculative bids ÂDi

Slide 27: Examples of Bottlenecks at Project Procurement Stage
Examples of Bottlenecks at Project Procurement Stage Project Stage Issue Critical Issues constraining Project Implementation Project Delay in Container Terminal at Ennore Port: Expected date of Procurement finalization of commencement of work delayed by more than one year bid documents due to delay

Slide 28: Bottlenecks at Project Development, Delivery and Exit Stage
Bottlenecks at Project Development, Delivery and Exit Stage ÂThe multiple interface for clearances and approvals from Inception ministries and departments at centre, state and local levels results in project delays. The concept of single window Feasibility clearance needs to be introduced for all st

Slide 29: Examples of Bottlenecks at Project Development Stage
Examples of Bottlenecks at Project Development Stage Project Stage Issue Critical Issues constraining Project Implementation Project Environmental Dhamra Port in Orissa: Project was delayed by more than Development clearance 4 years due to environmental issues – construction was to start by the end

Slide 30: Way Forward
Way Forward • Projects need to have a sound economic rationale with the feasibility well established. • Feasibility to be accorded due importance with consultant selection based on appropriate weightage to technical and financial bids- addressed under the new MCA and selection process with rigorous

Slide 31: Thank You
". INFRASTRUCTURE ADVISORY Thank You bd ". INFRASTRUCTURE ADVISORY
Source: Internet Archive copy of crisil.com
More decks from CRISIL Limited
Q3 2026 Earnings Presentation23 slides · Oct 23, 2026
Q2 2026 Earnings Presentation23 slides · Jul 21, 2026
Q1 FY2026 Earnings Presentation29 slides · Apr 17, 2026
FY2025 Earnings Presentation23 slides · Feb 13, 2026
Q3 2025 Earnings Presentation24 slides · Oct 20, 2025
Q2 2025 Earnings Presentation24 slides · Jul 22, 2025